A bidder unhappy with a procurement decision in Haiti, or with the contracting authority's silence, can take it to the Comité de règlement des différends (CRD) set up within the Commission Nationale des Marchés Publics (CNMP), a non judicial body that seeks an amicable solution or gives a reasoned decision on award and bidder choice disputes. Under the CNMP procedure manual a losing bidder has 9 calendar days from notice of the award to file, and the contract letter is only issued the day after that window closes; filing does not suspend the procedure. CRD decisions can be appealed to the CSCCA, and bidders who cheat face exclusion from public contracts for 6 months to 5 years imposed by the CNMP.

USD figures use HTG 130.7542 per US dollar, the BRH reference rate (taux de référence) for 8 November 2026 shown on the BRH home page on the verification date. Conversions are for orientation only.

Key facts

Procurement complaint bodyComité de règlement des différends at the CNMP (non judicial); appeal to the CSCCA textLoi du 10 juin 2009 art. 95 to 95-5, as of 2026-11-09 · in force
Time for a losing bidder to file a complaint9 calendar daysCNMP procedure manual section 3.8, as of 2026-11-09 · in force
Does a complaint suspend the procurementNo textLoi du 10 juin 2009 art. 95-5, as of 2026-11-09 · in force
Maximum exclusion from public contracts for fraud5 yearsLoi du 10 juin 2009 art. 91.2, as of 2026-11-09 · in force
Time to notify all bidders of the award decision24 hoursCNMP procedure manual section 3.7, as of 2026-11-09 · in force
Rate used for USD conversions on this page130.7542 HTG per USDBRH reference rate 8 Nov 2026, as of 2026-11-08 · in force

The rule

1. If the contracting authority gives no decision, or a decision the bidder does not accept, the bidder may refer the matter to the Comité de règlement des différends, a non judicial recourse body set up within the CNMP. The committee seeks fair terms for an amicable solution of disputes over the award and performance of public contracts, or gives a reasoned decision on disputes over the award procedure or the choice of the winning bidder. It is made up of a CNMP representative, two other public administration representatives (one for the Secretary General of the Prime Minister's office), a retired judge or a lawyer experienced in such disputes, and a representative chosen by private sector associations; the CNMP may add experts.
Cost to do it: The law sets no filing fee for the committee; prepare a written complaint with the bid documents and the award notice.
Example: A losing bidder on a HTG 65,377,100 road works tender asks the committee to review the evaluation of its bid. / HTG 65,377,100 is US$500,000 at the BRH reference rate.Loi No. CL 06 2009-009 fixant les règles générales relatives aux marchés publics et aux conventions de concession d'ouvrage de service public (Le Moniteur No. 60, 12 June 2009, reproduced in No. 78, 28 July 2009), Art. 2 (11), 95, 95-1, 95-2 and 95-3, 2009-06-10 official text · verified 2026-11-09
2. Proceedings before the committee must be fast and respect the right to be heard and a fair process; a party may ask for the removal of a member who has a conflict of interest. The committee's decisions can be challenged before the Cour Supérieure des Comptes et du Contentieux Administratif. A referral to the committee does not suspend the procurement. The committee's powers, membership terms, filing methods and deadlines are to be set by the implementing arrêté under art. 98.
Cost to do it: An appeal to the CSCCA carries the HTG 100 stamp per sheet of the 2026 Code Fiscal (art. 218).
Example: A bidder that loses before the committee on a HTG 26,150,840 supply contract files an appeal with the CSCCA. / HTG 26,150,840 is US$200,000 at the BRH reference rate.Loi No. CL 06 2009-009 fixant les règles générales relatives aux marchés publics et aux conventions de concession d'ouvrage de service public (Le Moniteur No. 60, 12 June 2009, reproduced in No. 78, 28 July 2009), Art. 95-4, 95-5 and 98, 2009-06-10 official text · verified 2026-11-09
3. After the award decision, the evaluation committee notifies all bidders in writing within 24 hours; unsuccessful bidders are told the winner, the award price and the complaint procedure. An unsuccessful bidder that wishes to contest the award may file a complaint within 9 calendar days from notice of the award, with the CRD at the CNMP, and may first ask the contracting authority for the reasons its bid was rejected. The contract letter is prepared the day after the complaint window expires, and the winner then has 2 days to return it signed with its performance guarantee.
Cost to do it: No fee is listed in the manual; the winner must post its performance guarantee within 12 calendar days of the award notice.
Example: Notified on a Monday that it lost a HTG 13,075,420 supply tender, a bidder must file with the CRD by the Wednesday of the following week. / HTG 13,075,420 is US$100,000 at the BRH reference rate.CNMP, Manuel des procédures, appel d'offres allégé pour marchés de fournitures (version of September 2013, published on the CNMP site), Sections 3.7, 3.8 and 3.9, 2013-09-01 official text · verified 2026-11-09
4. The CNMP issues opinions in the amicable settlement of disputes arising from the award or performance of public contracts and public service concessions through the dispute committee, can impose administrative sanctions for irregularities, publishes every quarter the list of firms barred from public contracts, and has approved contracts registered with the CSCCA by the approving authority.
Cost to do it: No fee set by the law.
Example: A concession holder in a dispute over a HTG 653,771,000 service concession asks for the CNMP committee's opinion before going to the CSCCA. / HTG 653,771,000 is US$5,000,000 at the BRH reference rate.Loi No. CL 06 2009-009 fixant les règles générales relatives aux marchés publics et aux conventions de concession d'ouvrage de service public (Le Moniteur No. 60, 12 June 2009, reproduced in No. 78, 28 July 2009), Art. 10 (10), (14), (15) and (16), 2009-06-10 official text · verified 2026-11-09
5. The CNMP imposes administrative sanctions on bidders and contract holders, without prejudice to civil and criminal penalties. Deliberate inaccuracies in bid documents, false information likely to affect the outcome, or attempts to influence the evaluation or award lead to exclusion from public contracts for 6 months to 2 years. False or inflated professional or financial guarantees, bid rigging, overbilling or false invoicing, and any other fraudulent manoeuvre lead to exclusion for more than 2 and up to 5 years; when exclusion hits during performance, the authority replaces the contract holder.
Cost to do it: Exclusion costs the excluded firm all public work for the period, and the extra cost of a replacement contract may be charged to it.
Example: A contractor found to have inflated its bank guarantee on a HTG 32,688,550 contract can be excluded from public procurement for up to 5 years. / HTG 32,688,550 is US$250,000 at the BRH reference rate.Loi No. CL 06 2009-009 fixant les règles générales relatives aux marchés publics et aux conventions de concession d'ouvrage de service public (Le Moniteur No. 60, 12 June 2009, reproduced in No. 78, 28 July 2009), Art. 91, 91.1, 91.2 and 91.3, 2009-06-10 official text · verified 2026-11-09
StepTime limitSource
Award decision notified to all biddersWithin 24 hoursManual 3.7
Losing bidder asks the authority for reasonsBefore the end of the complaint windowManual 3.8
Complaint to the CRD at the CNMP9 calendar days from the award noticeManual 3.8; Law art. 95
Contract letter preparedDay after the window expiresManual 3.9
Winner returns signed letter and guarantee2 daysManual 3.9
Appeal against the CRD decisionTo the CSCCA; not suspensiveLaw art. 95-5

Bid protest timeline (CNMP procedure manual, goods tenders)

MisconductExclusionArticle
Deliberate inaccuracies or false statements in a bid; trying to influence evaluation or award6 months to 2 years91.1
False or inflated guarantees; bid rigging; overbilling or false invoicing; other fraudMore than 2 and up to 5 years91.2

CNMP exclusion sanctions

Worked example

  • Bid protest: a foreign equipment supplier loses a US$100,000 (HTG 13,075,420) tender. On receiving the award notice it asks the contracting authority for the reasons, then files a complaint with the CRD within 9 calendar days. The procedure is not suspended, so it asks for a quick hearing; if the committee rejects the complaint, it can appeal to the CSCCA, paying the HTG 100 stamp on each sheet of its petition.

Step by step

  1. Read the tender documents for the complaint procedure and any timetable that differs from the manual.
  2. On notice of the award, diarize 9 calendar days and ask the contracting authority in writing for the reasons for rejection.
  3. File a written complaint with the CRD at the CNMP, with the bid, the notice and the specific irregularity.
  4. Ask the committee to act quickly, since the complaint does not stop the procedure.
  5. If the decision goes against you, appeal to the CSCCA; for disputes during performance, use the contract clause and the CSCCA route.

Common traps

  • The 9 day window comes from the CNMP procedure manual for goods tenders; the arrêté that the law requires to set the committee's deadlines was not found online, so check the tender documents.
  • A complaint does not suspend the award or signature, so a late complaint may leave only damages.
  • Excluded firms are published every quarter by the CNMP, and exclusion during performance means the contract passes to another firm.
  • Contracts awarded under an emergency regime may follow different rules; confirm the procedure that applied to the tender.

Sources

Related pages

Related: Haiti country profile · live dashboard · central bank and release calendar · our posts on X