Countries › Nicaragua › Guide › 12. Sectors › Electricity licences, concessions and tax treatment
Electricity licences, concessions and tax treatment
Last verified: 2026-11-04 · Status: Stable
Generation above the regulatory minimum and transmission need a licence from the energy ministry for up to 30 years; distribution needs a concession of up to 30 years granted by tender or direct negotiation; imports and exports need a licence of up to 10 years. Contracts take effect on publication in La Gaceta. Fuel for power generation and electricity imports and exports are tax exempt.
USD and córdoba conversions use C$36.6243 per US dollar, the 2026 official exchange rate shown by the Banco Central de Nicaragua in its monetary panorama table (Cuadro 2) dated 30 September 2026, the latest table retrieved on the verification date; the official rate has been unchanged since 2024. Amounts the law sets in dollars are payable in córdobas at the official rate. Conversions are for orientation only.
Key facts
| Maximum term of generation and transmission licences and distribution concessions | 30 yearsLey N°. 272 art. 66 and 70, as of 2026-11-04 · in force |
|---|---|
| Maximum term of electricity import and export licences | 10 yearsLey N°. 272 art. 70 bis, as of 2026-11-04 · in force |
| Maximum term of a provisional study licence | 2 yearsLey N°. 272 art. 68, as of 2026-11-04 · in force |
The rule
| Title | Term | Renewal | Source |
|---|---|---|---|
| Provisional licence (studies) | Up to 2 years | Per regulation | Art. 68 |
| Generation licence (natural resources) | Up to 30 years | Equal period | Art. 66, 78 |
| Transmission licence | Up to 30 years | Equal period | Art. 70, 78 |
| Distribution concession | Up to 30 years | Equal period | Art. 66, 71, 78 |
| Import or export licence | Up to 10 years | Equal period | Art. 70 bis |
Titles and terms
Worked example
- A 20 MW solar developer gets a two year provisional licence for studies, then a generation licence of up to 30 years published in La Gaceta. Equipment imports for public supply can be exempt for three years under art. 130, and renewable incentives under Ley N°. 532 may add more (see investing/renewable-energy-incentives). Any breach can cost up to US$100,000 (C$3,662,430) per fine under art. 126.
Step by step
- Apply for a provisional licence and run resource studies.
- Obtain the environmental permit and any water or land rights.
- Apply for the definitive licence, pay the ministry fee and sign the contract.
- Publish the contract in La Gaceta; it takes effect then.
- Request transmission connection and register with CNDC.
Common traps
- The ministry may reject applications with no compensation for bid costs (art. 73).
- Unauthorized transfers of a licence or concession are void (art. 84); check whether the contract treats a change of control as a transfer.
- Fees for licences are set by ministry act, not the law; confirm the current schedule with the ministry before budgeting.
Sources
- La Gaceta N°. 130 of 14 July 2021 (Ley N°. 272 consolidated)
- La Gaceta N°. 218 of 25 November 2021 (Ley N°. 1094)
- Banco Central de Nicaragua, Cuadro 2, 30 September 2026
Related pages
- sectors/electricity-market
- investing/renewable-energy-incentives
- investing/environmental-permits
- taxes/excise-taxes
Related: Nicaragua country profile · live dashboard · central bank and release calendar · our posts on X