The LatAm Thread

Countries › Bolivia › Guide › 12. Sectors › Mining consultation, environmental licence and closure

Mining consultation, environmental licence and closure

Last verified: 2026-10-31 · Status: Stable

Before most exploitation contracts, the State must consult indigenous and other protected groups in a process capped at about four months and paid for by the miner. An environmental licence is also required, responsibility runs with the operator, and producers must keep an accounting provision for closure.

USD figures use Bs 12.09 per US dollar, the official rate (TCO) published by the Banco Central de Bolivia for 31 October to 3 November 2026. UFV amounts use Bs 3.36631 per UFV from the same BCB page. The rate now floats, so boliviano amounts stay the same while their dollar value changes. Conversions are for orientation only.

Key facts

Consultation ceiling4 monthsLey 535 art. 212, as of 2026-10-31 · in force
Consultation meetings3 meetingsLey 535 art. 211, as of 2026-10-31 · in force
Term to order a stop on illegal mining48 hoursLey 535 art. 104, as of 2026-10-31 · in force

The rule

1. Prior, free and informed consultation by the State of indigenous peoples, intercultural communities and the Afro Bolivian people is a mandatory collective right, for any request to sign a mining contract likely to directly affect their rights.Ley 535 de Minería y Metalurgia, Art. 207 I, 2014-05-28 official text · verified 2026-10-31
2. Operations limited to prospecting and exploration need no consultation.Ley 535 de Minería y Metalurgia, Art. 207 II, 2014-05-28 official text · verified 2026-10-31
3. The aim is agreement to allow the contract to go ahead. Each subject must meet listed conditions, including pre colonial existence, ancestral domain, own institutions and collective land.Ley 535 de Minería y Metalurgia, Art. 208 and 209, 2014-05-28 official text · verified 2026-10-31
4. After any opposition phase, AJAM identifies who may be affected and opens consultation by resolution. Notice goes out within 15 working days.Ley 535 de Minería y Metalurgia, Art. 210 and 211, 2014-05-28 official text · verified 2026-10-31
5. Consultation takes up to 3 meetings, near the project, and cannot exceed 4 months from the last notice.Ley 535 de Minería y Metalurgia, Art. 211 and 212, 2014-05-28 official text · verified 2026-10-31
6. If no agreement arises, AJAM's national office mediates. If 15 working days pass with no deal, the Ministry of Mining decides within 15 working days by ministerial resolution.Ley 535 de Minería y Metalurgia, Art. 214 and 215, 2014-05-28 official text · verified 2026-10-31
7. The miner pays for notices, and AJAM covers consultation costs from funds the miner provides.
Cost to do it: Paid by the applicant at the amount AJAM sets; no fixed tariff found.Ley 535 de Minería y Metalurgia, Art. 216, 2014-05-28 official text · verified 2026-10-31
8. The Mining chapter on consultation must align with the general consultation law once that law is published, and a sector regulation follows within 180 days.Ley 535 de Minería y Metalurgia, Disposición Transitoria Cuarta, 2014-05-28 official text · verified 2026-10-31
9. Mining activities need an environmental licence under Ley 1333. Activities with known minor impacts (AMIAC) go to the departmental government.Ley 535 de Minería y Metalurgia, Art. 217 and 218, 2014-05-28 official text · verified 2026-10-31
10. Holders and operators must prevent, reduce and mitigate impacts, and remediate and rehabilitate explored and worked areas. Losing the right does not end remediation duties.Ley 535 de Minería y Metalurgia, Art. 114 and 219, 2014-05-28 official text · verified 2026-10-31
11. Mining in protected and forest areas is allowed if it meets environmental rules and does not harm the area's aims.Ley 535 de Minería y Metalurgia, Art. 220, 2014-05-28 official text · verified 2026-10-31
12. Producers must make an accounting provision for closure costs.Ley 535 de Minería y Metalurgia, Art. 221, 2014-05-28 official text · verified 2026-10-31
13. Residues such as tailings stay part of the area, the holder may work them under environmental rules, and rights over them end with the mining right.Ley 535 de Minería y Metalurgia, Art. 96, 2014-05-28 official text · verified 2026-10-31
14. Exploiting minerals with no right is illegal. The ministry and AJAM can order suspension within 48 hours, and seize or destroy machinery. Convictions include paying back mineral value, royalties and taxes.Ley 535 de Minería y Metalurgia, Art. 104, 2014-05-28 official text · verified 2026-10-31
15. Peoples have a right to share in benefits of mining in their territories, through the royalty regime and with any measures from consultation.Ley 535 de Minería y Metalurgia, Art. 19, 2014-05-28 official text · verified 2026-10-31
StepTermWho
Opposition phase endsPer art. 165AJAM regional office
Resolution opens consultationAfter oppositionAJAM
Notice to subjectsUp to 15 working daysAJAM
Up to 3 meetingsWithin 4 months of last noticeAJAM, miner, subjects
Mediation15 working days from last noticeAJAM national office
Final decision15 working daysMinistry of Mining

Consultation timeline under Ley 535

Worked example

  • A company plans for 4 months of consultation, 30 working days of mediation and decision, and then up to 90 days of Assembly review. That is about 8 to 9 months of State steps after AJAM clears opposition, before the environmental licence time. If a Bs 20,000,000 (about US$1,654,259.72) drilling budget stays idle over that time, the cost of waiting belongs in the investment case.

Step by step

  1. Map peoples and land titles early, and use real-estate/indigenous-and-communal-land.
  2. Start community relations before filing.
  3. File for the contract.
  4. Fund AJAM's consultation costs.
  5. Reach agreement, sign and record it.
  6. Obtain the environmental licence.
  7. Set up the closure provision once in production.

Common traps

  • The four month ceiling covers the formal process only. It does not stop court action.
  • The closure rule is an accounting provision, not a bond, and we found no fixed guarantee rule, so lenders may ask for more.
  • Losing a right does not free the holder from remediation (art. 114), so price those liabilities when buying a mining company.

Sources

Related pages

Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.