Countries › Dominican Republic › Guide › 12. Sectors › Electricity market and concessions
Electricity market and concessions
Last verified: 2026-10-30 · Status: Stable
Private and foreign capital may own generation and distribution, but transmission and hydroelectric generation stay in State hands. Plants feeding the grid need a definitive concession from the Executive for up to 40 years, processed through the SIE and the CNE. Below 2 MW no concession is needed, and users of 1 MW or more can buy directly from generators.
USD figures use the Banco Central de la República Dominicana reference selling rate of RD$60.9007 per US dollar, as shown on its home page on 30 October 2026, rounded to the cent.
Key facts
| Maximum term of a definitive concession | 40 yearsLey 125-01 art. 49, as of 2026-10-30 · in force |
|---|---|
| Generation below which no concession is needed | 2 MWDecreto 555-02 art. 60, as of 2026-10-30 · in force |
| Non regulated user threshold | 1 MWLey 125-01 art. 108 paragraph I, as of 2026-10-30 · in force |
| Non regulated user technical contribution | 10 %Ley 125-01 art. 108 paragraph II, as of 2026-10-30 · in force |
| Generation a distributor may own | 15 % of peak demandLey 125-01 art. 11 paragraph I, as of 2026-10-30 · in force |
| Transmission and hydroelectric generation | State only Ley 125-01 art. 131, as of 2026-10-30 · in force |
The rule
Cost to do it: Publication of the grant is at the applicant's cost (art. 65 paragraph). No official fee schedule for the application was found.Decreto 555-02, art. 62 and 64, 2002-07-19 official text · verified 2026-10-30
Cost to do it: 10% of the contract price. On a monthly contract bill of RD$10,000,000 (about US$164,201.73), the contribution is RD$1,000,000 (about US$16,420.17).
Example: RD$1,000,000 a month on a RD$10,000,000 contract / US$16,420.17 a month on a US$164,201.73 contractLey 125-01 as amended by Ley 186-07, art. 108 paragraphs II and III, 2007-08-06 official text · verified 2026-10-30
| Activity | Private or foreign capital | Permit |
|---|---|---|
| Thermal, solar and wind generation above 2 MW | Yes | Definitive concession from the Executive |
| Generation below 2 MW | Yes | No concession, technical rules apply |
| Distribution | Yes | Definitive concession with a defined zone |
| Transmission | No, State only (art. 131) | Not available, except a special connection line (art. 41 paragraph III) |
| Hydroelectric generation | No, State only under Ley 125-01 (art. 131) | See the trap on Ley 57-07 |
| Sale to users of 1 MW or more | Yes | Non regulated user status and SIE rules |
Who may do what in the electricity chain
Worked example
- A foreign group plans a 50 MW solar plant. It sets up or registers a local vehicle, takes a provisional concession to study the land, files for the definitive concession at the SIE with an environmental study, and waits for the CNE (25 working days after the SIE report) and the Executive. It may build the connection stretch, but the transmission company operates it (art. 11).
- A factory with 3 MW of demand moves to UNR status and signs a generator at a monthly bill of RD$10,000,000 (about US$164,201.73). The 10% contribution of RD$1,000,000 (about US$16,420.17) is paid by the generator, so expect it to be priced into the contract.
Step by step
- Check that the activity is open: transmission and hydro are not.
- Secure land rights and ask the SIE for a provisional concession if third party land must be studied.
- Obtain the environmental authorization and the no objection certificate (art. 45).
- File for the definitive concession at the SIE.
- SIE report to the CNE, CNE recommendation within 25 working days, then Executive authorization.
- Sign the power contract, or enter the tender process of the distributors.
- Register as a market agent with the Organismo Coordinador before injecting energy.
Common traps
- Ley 125-01 art. 41 paragraph IV bars hydro concessions, while Ley 57-07 lists hydro plants up to 5 MW for incentives. We found no text reconciling them, so confirm with the CNE before budgeting a mini hydro.
- The official compendium is a 2012 edition. Decreto 167-21 and other later changes to the regulation are not in it.
- A transfer of the concession by merger or between related companies still needs SIE approval (Decreto 555-02 art. 82). Check this before any share or asset deal.
- The ban on generators linked to distributors carries a 120 day divestment clock and penalties of up to 5% of assets. Screen group structures before bidding.
- No official current fee schedule for concession filings was found, so none is given.
Sources
- Ley 125-01 and Reglamento, SIE compendium
- Decreto 555-02, Edesur copy
- Ley 186-07, Ministry of Energy and Mines
- CNE notice on Resolución SIE-092-2025-LCE
- Decreto 342-20, Ministry of Energy and Mines
- Memoria MEM 2022 on Ley 365-22
Related pages
- sectors/distributed-generation-and-rooftop-solar
- investing/renewable-energy-incentives
- investing/project-permits-and-one-stop-shop
- sectors/key-sectors-and-regulators
- /country/dominican-republic/
- /calendar/
- Live dashboard
Related: Dominican Republic country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.