Countries › Costa Rica › Guide › 12. Sectors › Rooftop solar and self consumption in Costa Rica: distributed energy resources under Ley 10086
Rooftop solar and self consumption in Costa Rica: distributed energy resources under Ley 10086
Last verified: 2026-10-30 · Status: Stable
Since January 2022 homes and businesses can generate renewable power for their own use, store it and connect to the grid under Ley 10086 and its regulation DE 43879. Systems up to 5 MW count as small scale; those under 500 kVA need no municipal permit or SETENA viability. The distributor may buy surplus energy but is not obliged to, and selling power to third parties is not allowed. Free zone companies outside the Greater Metropolitan Area can share systems through registered aggregators.
USD figures use the Banco Central de Costa Rica reference selling rate of ₡454.82 per US dollar published for 29 October 2026 (indicator 318 on bccr.fi.cr), rounded to the cent.
Key facts
| Maximum capacity of a small scale distributed generation system | 5 MWDE 43879-MINAE art. 7, as of 2026-10-30 · in force |
|---|---|
| Capacity below which no municipal permit or SETENA viability is needed | 500 kVALey 10086 art. 10, as of 2026-10-30 · in force |
| SME capacity limit for exemption from ARESEP procedures | 15 kWLey 10086 art. 13, as of 2026-10-30 · in force |
| Distributor deadline to decide a claim | 10 business daysLey 10086 art. 15, as of 2026-10-30 · in force |
The rule
Cost to do it: 5 to 20 salarios base of ₡462,200 (2026).
Example: ₡2,311,000 to ₡9,244,000. / About US$5,081.13 to US$20,324.52.Ley 10086, Promoción y regulación de recursos energéticos distribuidos a partir de fuentes renovables, art. 14, 2021-12-08 official text · verified 2026-10-30
Worked example
- A hotel in Guanacaste installs a 300 kW solar array for self consumption. Because it is under 500 kVA it needs no municipal permit or SETENA viability, but a CFIA engineer must design and sign the plans and the distributor must authorise interconnection with surplus. If it breaches the rules, ARESEP can fine it ₡2,311,000 to ₡9,244,000 (about US$5,081.13 to US$20,324.52).
Step by step
- Ask the distributor for grid availability (penetration capacity) on the circuit.
- Have a CFIA registered engineer design the system and process plans with the CFIA.
- Choose the operating mode: island, without surplus, or with surplus.
- Sign the interconnection and supply contracts with the distributor on ARESEP terms.
- Install, file the sworn technical compliance statement and pay the ARESEP access tariffs.
Common traps
- Payment for surplus is not guaranteed: the distributor buys only when it benefits.
- Selling power to a tenant or neighbour is grounds for disconnection.
- Systems above 500 kVA on structures without environmental viability still need municipal and SETENA clearance.
- Free zone sharing applies only outside the Greater Metropolitan Area.
Sources
Related pages
- sectors/electricity-generation-and-private-power
- sectors/electric-vehicles-and-charging
- investing/free-zone-regime
- /country/costa-rica/
- /calendar/
- Live dashboard
Related: Costa Rica country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.