Countries › Costa Rica › Guide › 12. Sectors › Private power generation in Costa Rica: Ley 7200 plants, ICE purchase contracts and ARESEP tariffs
Private power generation in Costa Rica: Ley 7200 plants, ICE purchase contracts and ARESEP tariffs
Last verified: 2026-10-30 · Status: Stable
Electricity in Costa Rica is built around the State utility ICE, which buys power from private plants under Ley 7200. Private plants up to 20 MW need an ICE eligibility declaration and an ARESEP concession, and plants of up to 50 MW can win ICE tenders under BOT style contracts of up to 20 years that hand the plant to ICE at the end. Plants must be at least 35% Costa Rican owned, and private generation is capped at a share of national capacity.
USD figures use the Banco Central de Costa Rica reference selling rate of ₡454.82 per US dollar published for 29 October 2026 (indicator 318 on bccr.fi.cr), rounded to the cent.
Key facts
| Maximum size of a Chapter I private plant | 20 MWLey 7200 art. 2 and 5, as of 2026-10-30 · in force |
|---|---|
| Cap on Chapter I parallel generation in national capacity | 15 %Ley 7200 art. 7, as of 2026-10-30 · in force |
| Maximum block per Chapter II tender plant | 50 MWLey 7200 art. 20, as of 2026-10-30 · in force |
| Maximum term of an ICE purchase contract (Chapter II) | 20 yearsLey 7200 art. 22, as of 2026-10-30 · in force |
| Minimum Costa Rican share capital of a private generator | 35 %Ley 7200 art. 3, as of 2026-10-30 · in force |
| ICE deadline for eligibility declaration | 120 daysLey 7200 art. 6, as of 2026-10-30 · in force |
The rule
Cost to do it: Ownership structure: at least 35% Costa Rican capital in the generating company.
Example: A ₡1,000,000,000 share capital company needs at least ₡350,000,000 held by Costa Ricans. / About US$769,535.20 of US$2,198,672.00.Ley 7200, Ley que Autoriza la Generación Eléctrica Autónoma o Paralela, art. 3, 1995-05-09 official text · verified 2026-10-30
Cost to do it: Guarantee of 4% of project value during construction, then 1%.
Example: A project worth ₡22,741,000,000: ₡909,640,000 during construction, then ₡227,410,000. / On a US$50,000,000 project: US$2,000,000, then US$500,000.Ley 7200, Ley que Autoriza la Generación Eléctrica Autónoma o Paralela, art. 11, 1990-09-28 official text · verified 2026-10-30
Worked example
- A foreign developer plans a 40 MW wind farm costing US$50,000,000 (about ₡22,741,000,000). At 40 MW it cannot use a Chapter I concession (20 MW cap), so it must win an ICE public tender under Chapter II. It forms a Costa Rican company or domiciled branch with at least 35% Costa Rican capital, posts a US$2,000,000 environmental guarantee during construction (1% or US$500,000 thereafter) and signs a contract of up to 20 years, after which the plant passes to ICE at no cost.
Step by step
- Check ICE's generation expansion plan and whether a tender or eligibility window is open.
- Structure the project company with at least 35% Costa Rican capital.
- Obtain the water concession where needed and environmental viability from SETENA.
- Apply to ICE for the eligibility declaration (Chapter I) or bid in the public tender (Chapter II).
- Obtain the ARESEP concession and have the purchase contract and tariff approved.
- Post the 4% guarantee at contract signing and reduce it to 1% one year after start of operation.
Common traps
- The 35% Costa Rican capital rule applies to the generator and to foreign branches; a 100% foreign SPV does not qualify.
- Chapter II plants transfer to ICE free of charge at the end of the contract, so the tariff must recover the full investment within the term.
- ICE sells all output; private generators cannot sell to end users under Ley 7200.
- Distributed generation for self consumption is a separate regime (Ley 10086) and Ley 7200 concessions cannot be used for it.
Sources
Related pages
- sectors/key-sectors-and-regulators
- sectors/distributed-generation-and-self-consumption
- investing/concessions-and-public-private-partnerships
- investing/environmental-assessment-and-project-permits
- investing/restricted-activities-and-ownership-limits
- /country/costa-rica/
- /calendar/
- Live dashboard
Related: Costa Rica country profile · live dashboard · central bank and release calendar · our posts on X