The LatAm Thread

Countries › Cuba › Guide › 11. Real estate and land › Building permits, habitability certificates and zoning in Cuba

Building permits, habitability certificates and zoning in Cuba

Last verified: 2026-11-09 · Status: Changing

New homes, structural works and premises inside a home's boundaries need a building licence (licencia de obra) from the municipal territorial planning office, and minor exterior works need a works authorisation; interior conservation that does not touch facade or structure needs neither. The office registers an application within 3 working days, evaluates it in 10 and issues the licence in 5, and on completion a habitability certificate is issued on a similar timetable before the works can be described by notarial deed and registered. State investors must hand up to 20 percent of homes they build to the municipality or fund the surrounding urban works in the same proportion.

Key facts

Working days for evaluating a building licence application10 working daysDecreto 176/2026 art. 72.1, as of 2026-11-09 · in force
Working days to issue the building licence after approval5 working daysDecreto 176/2026 art. 73.2, as of 2026-11-09 · in force
Share of homes a State investor must contribute to the municipality20 % (maximum)Ley 187/2026 art. 17, as of 2026-11-09 · in force

The rule

1. New works and other architectural interventions by natural and legal persons in homes, apartment buildings and premises are authorised by a building licence or a works authorisation issued by the municipal territorial planning and urbanism office. Conservation works and interior works that do not change the facade or affect load bearing structure need neither.
Cost to do it: No fee is stated in this norm.Ley 187 Ley de la Vivienda, Art. 22.1 to 22.4, 2026-07-30 official text · verified 2026-11-09
2. Land management instruments are urban planning regulations, the building licence, the habitability certificate, the works authorisation, the cadastral certificate, the technical opinion on description, valuation, measures and boundaries, and the technical opinion declaring a building in ruin. Planning regulations are public and binding on everyone.
Cost to do it: No fee is stated in this norm.Decreto 176 Reglamento General de la Ley de la Vivienda, Art. 62, 2026-09-04 official text · verified 2026-11-09
3. A building licence covers works that permanently occupy land, new homes, premises and productive installations within the home's boundaries, and any structural change in homes or buildings under horizontal property. The application includes proof of title to the home, plot or roof, two copies of the executive project and proof of payment of documents stamp tax.
Cost to do it: Documents stamp tax under Ley 113 Annex 4 plus the cost of the executive project from an authorised design entity; no licence fee scale is set in the decree.Decreto 176 Reglamento General de la Ley de la Vivienda, Arts. 63 and 71, 2026-09-04 official text · verified 2026-11-09
4. The office registers the file within 3 working days and evaluates the project within 10 working days; correctable defects get recommendations within 10 working days, notified within 3. The licence is issued within 5 working days and notified within 3; files not corrected in time are archived, and refusals can be challenged in court.
Cost to do it: No fee is stated in this norm.Decreto 176 Reglamento General de la Ley de la Vivienda, Arts. 72 and 73, 2026-09-04 official text · verified 2026-11-09
5. On completion the owner applies for a habitability certificate, with stamp tax paid; the office registers the file within 3 working days, checks compliance within 10 days, obtains health and other approvals itself, and issues the certificate within 5 working days. It describes areas, measures, boundaries, numbering, price, common elements and easements.
Cost to do it: No fee is stated in this norm.Decreto 176 Reglamento General de la Ley de la Vivienda, Arts. 79 and 80, 2026-09-04 official text · verified 2026-11-09
6. A works authorisation is required for minor exterior works, exterior painting and repair in condominiums or special zones where required, temporary structures, interior works that add to water and sewage networks, demolitions and facade changes; homes not on main avenues or in special zones need no authorisation for facade repairs and minor works. The authorisation is issued within 3 working days after a 10 working day review.
Cost to do it: No fee is stated in this norm.Decreto 176 Reglamento General de la Ley de la Vivienda, Arts. 65 and 82 to 84, 2026-09-04 official text · verified 2026-11-09
7. Organs, agencies and economic entities acting as investors must contribute up to 20 percent of the homes they build to the municipal housing stock, or solve the surrounding urban conditions in the same proportion, unless defence and national security interests are affected.
Cost to do it: Up to 20 percent of homes built, or equivalent urban works.Ley 187 Ley de la Vivienda, Art. 17, 2026-07-30 official text · verified 2026-11-09
8. Works carried out by self builders must follow the approved technical and administrative documents and are described by notarial deed once finished.
Cost to do it: No fee is stated in this norm.Ley 187 Ley de la Vivienda, Arts. 25 and 48.1, 2026-07-30 official text · verified 2026-11-09
StepBuilding licenceWorks authorisationHabitability certificate
Register file333
Evaluate101010 (days)
Issue535
Notify323

Permit timetable for self build works (Decreto 176/2026, working days)

Step by step

  1. Obtain the certificate of urban regulations for the plot from the municipal territorial planning office.
  2. Commission an executive project from an authorised design entity.
  3. File the licence application with title, two copies of the project and the stamp tax receipt.
  4. Keep the licence and project on site for inspectors during works (Decreto 176 art. 68).
  5. Apply for the habitability certificate on completion, then describe the works by notarial deed and register them.

Common traps

  • Changes to the approved project must be approved before they are built (Decreto 176 art. 74.2).
  • Instruments obtained with defects can be cancelled at the request of the Prosecutor or Comptroller (Decreto 176 art. 69).
  • Homes in special zones need the zone authority's opinion before a licence (Decreto 176 art. 273).
  • The habitability timetable is short on paper, but health and other approvals are gathered by the office and can slow it down.

Sources

Related pages

Related: Cuba country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.