Environmental assessment and project permits in Guatemala: MARN categories, licences, insurance, public participation and Convention 169 consultation

Last verified: 2026-11-17 · Status: Changing

Any project that may harm the environment needs an approved environmental study before it starts, under Decreto 68-86 and MARN's regulation. Projects fall into categories A, B1, B2 or C, with licences of one to five years and fees to Q35,000 for five years. Category A and B1 projects face public notice. Indigenous consultation has stopped mining projects, so treat it as a core project risk.

USD figures use Q7.64187 per US dollar, the Banco de Guatemala reference rate (TCR) shown for 31 October 2026 in Banguat's dated exchange rate query. Conversions are for orientation only.

Key facts

Banguat reference rate used for conversions7.64187 GTQ per USDBanco de Guatemala, tipo de cambio de referencia, 31/10/2026, as of 2026-10-31 · in force
Longest environmental licence term5 yearsAcuerdo Gubernativo 137-2016 art. 61, as of 2026-10-31 · in force
Category A licence fee per year7000 GTQArt. 72 num. 8.1, as of 2026-10-31 · in force
Category B1 licence fee per year4000 GTQArt. 72 num. 8.3, as of 2026-10-31 · in force
Category B2 licence fee per year1500 GTQArt. 72 num. 8.5, as of 2026-10-31 · in force
Category A insured value cap3000000 GTQArt. 51, as of 2026-10-31 · in force
Public objection window20 daysArt. 45, as of 2026-10-31 · in force

The rule

1. Every project, work, industry or activity that by its nature may harm natural resources, the environment, the landscape or cultural heritage needs an environmental impact study, before development, by technical experts. Omitting it is fined at Q5,000 to Q100,000.Decreto Nº 68-86 del Congreso, Ley de Protección y Mejoramiento del Medio Ambiente, Art. 8, 1986 official text · verified 2026-10-31
2. Projects are classified by the MARN list as A (highest impact, including megaprojects), B1 (moderate to high), B2 (moderate to low) and C (low, for registration).Acuerdo Gubernativo Nº 137-2016, Reglamento de Evaluación, Control y Seguimiento Ambiental, as reformed, Art. 18 and 19, 2016-07-11 official text · verified 2026-10-31
3. MARN analyzes category A files within 90 days after public viewing ends, B2 within 15 days, with extensions for opinions or more information; the regulation sets 30 days to resolve. This copy predates later reforms, so confirm current terms with MARN.Acuerdo Gubernativo Nº 137-2016, Art. 23, 25 and 35, 2016-07-11 official text · verified 2026-11-15
4. Category A and B1 proponents publish edicts in national and regional papers and document participation, and anyone with an interest can object within 20 days from the third day after publication.Acuerdo Gubernativo Nº 137-2016 as reformed by Nº 121-2018, Art. 43 and 45, 2018-07-18 official text · verified 2026-10-31
5. A surety insurance in MARN's favor is required before the licence, and damage insurance is capped at Q3,000,000 for A, Q1,000,000 for B1 and Q500,000 for B2, without limiting liability for greater harm.
Cost to do it: Insurance premium on values up to Q3,000,000, Q1,000,000 or Q500,000.Acuerdo Gubernativo Nº 137-2016, Art. 48 and 51, 2018-07-18 official text · verified 2026-10-31
6. The licence must stay in force through every phase, including closure, and lasts one to five years for A and B. Fees are Q7,000 a year for A, Q4,000 for B1 and Q1,500 for B2, payable for the chosen term.
Example: Q35,000 for five years in category A. / About US$4,580.Acuerdo Gubernativo Nº 137-2016, Art. 61 and 72 num. 8, 2018-07-18 official text · verified 2026-11-17
7. Fines run in units of a Q100 base adjusted for the exchange rate: 50 to 250 units for C, 251 to 500 for B2, 501 to 750 for B1, and 751 to 1,000 for A.Acuerdo Gubernativo Nº 137-2016 as reformed, Art. 108 and 109, 2018-07-18 official text · verified 2026-10-31
8. Consultation with indigenous peoples under ILO Convention 169 can halt a licensed project. The Ministry of Energy and Mines reports that a provisional amparo of 11 November 2015 suspended its resolution granting the Progreso VII Derivada mining exploitation licence, challenged for lack of that consultation, and that the Constitutional Court's final ruling of 11 June 2020, in joined files 3207-2016 and 3344-2016, requires the consultation process to be carried out with the Maya Kaqchikel people in the area.Corte de Constitucionalidad, sentencia de 11 de junio de 2020, expedientes acumulados 3207-2016 y 3344-2016 (ILO Convention 169), as reported by the Ministerio de Energía y Minas, ILO Convention 169 consultation, 2020-06-11 official text · verified 2026-11-15
CategoryImpactLicence fee a yearInsured value capPublic process
AHighestQ7,000Q3,000,000Edicts and participation
B1Moderate to highQ4,000Q1,000,000Edicts; workshops excepted
B2Moderate to lowQ1,500Q500,000Not required by art. 43
CLowRegistration; licence on requestNot listedNot required by art. 43

Categories at a glance (2020 consolidated copy).

Worked example

  • A category B1 factory takes a five year licence at Q20,000 (US$2,617), and damage insurance is sized up to Q1,000,000 (US$130,858). If it starts without the study, the fine under art. 109 is 501 to 750 units, about Q50,100 to Q75,000 (US$6,556 to US$9,814) at the base unit before exchange rate adjustment, and works can be closed.

Step by step

  1. 1. Find the category in MARN's list; ask for categorization if absent.
  2. 2. Hire a registered consultant.
  3. 3. For A and B1, plan edicts and participation early.
  4. 4. Assess indigenous presence in the area, and engage before filing.
  5. 5. Obtain the licence and insurance, then diary renewals.

Common traps

  • The reachable copy runs to March 2020; later reforms exist, including Acuerdos 317-2019, 298-2022 and 148-2024 reported by others, and the listing Acuerdo 204-2019 may be updated. Check MARN's current text.
  • Art. 119 and 123 deadlines were extended repeatedly; do not rely on them.
  • Consultation is the State's duty, but the project bears the delay.
  • Municipal building licences and other permits are outside this page and were not verified.

Sources

Related pages

Related: Guatemala country profile · live dashboard · central bank and release calendar · our posts on X