Countries › Chile › Guide › 3. Investing › Project permits in Chile: environmental assessment (DIA and EIA) timelines, the Ley Nº 21.850 reforms to appeals and injunctions, and the new sectoral permits framework law
Project permits in Chile: environmental assessment (DIA and EIA) timelines, the Ley Nº 21.850 reforms to appeals and injunctions, and the new sectoral permits framework law
Last verified: 2026-10-26 · Status: Changing
Large projects in Chile, from power plants and mines to ports and factories, cannot be built until they pass the Environmental Impact Assessment System, through a Declaration (60 day review) or, where significant impacts exist, a full Study (120 day review), with clocks that stop whenever the authority asks for clarifications. Ley Nº 21.850 reshapes the back end from 1 November 2026: a single appeal route with tight deadlines, an optional fast track with fewer rounds of questions, a one year limit on invalidation and court injunctions against approvals capped at six months. Permits outside that system move to Ley Nº 21.770, which sets maximum terms, positive silence for project and operating permits and a single digital window, phased in permit by permit.
USD figures use the dólar observado of CLP 972.60 per US dollar for 1 October 2026, the latest value shown in the SII dólar observado table on the verification date. UTM amounts use the October 2026 UTM of CLP 72,151 and UTA of CLP 865,812, and UF amounts the UF of CLP 41,221.08 for 26 October 2026, all published by the SII. Conversions are for orientation only.
Key facts
| Review period for an Environmental Impact Study | 120 daysLey Nº 19.300 art. 15, as of 2026-10-26 · in force |
|---|---|
| Review period for an Environmental Impact Declaration | 60 daysLey Nº 19.300 art. 18, as of 2026-10-26 · in force |
| Power plant size that triggers assessment (until a new regulation applies) | 3 MWLey Nº 19.300 art. 10 letter c, as of 2026-10-26 · in force |
| Deadline to file the special appeal against an RCA | 30 daysLey Nº 21.850 art. 11 Nº 4, as of 2026-10-26 · in force |
| Deadline to decide appeals on an EIA | 60 daysLey Nº 21.850 art. 11 Nº 4, as of 2026-10-26 · in force |
| Maximum total duration of court injunctions suspending an RCA | 6 monthsLey Nº 21.850 art. 14 Nº 5, as of 2026-10-26 · in force |
| Deadline for the administration to invalidate unlawful acts | 1 yearsLey Nº 21.850 art. 4, as of 2026-10-26 · in force |
| Maximum term for a sectoral project permit under the framework law | 50 business daysLey Nº 21.770 art. 20 and 21, as of 2026-10-26 · pending |
| Silence effect for project and operating permits under the framework law | Deemed granted textLey Nº 21.770 art. 24, as of 2026-10-26 · pending |
The rule
Cost to do it: No SEA filing fee is set in Ley Nº 19.300. Costs are consultants' studies, baseline fieldwork and the publication of the EIA extract in the Diario Oficial and a newspaper.
Example: A DIA filed on day 0 with one round of questions answered in 45 days is due by day 105 at the earliest, before any 30 day extension. / Budget at least six months for a DIA and a year or more for an EIA once suspensions are counted.Ley Nº 19.300, Ley sobre Bases Generales del Medio Ambiente, Art. 15, art. 15 bis, art. 16, art. 18, art. 18 bis, art. 18 ter, art. 19 and art. 28, 2010-01-26 official text · verified 2026-10-26
Cost to do it: The law sets no new fees; sector fees, where they exist, still apply.Ley Nº 21.770, Ley Marco de Autorizaciones Sectoriales, Art. 20, art. 21, art. 24 and art. 25; first and fourth transitory articles, 2025-09-29 official text · verified 2026-10-26
| Step | DIA | EIA |
|---|---|---|
| Early return for missing essential information | First 30 days | First 40 days |
| Decision | 60 days, extendable once by up to 30 | 120 days |
| Missing sectoral environmental permit deemed granted | 10 days after request | 15 days after request |
| Rounds of questions under the voluntary special regime | One | Up to two |
| Special appeal: filing | 30 days, to the SEA Executive Director | 30 days, to the Committee of Ministers |
| Special appeal: decision | 30 days | 60 days |
| Court challenge | 20 days, Environmental Court | 20 days, Environmental Court |
Environmental assessment clocks (Ley Nº 19.300, as amended by Ley Nº 21.850 from 1 November 2026).
| Authorisation type | Maximum term | Default silence |
|---|---|---|
| Administration or disposal (public services, State property) | 120 | Refusal |
| Location | 50 | Refusal |
| Professional or service | 60 | Refusal |
| Project | 50 | Approval |
| Operation | 25 | Approval |
| Other | 60 | Approval |
Maximum terms and default silence under Ley Nº 21.770 (business days; applies to each permit eight months after its classification decree).
Worked example
- A developer plans a 9 MW solar plant. It must enter the system because it exceeds 3 MW, and if no art. 11 effect applies it files a DIA, opting into the voluntary special regime so the SEA can ask only one round of questions (Ley Nº 19.300 art. 10 and new art. 25 septies).
- The SEA asks questions on day 40; the developer answers on day 75 and the remaining 20 days run, so a decision is due around day 95. A neighbour who submitted observations appeals the approval within 30 days; the Executive Director must rule within 30 days, and the neighbour can then go to the Environmental Court within 20 days (new art. 20).
- If the court suspends the RCA, the injunction lapses after 30 days unless renewed and cannot exceed six months in total (Ley Nº 20.600 art. 24 as amended). The plant's sectoral permits outside the system will move to fixed terms and positive silence under Ley Nº 21.770 as each is classified.
Step by step
- 1. Screen the project against art. 10 and the regulation to know whether it must enter the system, and against art. 11 to choose DIA or EIA.
- 2. Decide whether to opt into the special regime at filing; it cuts rounds of questions but requires a complete filing up front.
- 3. Map public participation and indigenous consultation risks, and prepare the EIA extract publication if applicable.
- 4. Track suspensions and deadlines, including the 30 or 40 day early return windows.
- 5. After the RCA, calendar the 30 day appeal window and the 20 day court window, and prepare for injunction hearings.
- 6. List sectoral permits outside the system and check whether each has been classified under Ley Nº 21.770 and when its new terms start.
Common traps
- Splitting a project to stay under thresholds or file a DIA instead of an EIA is prohibited (Ley Nº 19.300 art. 11 bis).
- Assuming the 3 MW threshold has changed. The new wording only applies once the new regulation is published, and it cannot go below 3 MW (Ley Nº 21.850 thirteenth transitory article).
- Raising new arguments in court. The Environmental Court claim can only rest on matters raised in the special appeal (new art. 20 letter f).
- Counting on compensation if an RCA is annulled. That mechanism was struck down; no compensation route exists.
- Expecting positive silence today for every sectoral permit. Ley Nº 21.770's terms and silence rules apply permit by permit, eight months after each classification decree.
Sources
- Ley Nº 19.300 (Ley Chile)
- Ley Nº 21.850 (Ley Chile)
- Ley Nº 21.770, Ley Marco de Autorizaciones Sectoriales (Ley Chile)
- Ley Nº 19.880, administrative procedure law (Ley Chile)
Related pages
- investing/foreign-investment-regime
- investing/tax-stability-contracts
- sectors/mining-energy-and-key-sectors
- disputes/environmental-courts-and-project-challenges
- regulation/regulatory-compliance-essentials
- start/reform-tracker
- /country/chile/
- /calendar/
- Live dashboard
Related: Chile country profile · live dashboard · central bank and release calendar · our posts on X