Public private partnerships under Ley N°. 935

Last verified: 2026-11-03 · Status: Stable

PPPs for infrastructure and public services are run by the finance ministry's Dirección General de Inversiones Públicas (DGIP). The winner must form a single purpose Nicaraguan company within 30 business days, the contract is signed as a public deed and only enters into force when the National Assembly approves it by law, without amendments. Disputes go to mediation and then arbitration, and private proposals can enter through a yearly call.

Key facts

Days to form the PPP single purpose company after award30 business daysLey N°. 935 art. 9, as of 2026-11-03 · in force
PPP contract needs approval by lawYes textLey N°. 935 art. 23, as of 2026-11-03 · in force
Creditor majority to name a replacement after default75 %Ley N°. 935 art. 29, as of 2026-11-03 · in force

The rule

1. The law regulates public sector participation with the private sector in formulating, contracting, financing, executing, operating and ending PPP projects for infrastructure and public services.Ley N°. 935, Ley de Asociación Público Privada, Art. 1 and 2, 2016-10-12 official text · verified 2026-11-03
2. Projects are self sustaining (user tariffs cover all costs and an adequate return) or subsidized (needing State transfers or guarantees); in both the State may share in profits and ownership.Ley N°. 935, Art. 5, 2016-10-12 official text · verified 2026-11-03
3. The finance ministry (MHCP) through the DGIP applies the law, values and records firm and contingent liabilities, and identifies projects with contracting institutions.Ley N°. 935, Art. 6 to 8 and 12, 2016-10-12 official text · verified 2026-11-03
4. The winning bidder must form a Nicaraguan single purpose company within 30 business days, with "de APP" at the end of its name.Ley N°. 935, Art. 9, 2016-10-12 official text · verified 2026-11-03
5. Once a year the DGIP opens a call for private initiative projects with prefeasibility studies; if approved, the project passes to the contracting institution, the proponent is compensated as the call provides, and a tender must be called within two years.Ley N°. 935, Art. 14, 2016-10-12 official text · verified 2026-11-03
6. Offers are evaluated by a commission of two DGIP members, one Presidency member and two members from the contracting institution, deciding by simple majority.Ley N°. 935, Art. 17, 2016-10-12 official text · verified 2026-11-03
7. Contracts are signed in public deed before the State Notary; they, their assignment and substantial changes must be approved by law, on the President's initiative, and deputies may not amend the signed contract; it enters into force on approval.Ley N°. 935, Art. 20 and 23, 2016-10-12 official text · verified 2026-11-03
8. The contract may be assigned only once in operation, with MHCP authorization and National Assembly approval; if the Assembly rejects the contract it is cancelled at no cost to the State.Ley N°. 935, Art. 18 and 25, 2016-10-12 official text · verified 2026-11-03
9. Compensation for unforeseen acts of authority is possible only for post signing sector specific measures that significantly alter the contract's economics.Ley N°. 935, Art. 27, 2016-10-12 official text · verified 2026-11-03
10. If the private partner seriously breaches or abandons the project, creditors holding 75% may within 30 business days name a replacement company, to be offered the contract within 90 business days.Ley N°. 935, Art. 29, 2016-10-12 official text · verified 2026-11-03
11. PPP contracts must contain a dispute clause providing mediation first and then binding arbitration under Ley N°. 540; the contract and partner are subject to Nicaraguan law and courts whatever the origin of their capital.Ley N°. 935, Art. 31 and 34, 2016-10-12 official text · verified 2026-11-03

Worked example

  • A toll road consortium wins a tender. Within 30 business days it forms "Autopista Sur, S.A. de APP", signs the public deed contract, and waits for the President to send it to the National Assembly; until the law approving it is passed, the State may cancel without cost (art. 18), so lenders should not fund before approval.

Step by step

  1. Watch for the DGIP's yearly private initiative call if you have your own project.
  2. Form the single purpose company and obtain the RUIE.
  3. Model the time to legislative approval; the contract has no force before it.
  4. Agree step in rights with lenders around the 75% creditor rule.

Common traps

  • Ley N°. 935 refers disputes to Ley N°. 540 arbitration; DIRAC, which accredited arbitration centres, was abolished by Ley N°. 1287 in October 2026, so draft the institutional arbitration clause carefully.
  • Deputies cannot amend but can reject the contract.
  • State contracts with arbitration clauses need the Procuraduría's prior opinion (see disputes/investment-arbitration).

Sources

Related pages

Related: Nicaragua country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.