Project permits and environmental assessment

Last verified: 2026-11-15 · Status: Changing

Projects need an environmental permit from MARN and, at 250 square meters or more, construction permits from the national DOT. The environment ministry has 60 working days for a study, extendable by 60, and it categorizes each project by scale and potential impact. A bond must cover the cost of the required environmental works.

El Salvador is dollarized, so every amount here is already in US dollars, which have unrestricted legal tender (Decreto Legislativo Nº 201 of 30 November 2000, Ley de Integración Monetaria, art. 3). Colón equivalents use the fixed rate of ¢8.75 per US$1 set in art. 1 of the same law (https://www.asamblea.gob.sv/sites/default/files/documents/decretos/104A5755-354C-416D-A944-7314F6359CFF.pdf) and are for reference only.

Key facts

Impact study evaluation60 working daysDecreto 233 art. 24, as of 2026-11-15 · in force
Permit issue after approval10 working daysDecreto 233 art. 24, as of 2026-11-15 · in force
Area for national construction permit250 square metersDecreto 122 art. 3, as of 2026-11-15 · in force

The rule

1. Listed activities and projects need an environmental permit, issued after the impact study is approved.Decreto Legislativo Nº 233, Ley del Medio Ambiente, Art. 19, 1998-03-02 official text · verified 2026-11-15
2. Impact studies are needed for listed works such as roads, rail, airports, ports, pipelines and other projects.Decreto Legislativo Nº 233, Ley del Medio Ambiente, Art. 21, 1998-03-02 official text · verified 2026-11-15
3. The holder files the environmental form, a sworn statement in practice, and the ministry categorizes the project by scale and potential impact.Decreto Legislativo Nº 233, Ley del Medio Ambiente, Art. 22, 1998-03-02 official text · verified 2026-11-15
4. Studies are paid by the holder, and prepared by a multidisciplinary team.Decreto Legislativo Nº 233, Ley del Medio Ambiente, Art. 23, 1998-03-02 official text · verified 2026-11-15
5. Evaluation takes up to 60 working days, including public consultation, and can be extended by 60 for complex projects. The permit follows within 10 working days.Decreto Legislativo Nº 233, Ley del Medio Ambiente, Art. 24, 1998-03-02 official text · verified 2026-11-15
6. Public notice lasts 10 working days at the holder cost.Decreto Legislativo Nº 233, Ley del Medio Ambiente, Art. 25, 1998-03-02 official text · verified 2026-11-15
7. A compliance bond equal to the full cost of the works in the management plan stays until they are done.Decreto Legislativo Nº 233, Ley del Medio Ambiente, Art. 29, 1998-03-02 official text · verified 2026-11-15
8. The DOT authorizes new subdivisions and construction of 250 square meters or more. Smaller projects go to municipalities, municipal associations or planning offices, but the DOT still authorizes the prerequisite procedures listed in arts. 38, 40 and 42.Decreto Legislativo Nº 122, Ley de Creación de la DOT, Art. 2, 3, 2024-10-16 official text · verified 2026-11-15 · changed: Law of October 2024 (D.O. 205, T. 445, 28 October 2024) centralized large permits. D.L. 437 of 21 October 2025 (D.O. 202, T. 449, 27 October 2025) gave permits under 250 square meters to municipalities, municipal associations and planning offices, while the DOT keeps the prerequisite procedures of arts. 38, 40 and 42.
9. Anyone can request a territorial condition report for a fee, delivered within five working days, for information only.Decreto Legislativo Nº 122, Ley de Creación de la DOT, Art. 35, 2024-10-16 official text · verified 2026-11-15
10. Permits run in three phases: feasibility, permits, and compliance checks.Decreto Legislativo Nº 122, Ley de Creación de la DOT, Art. 36, 2024-10-16 official text · verified 2026-11-15
11. Notice of start of works is due at least 15 working days before starting.Decreto Legislativo Nº 122, Ley de Creación de la DOT, Art. 41, 2024-10-16 official text · verified 2026-11-15
12. No DOT request is processed until the fee set in the art. 47 table is paid, and other public bodies and municipalities may not charge extra fees on works within DOT competence.Decreto Legislativo Nº 122, Ley de Creación de la DOT, Art. 47, 48, 2024-10-16 official text · verified 2026-11-15

Worked example

  • Timeline for a project that needs an impact study: up to 60 working days of evaluation, up to 60 more if extended, and 10 to issue the permit: 130 working days at worst, or about six months, before any filing errors. A plan with US$500,000 of mitigation works needs a bond of US$500,000 (¢4,375,000.00).

Step by step

  1. Ask for a DOT territorial report early.
  2. File the environmental form so MARN can categorize the project.
  3. Prepare the impact study if required.
  4. Run consultation.
  5. Post the bond.
  6. Pay the DOT fee, then apply for DOT feasibility and permits.
  7. Give notice 15 working days before work.

Common traps

  • MARN permit fees and its current categorization guidance could not be checked, because the ministry sites block automated access, so none are given.
  • Art. 24 c) still cites the old administrative court law on silence. Do not assume approval.
  • The DOT report does not bind later permits.
  • Below 250 square meters the municipality issues the permit, but the DOT procedures of arts. 38, 40 and 42 still apply.
  • Municipal rules can add steps, as the State Department notes.
  • The State Department reports discretion in permits.

Sources

Related pages

Related: El Salvador country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.