Environmental disputes in Chile: Environmental Courts, challenges to environmental approvals, SMA fines and environmental damage claims
Last verified: 2026-10-26 · Status: Changing
Three specialised Environmental Courts, in Antofagasta, Santiago and Valdivia, hear challenges to environmental approvals, to SMA sanctions and to environmental regulations, as well as claims to repair environmental damage. Their final judgments can only be reviewed by the Corte Suprema through cassation (Ley Nº 20.600 art. 5, 17 and 26). A project owner unhappy with its environmental approval (RCA) has 30 days to file an administrative claim, with the Executive Director for a DIA or the Committee of Ministers for an EIA, and then 30 days to go to the Environmental Court. Citizens whose observations were not properly addressed have the same route (Ley Nº 19.300 art. 20 and 29). SMA fines reach 10,000 UTA (about CLP 8,658 million or US$8.8 million in October 2026) for the most serious infringements. They can be challenged within 15 business days, and paying within 5 business days without challenging cuts the fine by 25 percent (Ley Nº 20.417 art. 2, LOSMA art. 39 and 56). A reform bill to change the RCA claim system is pending in Congress.
USD figures use the Central Bank exchange rate of CLP 986.58 per US dollar published in the Diario Oficial for 23 October 2026 (CVE 2891564). UTM and UTA amounts use the October 2026 values published by the SII (UTM CLP 72,151; UTA CLP 865,812). Conversions are for orientation only.
Key facts
| Number of Environmental Courts | 3 Ley Nº 20.600 art. 5, as of 2026-10-26 · in force |
|---|---|
| Deadline for a project owner to file an administrative claim against an environmental approval (RCA) | 30 daysLey Nº 19.300 art. 20, as of 2026-10-26 · in force |
| Deadline to take the Committee of Ministers or Executive Director decision to the Environmental Court | 30 daysLey Nº 19.300 art. 20, as of 2026-10-26 · in force |
| Public observation period for an environmental impact study (EIA) | 60 daysLey Nº 19.300 art. 29, as of 2026-10-26 · in force |
| Deadline to challenge an SMA resolution before the Environmental Court | 15 business daysLOSMA (Ley Nº 20.417 art. 2) art. 56, as of 2026-10-26 · in force |
| Maximum SMA fine for very serious infringements | 10000 UTALOSMA (Ley Nº 20.417 art. 2) art. 39, as of 2026-10-26 · in force |
| Reduction for paying an SMA fine within 5 business days without challenge | 25 %LOSMA (Ley Nº 20.417 art. 2) art. 56, as of 2026-10-26 · in force |
| Limitation period for SMA infringements | 3 yearsLOSMA (Ley Nº 20.417 art. 2) art. 37, as of 2026-10-26 · in force |
| Limitation of environmental damage actions from when the damage becomes evident | 5 yearsLey Nº 19.300 art. 63, as of 2026-10-26 · in force |
| Environmental institutions reform bill changing RCA claims | Boletín Nº 16.552-12, second reading in the Chamber of Deputies Boletín Nº 16.552-12, as of 2026-10-26 · pending |
The rule
Cost to do it: No court fee was identified in this review. A private applicant for interim measures may be required to give security (art. 24).
Example: A mining company in Antofagasta challenging an SMA sanction files with the First Environmental Court, because that court has jurisdiction where the infringement originated (art. 17 Nº 3). / For a US$5,000,000 project in the Biobío region, project approval disputes go to the Third Environmental Court in Valdivia, where the project was assessed (art. 17 Nº 5).Ley Nº 20.600 creating the Environmental Courts (Ministerio del Medio Ambiente), Diario Oficial 28 June 2012, Art. 1, art. 5, art. 17, art. 18, art. 24 and art. 26, 2012-06-28 official text · verified 2026-10-26
Cost to do it: No filing fee for the administrative claim. The Committee of Ministers can commission independent technical reports (art. 20).
Example: A CLP 4,932,900,000 solar plant receives an RCA with conditions it considers unlawful. The owner files a claim with the Executive Director (DIA) or the Committee of Ministers (EIA) within 30 days, and then has 30 days to go to the Environmental Court. / The same plant is a US$5,000,000 investment. Community claims under art. 29 do not suspend the approval, so construction can proceed while they are decided, at the owner's risk.Ley Nº 19.300 on the general bases of the environment, Diario Oficial 9 March 1994, as amended, Art. 20 and art. 29, 1994-03-09 official text · verified 2026-10-26
Cost to do it: Maximum fines at the October 2026 UTA of CLP 865,812: very serious 10,000 UTA (CLP 8,658,120,000, about US$8,775,892); serious 5,000 UTA (CLP 4,329,060,000, about US$4,387,946); minor 1,000 UTA (CLP 865,812,000, about US$877,589).
Example: The SMA fines a plant 100 UTA, CLP 86,581,200 at the October 2026 UTA. If the company pays within 5 business days without challenging it, it pays 75 UTA, CLP 64,935,900. / The same fine is about US$87,759, or about US$65,819 with the early payment discount. The company has to choose between the discount and a court challenge within the first 5 business days.Ley Orgánica de la Superintendencia del Medio Ambiente, contained in art. 2 of Ley Nº 20.417 (Ministerio Secretaría General de la Presidencia), Diario Oficial 26 January 2010, LOSMA art. 36, art. 37, art. 38, art. 39 and art. 56, 2010-01-26 official text · verified 2026-10-26
Cost to do it: Repair costs are set by the court or by the SMA approved repair plan; the statute sets no figure.
Example: A tailings leak becomes evident on 1 August 2026. The municipality, affected neighbours or the Consejo de Defensa del Estado can sue for repair until 1 August 2031. A repair plan approved by the SMA and properly carried out bars the repair action (art. 53). / For a project with US$5,000,000 in assets, negotiating an SMA approved repair plan early can close off a court repair action.Ley Nº 19.300 on the general bases of the environment; Ley Nº 20.600, Ley Nº 19.300 art. 51, art. 53 and art. 63; Ley Nº 20.600 art. 17 Nº 2 and art. 18 Nº 2, 1994-03-09 official text · verified 2026-10-26
Cost to do it: None until enacted.
Example: A project expecting its RCA in 2027 should plan for the current 30 day claim terms, and track the bill in case the terms change before then. / For a US$5,000,000 project, the reform could change who hears RCA claims and the deadlines that apply; the final text is not yet known.Bill boletín Nº 16.552-12 (Senate legislative tracking), Not yet law, 2024-01-10 official text · verified 2026-10-26
| Gravity | Possible sanctions | Maximum fine (UTA) | Maximum fine (CLP) | Maximum fine (USD, approx.) |
|---|---|---|---|---|
| Very serious | Revocation of RCA, closure or fine | 10,000 | 8,658,120,000 | 8,775,892 |
| Serious | Revocation of RCA, closure or fine | 5,000 | 4,329,060,000 | 4,387,946 |
| Minor | Written warning or fine from 1 UTA | 1,000 | 865,812,000 | 877,589 |
SMA sanctions by gravity (LOSMA art. 36 and 39), with October 2026 values (UTA CLP 865,812; CLP 986.58 per US dollar).
Worked example
- A US developer obtains an RCA for a CLP 4,932,900,000 (about US$5,000,000) wind farm in the Maule region, after an EIA with conditions it considers excessive.
- It files a claim with the Committee of Ministers within 30 days. The Committee has 60 days to decide (Ley Nº 19.300 art. 20).
- The Committee confirms the conditions. The developer files with the Second Environmental Court in Santiago within 30 days (art. 20; Ley Nº 20.600 art. 17 Nº 5).
- The Court's final judgment can only be taken to the Corte Suprema by cassation (Ley Nº 20.600 art. 26).
Step by step
- 1. On notification of an RCA, diarise 30 days for the administrative claim (Ley Nº 19.300 art. 20).
- 2. During an EIA, track the 60 day observation period and make sure the SEA's response to every observation is on record, to limit art. 29 claims.
- 3. On notification of an SMA fine, decide within 5 business days whether to pay with the 25 percent discount or challenge it within 15 business days (LOSMA art. 56).
- 4. Keep compliance evidence for at least three years, the SMA limitation period (LOSMA art. 37).
- 5. If damage occurs, consider an SMA approved repair plan to bar a court repair action (Ley Nº 19.300 art. 53).
- 6. Track boletín Nº 16.552-12 for changes to the RCA claim system.
Common traps
- The 30 day RCA claim is open only to the project owner, plus citizens whose observations were ignored; other parties may need to seek invalidation, which has its own route (Ley Nº 19.300 art. 20 and 29; Ley Nº 20.600 art. 17 Nº 8).
- Community claims do not suspend the RCA, but a later court ruling can annul it, so building during the challenge carries risk (Ley Nº 19.300 art. 29).
- The 25 percent discount is lost if the fine is challenged or paid late (LOSMA art. 56).
- Environmental damage limitation runs from when the damage becomes evident, not from the act, so exposure can surface long after operations end (Ley Nº 19.300 art. 63).
- Final Environmental Court judgments can only be reviewed by cassation, with limited grounds; there is no ordinary appeal (Ley Nº 20.600 art. 26).
Sources
- Ley Nº 20.600 creating the Environmental Courts (Ley Chile)
- Ley Nº 19.300 on the general bases of the environment (Ley Chile)
- Ley Nº 20.417, art. 2 Ley Orgánica de la Superintendencia del Medio Ambiente (Ley Chile)
- Senate legislative tracking, boletín Nº 16.552-12
- SII, UTM and UTA values for 2026
- Diario Oficial, Central Bank exchange rates for 23 October 2026, CVE 2891564
Related pages
- disputes/disputes-with-the-state
- disputes/courts-arbitration-and-enforcement
- regulation/regulatory-compliance-essentials
- sectors/mining-energy-and-key-sectors
- /country/chile/
- /calendar/
- Live dashboard
Related: Chile country profile · live dashboard · central bank and release calendar · our posts on X