Countries › Brazil › Guide › 12. Sectors › Power generation in Brazil: concessions, authorizations, regulated auctions and ANEEL fees
Power generation in Brazil: concessions, authorizations, regulated auctions and ANEEL fees
Last verified: 2026-10-27 · Status: Changing
Hydro potentials belong to the Union, and the size and use of a plant decide whether it needs a concession after bidding, an ANEEL authorization or only a notice. Distributors must buy all their energy in regulated auctions under long term contracts of up to 35 years for new plants, which is the main bankable revenue route for new generation, while the free market keeps opening. The 2025 power reform also shifted capacity reserve costs onto new generators that do not meet system requirements and let coal plants exit early.
Key facts
| Capacity above which hydro and public service thermal plants need a concession | 50000 kWLei nº 9.074 art. 5, as of 2026-10-27 · in force |
|---|---|
| Capacity above which thermal plants and hydro need an ANEEL authorization | 5000 kWLei nº 9.074 art. 7, as of 2026-10-27 · in force |
| Maximum supply term of regulated contracts for new plants | 35 yearsLei nº 10.848 art. 2 § 2 III, as of 2026-10-27 · in force |
| Maximum supply term of regulated contracts for existing plants | 15 yearsLei nº 10.848 art. 2 § 2 II, as of 2026-10-27 · in force |
| ANEEL inspection fee (TFSEE) | 0.4 % of annual economic benefitLei nº 9.427 art. 12 § 1, as of 2026-10-27 · in force |
| Minimum notice for early coal plant decommissioning | 6 monthsLei nº 9.074 art. 7 § 2, as of 2026-10-27 · in force |
The rule
Cost to do it: 0.4 percent of the annual economic benefit set by ANEEL for the plant.Lei nº 9.427 (ANEEL Law), as worded by Lei nº 12.783 of 11 January 2013, Art. 12 caput and § 1, 1996-12-26 official text · verified 2026-10-27
| Plant | Use | Grant |
|---|---|---|
| Hydro above 50 MW | Public service, independent producer or autoproducer | Concession after bidding |
| Thermal above 50 MW | Public service | Concession after bidding |
| Thermal above 5 MW | Independent producer or autoproducer | ANEEL authorization |
| Hydro above 5 MW up to 50 MW | Independent producer or autoproducer | ANEEL authorization |
| Hydro or thermal up to 5 MW | Any | Notice to the grantor only |
| Solar or wind micro and mini generation | Consumer generation | See Distributed generation page |
Which grant a power plant needs (Lei nº 9.074 arts. 5, 7 and 8).
Worked example
- A 30 MW small hydro plant selling to the regulated market: it needs an ANEEL authorization (Lei nº 9.074 art. 7 II), can sell in a new energy auction with delivery starting between the third and seventh year after the auction and a contract of up to 35 years (Lei nº 10.848 art. 2 § 2 III), and pays TFSEE at 0.4 percent of the annual benefit set by ANEEL. If it requested grid access after 24 November 2025 and does not meet the system requirements, it also bears a share of capacity reserve costs (Lei nº 9.074 art. 8-A).
Step by step
- 1. Size the plant and use to identify the grant: concession, authorization or notice.
- 2. Register the project with ANEEL and the river inventory where hydro is involved; check no other holder has an active registration on the stretch.
- 3. Obtain environmental licences and grid access; check whether art. 8-A capacity reserve charges apply.
- 4. Qualify with the energy planning agency and bid in regulated auctions, or sign free market PPAs.
- 5. Sign CCEARs with all distributors buying in the auction and post guarantees.
- 6. Budget TFSEE and sector charges from commercial operation.
Common traps
- Even plants of 5 MW or less, which need only a notice, must follow the river's approved fall division and cannot sit on a stretch where another party holds an active ANEEL registration (art. 8 §§ 1 and 3).
- Delivery under a new energy auction can start as late as the seventh year; financing must bridge construction to first revenue.
- New grid applicants after 24 November 2025 may carry capacity reserve costs until they meet system requirements, which changes merchant solar and wind economics.
- Free market buyers must contract 100 percent of their load; under contracting is penalized.
Sources
- Lei nº 9.074, consolidated, Congress normas.leg.br
- Lei nº 10.848 (power trading), Congress normas.leg.br
- Lei nº 9.427 (ANEEL Law), Congress normas.leg.br
- Lei nº 15.269 of 24 November 2025 (power sector reform), Congress normas.leg.br
- Constitution of Brazil, Congress normas.leg.br
Related pages
- sectors/key-sectors-and-regulators
- sectors/distributed-generation
- sectors/natural-gas-market
- investing/energy-transition-incentives
- investing/infrastructure-concessions-and-ppps
- real-estate/water-rights
- /calendar/
- /country/brazil/
- Live dashboard
Related: Brazil country profile · live dashboard · central bank and release calendar · our posts on X