Prior consultation comes before resource projects

Last verified: 2026-11-01 · Status: Stable

Abroad a permit may need a public hearing; in Bolivia the Constitution requires prior, free and informed consultation before resource projects. Oil and gas law requires it for any activity, and mining law for contracts that may affect collective rights. In mining, the applicant funds the process.

USD figures use Bs 12.09 per US dollar, the official rate published by the Banco Central de Bolivia for 31 October to 3 November 2026. The rate now moves under the flexible regime, so boliviano amounts stay the same while their dollar value changes. Conversions are for orientation only.

Key facts

Maximum mining consultation stage4 monthsLey 535 art. 212, as of 2026-11-01 · in force

The rule

1. Indigenous peoples have the right to be consulted, with mandatory prior consultation by the State, in good faith and agreed, on non renewable resources in their territory.Constitución Política del Estado, Art. 30 II no. 15, 2009-02-07 official text · verified 2026-11-01
2. Use of natural resources in a given territory is subject to free, prior and informed consultation of the population affected, called by the State.Constitución Política del Estado, Art. 352, 2009-02-07 official text · verified 2026-11-01
3. Communities must be consulted in advance, as a duty and in good time, on any hydrocarbon activity.Ley 3058, Art. 114, 2005-05-17 official text · verified 2026-11-01
4. If the outcome is negative, the State may promote conciliation in the national interest. Results and agreements are valid for the project.Ley 3058, Art. 116, 2005-05-17 official text · verified 2026-11-01
5. Prior consultation applies to every application for a mining administrative contract that may directly affect collective rights.Ley 535, Art. 207 I, 2014-05-28 official text · verified 2026-11-01
6. The stage cannot run beyond four months from last notice, and failing agreement the Ministry of Mining decides within 15 administrative working days.
Cost to do it: Time, plus a final ministerial ruling.Ley 535, Art. 212 and 215, 2014-05-28 official text · verified 2026-11-01
7. The applicant bears notice costs, and the AJAM covers process costs with funds given by the mining actor.
Cost to do it: Paid by the applicant. Amounts are set case by case.Ley 535, Art. 216, 2014-05-28 official text · verified 2026-11-01

Worked example

  • A mining applicant in an area with an indigenous community budgets four months for meetings, funds the process, and if no deal is reached awaits a ministerial ruling.

Step by step

  1. Map communities early.
  2. Budget the process.
  3. Keep records of each meeting.
  4. Coordinate with the environmental license.

Common traps

  • Consultation is run by the State, so a private deal does not replace it.
  • Communities can include intercultural and Afro Bolivian groups in mining.
  • Skipping it invites constitutional action.

Sources

Related pages

Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.