Cuba electricity and renewable power: selling to the grid, tariffs and incentives
Last verified: 2026-11-15 · Status: Changing
Cuba's grid stays in State hands through the Unión Eléctrica (UNE), but private and foreign investors may now generate renewable power: UNE must buy all compliant renewable output, at CUP 90 per kWh at any hour since 2026, with profit tax exempt up to the investment value for up to eight years and duty free equipment listed to 31 December 2027. Businesses can also buy shares of UNE solar parks from US$90 to US$600 per kW to cut their bills. Energy is a sector named in U.S. Executive Order 14404.
USD figures use CUP 800 per US dollar, the Segment III floating rate (tasaEspecial) in the Banco Central de Cuba rate service for 9 November 2026, read on 9 November 2026. Segment I is CUP 24 and Segment II CUP 120 per US dollar, so the dollar value of a peso amount depends on the segment open to you. Conversions are for orientation only.
Key facts
| Grid purchase tariff for renewable electricity | 90 CUP/kWhMFP Res. 114/2026 as amended by Res. 179/2026, as of 2026-11-15 · in force |
|---|---|
| Maximum period of profit tax exemption for renewable investment (capped at investment value) | 8 yearsMFP Res. 180/2026 apartado Sexto, as of 2026-11-15 · in force |
| Price of UNE solar park capacity, 20 year contract | 600 USD/kWMINEM Res. 76/2025 Anexo Único, as of 2026-11-15 · in force |
| Minimum solar park capacity a customer may contract | 0.5 kWMINEM Res. 76/2025 apartado Primero a), as of 2026-11-15 · in force |
| Grid owner and single buyer | Unión Eléctrica (UNE), State owned textDecreto-Ley 345/2019 art. 15.2, as of 2026-11-15 · in force |
| Customs duty exemption lists for renewable equipment valid until | 2027-12-31 dateMFP Res. 180/2026 Anexos I and II, as of 2026-11-15 · in force |
The rule
Example: A 1 MW solar plant exporting 1,500,000 kWh a year earns CUP 135,000,000. / The same CUP 135,000,000 is about US$168,750 at the Segment III rate of CUP 800, or US$1,125,000 at the Segment II rate of CUP 120.MFP Resolución 114/2026 (Gaceta Ordinaria 45 of 2026) as amended by MFP Resolución 179/2026 (Gaceta Ordinaria 66 of 2026), Res. 114 apartados Primero and Segundo; Res. 179 apartado Único, 2026-08-07 official text · verified 2026-11-15 · changed: Res. 114 of 6 May 2026, published and in force on 21 May 2026, set CUP 90 per kWh for non residential (C1F) and residential (CFR) producers; Res. 179, in force on publication on 7 August 2026, rewrote apartado Primero without those tariff codes to widen the tariff to power from any renewable source.
Cost to do it: US$600 per kW for a 20 year contract; US$90 per kW for 2 years.
Example: A workshop buying 10 kW for 20 years pays US$6,000 (about CUP 4,800,000 at CUP 800) and gets 1,250 kWh a month off its bill. / 10 kW for 20 years costs US$6,000; for 5 years US$1,680; for 2 years US$900.MINEM Resolución 76/2025 (Gaceta Ordinaria 30 of 2026), Apartados Primero, Segundo, Cuarto and Anexo Único, 2026-03-26 official text · verified 2026-11-15 · changed: Res. 76/2025, dated 13 August 2025 and published 26 March 2026, repealed MINEM Res. 242/2021 and updated solar park capacity prices, citing the fall in solar technology prices.
| Capacity contracted | 20 years | 10 years | 5 years | 2 years | Monthly kWh off the bill |
|---|---|---|---|---|---|
| 0.5 kW | 300.00 | 156.00 | 84.00 | 45.00 | 63 |
| 1 kW | 600.00 | 312.00 | 168.00 | 90.00 | 125 |
| 5 kW | 3,000.00 | 1,560.00 | 840.00 | 450.00 | 625 |
| 10 kW | 6,000.00 | 3,120.00 | 1,680.00 | 900.00 | 1,250 |
| Above 10 kW | Capacity × 1 kW price | Capacity × 1 kW price | Capacity × 1 kW price | Capacity × 1 kW price | 125 per kW |
UNE solar park capacity prices, US$ (MINEM Res. 76/2025 Anexo Único)
Worked example
- A private manufacturer installs a 1 MW rooftop and ground solar system costing the equivalent of US$700,000, uses part of the output and exports 1,500,000 kWh a year to the grid. Grid sales earn CUP 135,000,000 a year, free of the services tax. With an ONURE energy certificate, ONAT exempts its profit tax up to the US$700,000 investment value over the payback period, for up to eight years, starting within 60 days of the request. Panels and inverters listed in Annex I enter duty free. At CUP 800 per dollar the grid income is about US$168,750 a year, so the payback depends on which FX segment the company can use to service foreign costs.
Step by step
- Check whether your structure is a private Cuban business (Decreto 160 item 21) or a foreign investment needing Council of Ministers approval (Ley 118 art. 21.3 f).
- Screen the project, suppliers and banks against Executive Order 14404 and the Cuba Restricted List.
- Agree grid connection and the purchase contract with the UNE provincial company at the CUP 90 per kWh tariff.
- Import listed equipment under Res. 180 Annex I or II, or ask the Ministry of Finance and Prices for a specific exemption for unlisted project goods.
- After commissioning, obtain the ONURE Dictamen Energético and apply to ONAT for the profit tax exemption with the feasibility study.
- If buying solar park capacity instead, sign the UNE proforma and pay the US$ price into the UNE account.
Common traps
- The grid tariff is in pesos; the dollar value swings almost sevenfold between Segment II (CUP 120) and Segment III (CUP 800).
- The sales tax exemption on renewable equipment trade ends one year after 7 August 2026.
- The profit tax exemption is capped at the investment value and the payback period; it is not a flat eight year holiday.
- Joint ventures and wholly foreign owned plants do not get the DL 345 art. 10 and 11 benefits; their incentives rest on art. 9 and the foreign investment regime.
- Private actors may not manage the grid itself; any grid asset must go through an association or mixed company between Cuban entities.
Sources
- Gaceta Oficial, Decreto-Ley 345/2019 (Edición Ordinaria 95 of 28 November 2019)
- Gaceta Oficial, MFP Resolución 114/2026 (Edición Ordinaria 45 of 21 May 2026)
- Gaceta Oficial, MFP Resoluciones 179 and 180/2026 (Edición Ordinaria 66 of 7 August 2026)
- Gaceta Oficial, MINEM Resolución 76/2025 (Edición Ordinaria 30 of 26 March 2026)
- Gaceta Oficial, Decreto 160/2026 (Edición Ordinaria 62 of 2026)
- Gaceta Oficial, Ley 118 consolidated (Edición Especial 11 of 2026)
- Federal Register via govinfo.gov, Executive Order 14404 of 1 May 2026 (91 FR 25061)
- Banco Central de Cuba rate service, 9 November 2026
Related pages
- sectors/us-sanctions-by-sector
- sectors/private-sector-activity-limits
- taxes/tax-incentives
- taxes/customs-duties
- fx/exchange-rates-and-the-three-segments
- /country/cuba/
- /calendar/
- Live dashboard
- https://theargentinethread.com/guide/
Related: Cuba country profile · live dashboard · central bank and release calendar · our posts on X