Countries › Ecuador › Guide › 13. Regulation › Environmental liability in Ecuador: strict liability, no time bar and fines up to 300 basic wages
Environmental liability in Ecuador: strict liability, no time bar and fines up to 300 basic wages
Last verified: 2026-11-15 · Status: Changing
Liability for environmental damage is strict and claims do not lapse, and a valid permit is no defence. Report damage within 24 hours. Fine bases run from 1 to 200 basic wages by income group and gravity, up 50% with aggravating factors. Crimes add prison and company fines up to US$482,000.
Ecuador is dollarized: the US dollar is the currency in use, so local currency and USD amounts are the same and no conversion is applied. Amounts tied to the basic wage use US$482 a month, the 2026 figure set by Acuerdo Ministerial MDT-2025-195 (Registro Oficial Suplemento 187, 18 December 2025) as reported by INEC in its January 2026 basket report. The 2026 basic income tax allowance of US$12,208 is from SRI Resolución NAC-DGERCGC25-00000043, 29 December 2025.
Key facts
| Damage report | 24 hoursCódigo Orgánico del Ambiente art. 291, as of 2026-10-30 · in force |
|---|---|
| Top fine base, very serious, group D, 200 basic wages | 96400 USDCódigo Orgánico del Ambiente art. 326, as of 2026-10-30 · in force |
| Time limit for damage actions | None textCódigo Orgánico del Ambiente art. 305, as of 2026-10-30 · in force |
| Top company fine for environmental crime | 482000 USDCOIP art. 258, as of 2026-11-15 · in force |
| Basic unified wage (SBU) 2026, unit for fines | 482 USDAcuerdo Ministerial MDT-2025-195, Registro Oficial Suplemento 187, 18 December 2025, as of 2026-01-01 · in force |
| Basic income tax allowance 2026, unit for income groups | 12208 USDSRI Resolución NAC-DGERCGC25-00000043, 29 December 2025, as of 2026-01-01 · in force |
The rule
Example: At the 2026 allowance of US$12,208 (SRI Resolución NAC-DGERCGC25-00000043), group D starts at US$122,080 / US$122,080Código Orgánico del Ambiente, Registro Oficial Suplemento 983, 12 April 2017, copy to 21 December 2021, arts. 322 and 323, 2017-04-12 official text · verified 2026-11-15
Example: 200 basic wages + 50%: US$144,600 / US$144,600Código Orgánico del Ambiente, Registro Oficial Suplemento 983, 12 April 2017, copy to 21 December 2021, arts. 327 and 328, 2017-04-12 official text · verified 2026-10-30
Cost to do it: 100 to 1,000 basic wages; at the 2026 basic wage of US$482 (Acuerdo MDT-2025-195, per INEC), US$48,200 to US$482,000.
Example: US$48,200 to US$482,000 / US$48,200 to US$482,000Código Orgánico Integral Penal (COIP), Registro Oficial Suplemento 180, 10 February 2014, Defensoría Pública copy to Registro Oficial Séptimo Suplemento 382, 2 October 2026, art. 258, 2014-02-10 official text · verified 2026-11-15
| Income group | Light | Serious | Very serious |
|---|---|---|---|
| A | 1: US$482 | 5: US$2,410 | 10: US$4,820 |
| B | 1.5: US$723 | 15: US$7,230 | 50: US$24,100 |
| C | 2: US$964 | 35: US$16,870 | 100: US$48,200 |
| D | 2.5: US$1,205 | 75: US$36,150 | 200: US$96,400 |
Fine bases in basic wages, arts. 324 to 326 (dollars at US$482)
Worked example
- A plant in group D exceeds discharge limits: a very serious infraction, base US$96,400. Repeat conduct as an aggravating factor adds 50%, for US$144,600. Paying within 15 days of the final ruling cuts 10%, to US$130,140. Suspension and full repair are extra, and repair cost is often the largest item.
Step by step
- Keep permits and monitoring reports current.
- Set a 24 hour damage alert.
- Calculate your income group.
- Buy suitable cover where available.
- Check past damage in acquisitions, since claims do not lapse.
- Plan site closure with the authority.
Common traps
- A permit is no shield.
- The code copy we read stops at December 2021, and 2026 reforms exist, including RO 360.
- Fines are small next to repair and stoppage.
- Art. 325 serious items are mostly forestry and wildlife, so check the exact list.
- The allowance for the prior tax year applies, so the 2026 figure is only a guide.
Sources
- Código Orgánico del Ambiente, public copy
- COIP to Registro Oficial 382 (2 October 2026), Defensoría Pública copy
- Registro Oficial 360
- SRI Resolución NAC-DGERCGC25-00000043 (2026 income tax table, US$12,208 basic allowance)
- INEC Informe Ejecutivo Canastas, January 2026 (SBU US$482, Acuerdo MDT-2025-195)
Related pages
- investing/environmental-permits-and-consultation
- regulation/waste-and-producer-responsibility
- regulation/corporate-criminal-liability-and-compliance-programs
- real-estate/protected-areas-forests-and-mangroves
- sectors/mining-operations-closure-and-communities
- /country/ecuador/
- /calendar/
- Live dashboard
Related: Ecuador country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.