Environmental licensing in Honduras: SINEIA categories 1 to 4, the 2021 categorization table, public notice and fines up to L1,000,000
Last verified: 2026-11-03 · Status: Stable
Under the Ley General del Ambiente (Decreto 104-93) every project or activity that may pollute or degrade the environment needs a prior environmental impact assessment, and every project needs an environmental license from MiAmbiente. The SINEIA regulation sorts projects into categories 1 (low) to 4 (very high impact) using the 2021 categorization table; activities below category 1 need no license. Category 4 adds a full impact study, press and radio notices and 30 business days of public access. Administrative fines run from L1,000 to L1,000,000.
USD figures use L26.9080 per US dollar, the Banco Central de Honduras reference exchange rate (buying) for 3 November 2026, from the BCH daily dollar price series retrieved on the verification date. Conversions are for orientation only.
Key facts
| Prior environmental impact assessment required | Yes, for activities that may pollute or degrade textDecreto 104-93 art. 5, as of 1993-06-30 · in force |
|---|---|
| Environmental license categories | 4 categoriesSINEIA art. 30, as of 2019-08-21 · in force |
| Maximum administrative environmental fine | 1000000 HNLDecreto 104-93 art. 97, as of 1993-06-30 · in force |
| Minimum administrative environmental fine | 1000 HNLDecreto 104-93 art. 97, as of 1993-06-30 · in force |
| Public access to category 4 impact study | 30 business daysSINEIA art. 28, as of 2019-08-21 · in force |
| Hotel rooms at which category 1 licensing starts | 25 roomsAM 705-2021 item 293, as of 2021-05-10 · in force |
The rule
Cost to do it: L1,000 to L1,000,000 (US$37.16 to US$37,163.67).
Example: Operating a category 2 plant without a license: up to L1,000,000 plus suspension. / Up to about US$37,164.Decreto Nº 104-93, Art. 87, 88, 96 and 97, 1993-06-30 official text · verified 2026-11-03
| Category | Impact or risk | Hotel example | What the file needs |
|---|---|---|---|
| Below 1 | Very low | Under 25 rooms | No license; optional certificate of not requiring one |
| 1 | Low | 25 to 50 rooms | SLAS online file and license |
| 2 | Moderate | 51 to 100 rooms | SLAS file with technical documents |
| 3 | High | More than 100 rooms | Environmental impact or audit study by registered consultants |
| 4 | Very high, megaprojects | Not listed for hotels | Full impact study, five copies, press and radio notices, 30 business days of public access |
SINEIA categories (Reglamento art. 30) with sample thresholds from the 2021 table
Worked example
- A 60 room beach hotel is category 2. The developer files through the SLAS with a registered environmental consultant, posts the mitigation guarantee and signs the compliance contract before the license. Building without it exposes the project to fines up to L1,000,000 (US$37,164) and suspension. A 120 room resort would be category 3 and needs a full impact study.
Step by step
- 1. Find the project's ISIC code and size parameter in the 2021 categorization table; if absent, request a category from MiAmbiente in writing.
- 2. Hire a consultant registered with MiAmbiente; they are jointly liable for the data filed.
- 3. File through the SLAS; for categories 3 and 4 prepare the study and the public notices and consultation.
- 4. Post the mitigation guarantee and sign the compliance contract to obtain the license.
- 5. On acquisition of a licensed project, record the license assignment by public deed.
Common traps
- The table measures size by parameters such as rooms, square meters or megawatts; a phased project may cross a category line in a later phase.
- Sites in protected or fragile areas need the managing agency's opinion first, which adds time.
- Buying a project without assigning its license leaves the buyer exposed to the seller's unmet mitigation measures.
- Criminal environmental offences are now governed by the 2019 Penal Code, so the old criminal articles of Decreto 104-93 should not be relied on alone.
Sources
- Decreto 104-93, Ley General del Ambiente, La Gaceta 27,083 of 30 June 1993 (Tribunal Superior de Cuentas)
- Acuerdo Ejecutivo 005-2019 reforming the SINEIA regulation, La Gaceta 35,028 of 21 August 2019 (FAOLEX gazette copy)
- Acuerdo Ejecutivo 011-2016 on the guarantee certificate, La Gaceta 34,245 of 21 January 2017 (FAOLEX gazette copy)
- Acuerdo Ministerial 705-2021, Tabla de Categorización Ambiental, La Gaceta 35,595 of 10 May 2021 (Tribunal Superior de Cuentas)
- Decreto 80-2020 on lead acid batteries, La Gaceta 35,546 of 17 March 2021 (Tribunal Superior de Cuentas)
- BCH daily dollar price series
Related pages
- sectors/mining-concessions-and-consultation
- sectors/renewable-energy-incentives
- real-estate/buying-property
- regulation/regulatory-landscape
- /country/honduras/
- /calendar/
- Live dashboard
Related: Honduras country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.