The LatAm Thread

Countries › Honduras › Guide › 3. Investing › Contracting with the Honduran State in 2026: payment of judgments and awards, contract reviews and settlements under Decreto 17-2026

Contracting with the Honduran State in 2026: payment of judgments and awards, contract reviews and settlements under Decreto 17-2026

Last verified: 2026-11-03 · Status: Changing

The Ley de Reactivación Económica y Desarrollo Humano (Decreto 17-2026), in force from 27 February 2026 for at most 24 months, matters to anyone with State contracts or claims. Judgments and final arbitral awards against the State are paid within budget availability, with court enforcement only after 12 months without payment. Public bodies may review and annul or rescind earlier acts and contracts issued without full legality, and settlements of L5 million or more need a congressional commission's favorable opinion.

USD figures use L26.9080 per US dollar, the Banco Central de Honduras reference exchange rate (buying) for 3 November 2026, from the BCH daily dollar price series retrieved on the verification date. Conversions are for orientation only.

Key facts

Maximum life of Decreto 17-202624 monthsDecreto 17-2026 art. 11, as of 2026-11-03 · in force
Settlement amount needing a congressional commission opinion5000000 HNLDecreto 17-2026 art. 5, as of 2026-11-03 · in force
Months without payment before courts enforce money judgments against the State12 monthsDecreto 17-2026 art. 4, as of 2026-11-03 · in force

The rule

1. The law declares the rationalization of public spending of national interest, sets an extraordinary and temporary fiscal and financial regime for the whole public sector, and states that its revenue measures do not imply new taxes.Ley de Reactivación Económica y Desarrollo Humano, Decreto 17-2026, art. 1 and 2, 2026-02-27 official text · verified 2026-11-03
2. When courts order embargoes or payment against the State in any matter, including final arbitral awards, they send a certified copy to the Treasury (TGR) and the condemned body, and payment is adjusted to each body's budget availability without affecting public debt service, salaries and core operations; the order goes out within five business days of the judgment becoming final, budget reforms start within three months (general budget) or one month (institutional budgets), and after 12 months without payment of liquid sums the court enforces by the apremio procedure.Decreto 17-2026, art. 4, 2026-02-27 official text · verified 2026-11-03
3. SEFIN must include in the next budget or a budget reform the adjustments needed for payments arising from national or international arbitrations, claims before international tribunals and cases in international bodies.Decreto 17-2026, art. 4, 2026-02-27 official text · verified 2026-11-03
4. The Procuraduría General de la República may settle in court; judicial approval of a settlement requires proof of budget availability, and settlements of L5,000,000 or more need the favorable opinion of a special commission of members of Congress.
Cost to do it: Threshold for the congressional commission opinion: L5,000,000.
Example: L5,000,000 / US$185,818Decreto 17-2026, art. 5, 2026-02-27 official text · verified 2026-11-03
5. Heads of central, decentralized and municipal bodies must review acts and contracts issued before the law, including procurement, works, concessions, licences and permits, and may annul, cancel, revoke or rescind in whole or part those issued without full legality, without required procedures, in breach of others' preferential rights or without budget cover.Decreto 17-2026, art. 6, 2026-02-27 official text · verified 2026-11-03
6. For art. 3 and 4, art. 22 of the contentious administrative jurisdiction law does not apply; bodies must report findings to Congress every six months; the law lasts at most 24 months and took effect on publication in La Gaceta.Decreto 17-2026, art. 9 to 11, 2026-02-27 official text · verified 2026-11-03
StepTime limitArticle
Court sends payment order to TGR and the condemned body5 business days after the judgment is finalart. 4
Budget reform for the payment3 months (general) or 1 month (institutional)art. 4
Court enforcement by apremioAfter 12 months without paymentart. 4
Law expiresAt most 24 months from 27 February 2026art. 11

Payment of judgments and awards against the State under Decreto 17-2026.

Worked example

  • A contractor wins a final arbitral award of L20,000,000 (US$743,273) against a ministry in June 2026. The court must send the order within five business days; the ministry pays within its budget availability; if nothing is paid within 12 months, the contractor can ask the court to enforce. A negotiated settlement of the same claim would need the congressional commission's favorable opinion because it exceeds L5,000,000 (US$185,818).

Step by step

  1. 1. Review State contracts signed before February 2026 for legality, procedure and budget cover, since art. 6 reviews target those defects.
  2. 2. Keep evidence of budget certifications and approvals.
  3. 3. In claims, request inclusion of the amount in the budget early and track the 12 month enforcement window.
  4. 4. Consider treaty protection and stability clauses for large exposures.

Common traps

  • The law runs to February 2028 at the latest, so contracts and claims in that window are exposed to its reviews and payment rules.
  • Settlements of L5,000,000 or more need a political step, which adds time.
  • Final arbitral awards against the State are covered, so arbitration does not escape the budget availability rule.

Sources

Related pages

Related: Honduras country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.