Countries › Nicaragua › Guide › 3. Investing › Environmental permits for projects: the MARENA categories and timelines
Environmental permits for projects: the MARENA categories and timelines
Last verified: 2026-11-03 · Status: Changing
Projects are classified in five environmental categories under Decreto N°. 20-2017, reformed in May 2025. Category I special projects (national roads, canals, hydrocarbons, refineries, cross border basins) need an environmental impact study; Category II (geothermal, metal mining, hydro above 100 MW, ports, large dredging, airports) now needs an environmental management programme decided in 30 business days; Categories III and IV are handled by MARENA departmental offices in 15 business days. Permits lapse if the project is not developed and renewal is not sought in time.
Key facts
| Decision period for Category II environmental permits | 30 business daysDecreto N°. 20-2017 art. 35 as reformed by Decreto N°. 06-2025, as of 2026-11-03 · in force |
|---|---|
| Decision period for Category III and IV authorizations | 15 business daysDecreto N°. 20-2017 art. 35 as reformed by Decreto N°. 06-2025, as of 2026-11-03 · in force |
| Months to develop a permitted project before it cannot be renewed | 18 monthsDecreto N°. 20-2017 art. 39, as of 2026-11-03 · in force |
The rule
| Category | Typical projects | Instrument | Decision period |
|---|---|---|---|
| I | National roads, canals, hydrocarbons, refineries, pipelines, shared basins | Environmental impact study | Depends on project |
| II | Geothermal, metal mining, hydro above 100 MW, ports, airports | Environmental management programme | 30 business days |
| III | Moderate impact projects | Environmental valuation and management programme | 15 business days |
| IV | Low impact projects | Environmental measures in a management programme | 15 business days |
| V | Experimental projects | Provisional valuation | 15 business days |
Categories and instruments after the 2025 reform
Worked example
- A 50 MW geothermal project is Category II whatever its size. The developer files with MARENA central, expects a decision within 30 business days of a complete file, and must start works within 18 months or ask for renewal 30 business days before expiry.
Step by step
- Classify the project under art. 14 to 19 and identify whether MARENA central, a departmental office or a Caribbean regional council decides.
- Prepare the impact study or management programme with a registered consultant.
- Keep the file moving; inactivity lapses it after 3 or 6 months.
- Calendar renewal 30 business days before expiry and plan for at most two renewals.
Common traps
- Older guides list Category II as needing an impact study; since May 2025 it needs a management programme.
- Article numbers may shift once the consolidated text is published.
- Ley N°. 1240 art. 13 also makes foreign investors liable to restore environmental damage in full.
Sources
- Decreto Ejecutivo N°. 20-2017, Sistema de Evaluación Ambiental de Permisos y Autorizaciones, La Gaceta N°. 228 of 29 November 2017
- Decreto Presidencial N°. 06-2025, reform to Decreto N°. 20-2017, La Gaceta N°. 80 of 7 May 2025
- Ley N°. 1240, Ley de Inversiones Extranjeras, La Gaceta N°. 36 of 24 February 2025
Related pages
- investing/renewable-energy-incentives
- investing/foreign-investment-regime
- /calendar/
- /country/nicaragua/
- Live dashboard
Related: Nicaragua country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.