Environmental permits for projects: the MARENA categories and timelines

Last verified: 2026-11-03 · Status: Changing

Projects are classified in five environmental categories under Decreto N°. 20-2017, reformed in May 2025. Category I special projects (national roads, canals, hydrocarbons, refineries, cross border basins) need an environmental impact study; Category II (geothermal, metal mining, hydro above 100 MW, ports, large dredging, airports) now needs an environmental management programme decided in 30 business days; Categories III and IV are handled by MARENA departmental offices in 15 business days. Permits lapse if the project is not developed and renewal is not sought in time.

Key facts

Decision period for Category II environmental permits30 business daysDecreto N°. 20-2017 art. 35 as reformed by Decreto N°. 06-2025, as of 2026-11-03 · in force
Decision period for Category III and IV authorizations15 business daysDecreto N°. 20-2017 art. 35 as reformed by Decreto N°. 06-2025, as of 2026-11-03 · in force
Months to develop a permitted project before it cannot be renewed18 monthsDecreto N°. 20-2017 art. 39, as of 2026-11-03 · in force

The rule

1. The system covers sector and national investment plans, projects requiring environmental impact studies, projects requiring environmental valuation and management programmes, experimental activities and listed natural resource permits; MARENA is the authority.Decreto N°. 20-2017 as reformed by Decreto N°. 06-2025, Art. 2, 2025-05-07 official text · verified 2026-11-03
2. Category I special projects of national, binational or regional importance with high potential impact need an environmental impact study: major transport infrastructure, river and interoceanic canals, hydrocarbon exploration and production, refineries, fluid pipelines, projects in shared basins and water transfers above 100 m3 per second.Decreto N°. 20-2017 as reformed by Decreto N°. 06-2025, Art. 14, 2025-05-07 official text · verified 2026-11-03
3. Category II projects need an environmental management programme and include geothermal exploration with drilling and geothermal generation of any size, metal mining exploration, metal mining above 15 tonnes a day, mineral processing plants, new tailings dams, intensive shrimp farming, interdepartmental roads, hydro above 100 MW, large ports, dredging of 250,000 m3 or more, docks with dredging of 1 ha or more, shipyards and airports.Decreto N°. 20-2017 as reformed by Decreto N°. 06-2025, Art. 15, 2025-05-07 official text · verified 2026-11-03 · changed: May 2025: Decreto N°. 06-2025 moved several project types from Category I to II and replaced the impact study for Category II with a management programme.
4. Category III A projects with moderate impacts need an environmental valuation through a management programme, handled by MARENA departmental offices or the Caribbean regional councils; Category IV low impact projects (for example hydro under 1 MW, solar of 1 to 10 ha, hotels of up to 49 rooms in the 2017 list) follow environmental measures in a management programme.Decreto N°. 20-2017 (art. 18 list) and art. 16 as reformed by Decreto N°. 06-2025, Art. 16 and 18, 2025-05-07 official text · verified 2026-11-03
5. Decision periods: Category I depends on the project's size; Category II 30 business days; Categories III, IV and V 15 business days.Decreto N°. 20-2017 as reformed by Decreto N°. 06-2025, Art. 35, 2025-05-07 official text · verified 2026-11-03
6. Category II, III and IV projects in the Caribbean Coast autonomous regions are administered by the regional councils through their natural resources secretariats in coordination with MARENA.Decreto N°. 20-2017 as reformed by Decreto N°. 06-2025, Art. 7, 2025-05-07 official text · verified 2026-11-03
7. Category II applications lapse if not pursued for 6 months, and Category III and IV applications after 3 months.Decreto N°. 20-2017, Art. 37, 2017-11-29 official text · verified 2026-11-03
8. Renewal must be requested 30 business days before expiry, with at most two renewals; projects not developed within 18 months of the permit and not renewed in time must start over; permits can be assigned with MARENA's prior authorization.Decreto N°. 20-2017, Art. 38 to 40, 2017-11-29 official text · verified 2026-11-03
9. Expansions that increase identified impacts need a new authorization or permit; modifications only need an updated management programme.Decreto N°. 20-2017 as reformed by Decreto N°. 06-2025, Art. 42 and 43, 2025-05-07 official text · verified 2026-11-03
10. The 2025 reform ordered publication of a consolidated, renumbered text of Decreto N°. 20-2017, so article numbers may change.Decreto N°. 06-2025, Art. tercero, 2025-05-07 official text · verified 2026-11-03
CategoryTypical projectsInstrumentDecision period
INational roads, canals, hydrocarbons, refineries, pipelines, shared basinsEnvironmental impact studyDepends on project
IIGeothermal, metal mining, hydro above 100 MW, ports, airportsEnvironmental management programme30 business days
IIIModerate impact projectsEnvironmental valuation and management programme15 business days
IVLow impact projectsEnvironmental measures in a management programme15 business days
VExperimental projectsProvisional valuation15 business days

Categories and instruments after the 2025 reform

Worked example

  • A 50 MW geothermal project is Category II whatever its size. The developer files with MARENA central, expects a decision within 30 business days of a complete file, and must start works within 18 months or ask for renewal 30 business days before expiry.

Step by step

  1. Classify the project under art. 14 to 19 and identify whether MARENA central, a departmental office or a Caribbean regional council decides.
  2. Prepare the impact study or management programme with a registered consultant.
  3. Keep the file moving; inactivity lapses it after 3 or 6 months.
  4. Calendar renewal 30 business days before expiry and plan for at most two renewals.

Common traps

  • Older guides list Category II as needing an impact study; since May 2025 it needs a management programme.
  • Article numbers may shift once the consolidated text is published.
  • Ley N°. 1240 art. 13 also makes foreign investors liable to restore environmental damage in full.

Sources

Related pages

Related: Nicaragua country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.