Countries › Ecuador › Guide › 3. Investing › Environmental permits and consultation in Ecuador: SUIA, impact levels and who the State must consult
Environmental permits and consultation in Ecuador: SUIA, impact levels and who the State must consult
Last verified: 2026-11-15 · Status: Changing
Every project, work or activity is classified by impact in the SUIA system, and the permit type follows automatically. Medium and high impact projects need an impact study and an environmental bond. The State, not the investor, must consult affected communities: indigenous peoples have a separate right, and the 2023 ruling that struck the consultation decree is still waiting for a law from the Assembly.
Ecuador is dollarized: the US dollar is the currency in use, so local currency and USD amounts are the same and no conversion is applied.
Key facts
| Impact levels | Non significant, low, medium, high textCódigo Orgánico del Ambiente art. 172, as of 2026-10-30 · in force |
|---|---|
| Impact study required for | Medium and high impact textCódigo Orgánico del Ambiente art. 179, as of 2026-10-30 · in force |
| Environmental consultation law | Not found at 30 October 2026; Decreto 754 applied provisionally textSentencia 51-23-IN/23, as of 2026-10-30 · pending |
The rule
Cost to do it: Study by a registered consultant. Consultant costs and permit fees vary and were not verified.
Example: A US$30,000,000 plant rated medium impact needs the study. Size in dollars does not decide it: the impact rating does. / Same figure: Ecuador uses the US dollar.Código Orgánico del Ambiente, Registro Oficial Suplemento 983, 12 April 2017, copy to 21 December 2021, art. 179, 2017-04-12 official text · verified 2026-10-30
Cost to do it: Premium or guarantee cost depends on the activity.Código Orgánico del Ambiente, Registro Oficial Suplemento 983, 12 April 2017, copy to 21 December 2021, art. 183, 2017-04-12 official text · verified 2026-10-30
| Consultation | Who it protects | Who runs it | Effect of opposition | Source |
|---|---|---|---|---|
| Environmental | Affected community | The State | Higher body decides by reasoned resolution | Constitution art. 398 |
| Prior, free and informed | Indigenous peoples | The State | Proceeds under Constitution and law | Constitution art. 57 no. 7 |
| Legislative prior | Collective rights | Assembly | Applies to bills | Constitution art. 57 no. 17 |
Do not mix these up
Worked example
- A US$30,000,000 food plant enters SUIA, is rated medium impact, hires a registered consultant for the study and management plan, runs participation through the authority and posts a policy. A mining project on indigenous land also needs prior consultation run by the State. Skipping it puts the permit, and a project of any size, at risk.
Step by step
- Register in SUIA early, before you commit land.
- Map water, protected areas and indigenous territories.
- Budget for the study, facilitator and guarantee.
- Ask the authority to run consultation early and in good faith.
- List permits in any investment contract file.
- Keep the management plan and audits current.
Common traps
- The State must consult, and an investor's own community meetings do not replace it.
- The Código copy we read is dated to 2021 and excludes the 2026 reform. Check for later changes.
- The regulation to the code was not read for this page, so we state no permit names, fees or days beyond the code.
- Provincial and municipal governments also run licence procedures, as gob.ec sheets for Guayas and Quito show. Confirm which authority is competent for your site.
- Consultation fights are decided in the constitutional courts: see disputes/constitutional-actions.
- Mining permits now use the words environmental administrative authorization. Check how this maps to the older licence in your stage.
Sources
- Código Orgánico del Ambiente, copy to 2021
- Constitution
- Sentencia 51-23-IN/23
- Court note on the ruling
- Registro Oficial 360
- Registro Oficial Quinto Suplemento 234 (2 March 2026), mining law reform incl. new art. 26
- Registro Oficial Tercer Suplemento 496 (9 February 2024), Decreto Ejecutivo 157, Reglamento General LOEEGE
Related pages
- investing/restricted-activities-and-sector-limits
- investing/investment-contracts
- disputes/constitutional-actions
- macro/oil-mining-and-energy
- /country/ecuador/
- /calendar/
- Live dashboard
Related: Ecuador country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.