Environmental impact assessment and liability in Haiti: the non objection, the BNEE procedure, pollution rules and levies
Last verified: 2026-11-09 · Status: Stable
Under the environment decree of 12 October 2005, any project or activity likely to affect the environment needs an environmental assessment and the Ministry of the Environment's non objection before it goes ahead, and mining and quarry concessions are conditional on it. The ministry's Bureau national des évaluations environnementales (BNEE), set up in the 2020 organic decree, runs the procedure, validates studies and organises public hearings at the promoter's cost. Polluters face criminal and civil liability with restoration costs and possible closure, and the 2026 Code Fiscal adds a 0.5 percent pollution levy and a 1 percent wood fuel tax on prior year turnover.
USD figures use HTG 130.7542 per US dollar, the reference rate (taux de référence) published by the Banque de la République d'Haïti for 8 November 2026. Amounts fixed in gourdes keep their gourde value, so their dollar value moves with the rate. Conversions are for orientation only.
Key facts
| Environmental assessment and ministry non objection required for projects likely to affect the environment | Yes textDécret du 12 octobre 2005, art. 56 to 59, as of 2026-11-09 · in force |
|---|---|
| Environmental assessment authority | Ministère de l'Environnement, Bureau national des évaluations environnementales (BNEE) textDécret du 5 août 2020, art. 73 and 74, as of 2026-11-09 · in force |
| Special duty on polluting businesses, share of prior year turnover | 0.5 %Code Fiscal 2026, art. 172, as of 2026-11-09 · in force |
| Annual tax on businesses using wood as fuel, share of prior year turnover | 1 %Code Fiscal 2026, art. 173, as of 2026-11-09 · in force |
| Import of hazardous waste banned | Yes textDécret du 12 octobre 2005, art. 143, as of 2026-11-09 · in force |
| Legal persons criminally and civilly liable for environmental offences | Yes textDécret du 12 octobre 2005, art. 154 and 155, as of 2026-11-09 · in force |
| Deadline for the ad hoc committee memorandum after public hearings | 30 daysMinistère de l'Environnement, CGES TPR II (October 2024), national procedure step 5, as of 2026-11-09 · in force |
The rule
Cost to do it: No official fee schedule for the non objection or BNEE review was found. The promoter bears the cost of the study itself, of the public hearings and of carrying out the environmental and social management plan.Ministère de l'Environnement, Cadre de gestion environnementale et sociale (CGES), Projet Territoires productifs résilients II, version October 2024, Section on the national environmental assessment procedure (pp. 120 to 122), 2024-10 official text · verified 2026-11-09
Cost to do it: 0.5 percent (pollution duty) or 1 percent (wood fuel tax) of prior year turnover, paid once a year in October.
Example: Industrial plant with HTG 80,000,000 turnover in fiscal 2025 to 2026: pollution duty HTG 400,000 due by 31 October 2026. / HTG 400,000 is about US$3,059; on US$1,000,000 of turnover the duty is US$5,000.Code Fiscal, Le Moniteur Spécial N° 48-A, 30 September 2026, Art. 172 and 173, 2026-09-30 official text · verified 2026-11-09
| Step | Who acts | What happens | Legal basis |
|---|---|---|---|
| 1. Project notice | Promoter, BNEE, sector UTES | BNEE decides whether the project is subject to assessment and its depth: impact notice, simplified study or detailed study | Decree 2005 art. 21, 56 to 58; decree 2020 art. 74 |
| 2. Terms of reference | Promoter drafts, BNEE validates | Scope and content of the study under the 2015 methodological guide | Decree 2020 art. 74 (2) |
| 3. Study | Promoter, at its cost | Environmental and social impact study with management plan | Decree 2005 art. 56 |
| 4. Admissibility | BNEE expert group | Site visit and evaluation report | Decree 2020 art. 74 (4) |
| 5. Public hearings | BNEE organises, promoter pays | Ad hoc committee memorandum to the ministry within thirty days | Decree 2005 art. 58 and 69; decree 2020 art. 74 (9) |
| 6. Decision | Ministry of the Environment | Non objection and certificate of environmental compliance | Decree 2005 art. 59 |
| 7. Monitoring | Promoter reports, BNEE and ministry check | Management plan acts as binding specifications; audits | Decree 2005 art. 61; decree 2020 art. 74 (7) and (8) |
| 8. Closure | Promoter | Closing environmental audit | Decree 2005 art. 56 |
The national environmental assessment procedure as described by the Ministry of the Environment (CGES TPR II, October 2024), with the legal basis in the 2005 and 2020 decrees.
| Levy | Who pays | Rate or amount | When | Article |
|---|---|---|---|---|
| Special duty on polluting businesses | Commercial and industrial installations (with a pharmaceutical and nursery exception), waste disposal sites, incinerators, air emitters | 0.5% of prior year turnover | 1 to 31 October | 172 |
| Wood fuel tax | Businesses using wood as fuel | 1% of prior year turnover | 1 to 31 October | 173 |
Environmental levies in the 2026 Code Fiscal (Le Moniteur Spécial N° 48-A, 30 September 2026).
Worked example
- A foreign investor plans a cement grinding plant near the coast with HTG 300,000,000 of expected annual sales (about US$2,294,381). Before building, it files a project notice with the BNEE and the industry ministry's UTES, commissions a detailed impact study, pays for the public hearings and waits for the ministry's non objection. Once operating, it pays the 0.5 percent pollution duty each October on the prior year's sales: HTG 1,500,000 (about US$11,472) on a full year at that level.
- A bakery that fires its ovens with wood and had HTG 12,000,000 of sales last fiscal year (about US$91,775) owes the 1 percent wood fuel tax of HTG 120,000 (about US$918) between 1 and 31 October.
Step by step
- At concept stage, file a project notice with the BNEE (Ministry of the Environment) and contact the UTES of the ministry that will grant your permit or concession, to learn whether a study is needed and at what depth.
- Budget for the study, the public hearings and the management plan: the promoter pays for all three, and no official fee schedule for the ministry's review was found.
- Get the terms of reference validated before hiring consultants, so the study is not rejected at admissibility.
- Do not start works before the non objection; for mining and quarries, the concession itself depends on it.
- Separately obtain the ministry's authorisation for any water intake or discharge in the public water domain.
- Add the October pollution duty or wood fuel tax to the tax calendar if your activity falls under Code Fiscal art. 172 or 173.
- Keep monitoring reports under the management plan and plan a closing audit at the end of the project.
Common traps
- The project list and procedures promised in art. 57 of the 2005 decree were never adopted as a formal regulation; the ministry applies its 2015 methodological guide, so scope decisions are made case by case by the BNEE.
- The ministry itself notes that it has not been able to apply the procedure fully for lack of funding; lenders such as development banks often require their own standards on top, so a Haitian non objection alone may not satisfy financiers.
- Criminal liability does not replace civil liability: restoration costs are owed in addition to any fine, and courts can close the business.
- The polluting business duty is 0.5 percent of turnover, not of profit, so it is owed even in a loss year.
- Free access to beaches and the coastline is protected; a hotel or port design that blocks public access breaches art. 126.
- Discharge permits and water analysis by an approved laboratory are separate duties from the impact assessment.
Sources
- Décret du 12 octobre 2005 portant sur la gestion de l'environnement, Le Moniteur No. 11 of 26 January 2006 (FAOLEX copy of the gazette)
- Décret du 5 août 2020 organisant le Ministère de l'Environnement (Ministry of the Environment)
- Ministère de l'Environnement, official documents page
- Ministère de l'Environnement, CGES Projet Territoires productifs résilients II, October 2024
- Code Fiscal, Le Moniteur Spécial N° 48-A of 30 September 2026 (DGI)
- Banque de la République d'Haïti, taux du jour
Related pages
- regulation/regulatory-compliance-essentials
- regulation/anti-corruption-and-bribery
- taxes/environmental-and-resource-levies
- /country/haiti/
- /calendar/
- Live dashboard
Related: Haiti country profile · live dashboard · central bank and release calendar · our posts on X