Countries › Bolivia › Guide › 12. Sectors › Mining consultation, environmental licence and closure
Mining consultation, environmental licence and closure
Last verified: 2026-10-31 · Status: Stable
Before most exploitation contracts, the State must consult indigenous and other protected groups in a process capped at about four months and paid for by the miner. An environmental licence is also required, responsibility runs with the operator, and producers must keep an accounting provision for closure.
USD figures use Bs 12.09 per US dollar, the official rate (TCO) published by the Banco Central de Bolivia for 31 October to 3 November 2026. UFV amounts use Bs 3.36631 per UFV from the same BCB page. The rate now floats, so boliviano amounts stay the same while their dollar value changes. Conversions are for orientation only.
Key facts
| Consultation ceiling | 4 monthsLey 535 art. 212, as of 2026-10-31 · in force |
|---|---|
| Consultation meetings | 3 meetingsLey 535 art. 211, as of 2026-10-31 · in force |
| Term to order a stop on illegal mining | 48 hoursLey 535 art. 104, as of 2026-10-31 · in force |
The rule
Cost to do it: Paid by the applicant at the amount AJAM sets; no fixed tariff found.Ley 535 de Minería y Metalurgia, Art. 216, 2014-05-28 official text · verified 2026-10-31
| Step | Term | Who |
|---|---|---|
| Opposition phase ends | Per art. 165 | AJAM regional office |
| Resolution opens consultation | After opposition | AJAM |
| Notice to subjects | Up to 15 working days | AJAM |
| Up to 3 meetings | Within 4 months of last notice | AJAM, miner, subjects |
| Mediation | 15 working days from last notice | AJAM national office |
| Final decision | 15 working days | Ministry of Mining |
Consultation timeline under Ley 535
Worked example
- A company plans for 4 months of consultation, 30 working days of mediation and decision, and then up to 90 days of Assembly review. That is about 8 to 9 months of State steps after AJAM clears opposition, before the environmental licence time. If a Bs 20,000,000 (about US$1,654,259.72) drilling budget stays idle over that time, the cost of waiting belongs in the investment case.
Step by step
- Map peoples and land titles early, and use real-estate/indigenous-and-communal-land.
- Start community relations before filing.
- File for the contract.
- Fund AJAM's consultation costs.
- Reach agreement, sign and record it.
- Obtain the environmental licence.
- Set up the closure provision once in production.
Common traps
- The four month ceiling covers the formal process only. It does not stop court action.
- The closure rule is an accounting provision, not a bond, and we found no fixed guarantee rule, so lenders may ask for more.
- Losing a right does not free the holder from remediation (art. 114), so price those liabilities when buying a mining company.
Sources
Related pages
- sectors/mining-rights-and-contracts
- disputes/constitutional-amparo
- /country/bolivia/
- /calendar/
- Live dashboard
Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.