Public private partnerships in Ecuador: the 2023 law, a US$20 million floor and terms up to 40 years
Last verified: 2026-10-30 · Status: Changing
PPPs now run under Book II of the 2023 Efficiency Law, not the 2015 law most summaries still quote. Projects must be worth at least US$20 million, or US$10 million for local governments, are tendered competitively and last 5 to 30 years, extendable to 40. The Secretaría de Inversiones Público Privadas was folded into the infrastructure ministry in 2025, and the 2015 income tax exemption is gone.
Ecuador is dollarized: the US dollar is the currency in use, so local currency and USD amounts are the same and no conversion is applied. Amounts tied to the basic wage use US$482 a month, the 2026 figure.
Key facts
| Minimum project value | 20000000 USDRGL art. 228, as of 2026-10-30 · in force |
|---|---|
| Minimum value for local governments | 10000000 USDRGL art. 228, as of 2026-10-30 · in force |
| Minimum term | 5 yearsLey APP art. 47, as of 2026-10-30 · in force |
| Maximum term with extension | 40 yearsLey APP art. 47, as of 2026-10-30 · in force |
| Maximum bonus for proposer | 10 pointsLey APP art. 36, as of 2026-10-30 · in force |
| Cap on changes | 20 %Ley APP art. 49, as of 2026-10-30 · in force |
The rule
Cost to do it: Project floor of US$20,000,000, or US$10,000,000 for local governments.
Example: A US$15,000,000 municipal market qualifies; a US$15,000,000 national project does not. / Same figure: Ecuador uses the US dollar.Reglamento General de la Ley Orgánica de Eficiencia Económica y Generación de Empleo, Decreto Ejecutivo 157, Registro Oficial Tercer Suplemento 496, 9 February 2024, SRI copy to 14 March 2024, art. 228; Ley APP art. 2, 2024-02-09 official text · verified 2026-10-30
Cost to do it: Formation of an S.A. See entities/compania-anonima.Ley Orgánica de Eficiencia Económica y Generación de Empleo, Book II (Ley APP), Registro Oficial Suplemento 461, 20 December 2023, art. 15, 2023-12-20 official text · verified 2026-10-30
Cost to do it: All study costs fall on the proposer until refund.Ley Orgánica de Eficiencia Económica y Generación de Empleo, Book II (Ley APP), Registro Oficial Suplemento 461, 20 December 2023, arts. 33 and 34, 2023-12-20 official text · verified 2026-10-30
Example: US$2,000,000 of approved study costs comes back within six months if a rival wins, and nothing comes back if the tender is void. / Same figure: Ecuador uses the US dollar.Ley Orgánica de Eficiencia Económica y Generación de Empleo, Book II (Ley APP), Registro Oficial Suplemento 461, 20 December 2023, arts. 36 and 37, 2023-12-20 official text · verified 2026-10-30
| Stage | Lead for central government | Key output |
|---|---|---|
| Planning and eligibility | Delegating entity and PPP unit, CIAPP | National PPP Registry entry |
| Structuring | PPP unit with entity | Business case, risk matrix, fiscal opinion |
| Tender | PPP unit | Award |
| Contract | Delegating entity and S.A. | Signed contract, supervision |
Project cycle under art. 32 and the CIAPP guides
Worked example
- A consortium proposes a US$60,000,000 toll road. It pays for studies of US$2,000,000. CIAPP declares public interest, and the project is tendered with an 8 point bonus for the consortium. If a rival wins, the rival refunds the approved costs within six months. If the consortium wins, it sets up a sole purpose S.A. and can ask for a separate investment contract for tax stability.
Step by step
- Check the National PPP Registry and the priority sectors.
- Confirm the value clears the floor.
- Check the current window for private initiatives.
- Plan for the sole purpose S.A. and lender step in rights.
- Seek Attorney General approval of any arbitration clause.
- Sign a separate investment contract if you want tax stability.
Common traps
- Search results still point to the 2015 law and Decreto 1040. Its core was repealed: use Book II of the 2023 law and RGL Book on PPP.
- The law still names the SIPP, and the Efficiency Law copy we read runs to January 2024.
- The press said 7 projects worth about US$2.3 billion entered the registry in April 2024. We found no official 2026 count and no 2026 award.
- The Ninth Transitory Provision let private initiatives filed in 2024 and 2025 reach the top 10 point bonus. That window has passed, so a new filing should expect the bonus set for it within the 3 to 10 range.
- In July 2026 Celec's manager said electricity PPPs needed a law reform, so test power projects with care.
- LRTI art. 9.3 is printed in the code as an empty heading. It gives no exemption.
Sources
- Efficiency Law, Book II, SRI copy
- General regulation, SRI copy
- Integrity Law
- APP Ecuador norms page
- Ministry service sheet
- Primicias report on Decreto 276 (press, secondary)
- El Oriente report on electricity PPPs (press, secondary)
Related pages
- investing/tax-and-legal-stability
- investing/selling-to-the-state
- disputes/arbitration-with-the-state
- entities/compania-anonima
- /country/ecuador/
- /calendar/
- Live dashboard
Related: Ecuador country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.