Countries › Bolivia › Guide › 3. Investing › Environmental licenses and prior consultation in Bolivia: categories, deadlines and who must be consulted
Environmental licenses and prior consultation in Bolivia: categories, deadlines and who must be consulted
Last verified: 2026-11-15 · Status: Stable
Every project needs an environmental category before investment starts. Category 1 and 2 projects need an impact study and a license, category 3 needs a mitigation plan, and category 4 only registers. Oil, gas and new mining contracts also need State run consultation with affected peoples. Mining consultation has a four month limit, and exploration is outside it.
Key facts
| Authority term for license, category 1 and 2, with sector body | 20 business daysD.S. 3549 art. 4, as of 2026-11-11 · in force |
|---|---|
| Authority term for license, category 3, with sector body | 10 business daysD.S. 3549 art. 4, as of 2026-11-11 · in force |
| Maximum mining consultation period | 4 monthsLey 535 art. 212, as of 2026-11-11 · in force |
| Maximum mining consultation meetings | 3 meetingsLey 535 art. 211, as of 2026-11-11 · in force |
The rule
Cost to do it: We found no official fee table. Budget for the RENCA consultant, whose price is set by contract.D.S. 3549, replacing RPCA art. 17, Art. 4, 2018-05-02 official text · verified 2026-11-11
| Category and setting | First reviewer | Authority | Instrument |
|---|---|---|---|
| 1 and 2, sector body | Sector body, 15 business days | 20 business days | EEIA |
| 1 and 2, protected area | SERNAP 15; sector body by day 18 | 5 business days | EEIA |
| 1 and 2, no sector body | None | 20 business days | EEIA |
| 3, sector body | Sector body, 10 business days | 10 business days | PPM PASA |
| 3, no sector body | None | 10 business days | PPM PASA |
| 4 | None | Registration of the form | Annex A form |
Review clocks, best case with no observations
Worked example
- A category 2 plant with a sector body has a best case of about 35 business days of review after filing (15 plus 20), before study preparation, consultation and any observations.
- A mining applicant in a free area adds up to four months for consultation, and new mining contracts then need Assembly approval, which has 90 days to decide (Ley 535 art. 132).
Step by step
- Check the Annex A list and hire a RENCA consultant.
- File the form and confirm the category.
- Run public consultation inside the study.
- File with the correct sector body or SERNAP.
- Add the State consultation stage for oil, gas or mining.
- Report start within 12 months and file monitoring reports.
Common traps
- Deadlines run only on a complete file and reset on observations.
- The State runs consultation, so the timing is not fully yours, even when you pay.
- Consultation agreements bind you. Budget for them.
- Protected areas add SERNAP and possibly municipal review.
- Departmental projects go to the departmental authority.
- The hydrocarbon regulation of consultation, D.S. 29033, was not reachable, so read it with counsel.
Sources
- Ley 1333 (Ministry SNIA copy)
- D.S. 3549 (Ministry SNIA compendium copy)
- D.S. 5675 (Gaceta Oficial consultation text, ASFI copy)
- Constitución Política del Estado (BCB copy)
- Ley 3058 (ANH copy, also recites Ley 1257)
- Ley 535 (AJAM copy with amendment notes)
Related pages
- investing/restricted-activities-and-ownership-limits
- start/who-regulates-what
- /country/bolivia/
- /calendar/
- Live dashboard
Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.