Public private partnerships in Guatemala: the 2025 reform, ANI, 50 year contracts, unsolicited proposals and arbitration

Last verified: 2026-11-15 · Status: Changing

Decreto 21-2025, in force since January 2026, rebuilt the PPP law. ANADIE became the Agencia Nacional de Infraestructura (ANI), contracts can run up to 50 years, private parties can bring unsolicited projects, and only contracts that provide public services still need Congress. Foreign bidders are welcome, and those with foreign investment can go to ICSID. The regulation update and first projects under the new rules remain to be proven.

USD figures use Q7.64187 per US dollar, the Banco de Guatemala reference rate (TCR) for 31 October 2026 in the Banguat historical exchange rate query for that date. Conversions are for orientation only.

Key facts

Banguat reference rate used for conversions7.64187 GTQ per USDDecreto 94-2000 art. 4, as of 2026-10-31 · in force
Maximum PPP contract term including extensions50 yearsDecreto 16-2010 art. 4 letter h as worded by Decreto 21-2025 art. 5, as of 2026-11-15 · in force
Stake in a listed project company needing Agency approval25 %Decreto 16-2010 art. 65 letter a, as of 2026-11-15 · in force
Days to form the project company after award notice30 daysDecreto 16-2010 art. 58, as of 2026-11-15 · in force
Initial project guarantee account allocation2000000000 GTQDecreto 21-2025 art. 43, as of 2026-11-15 · in force
Minimum annual allocation from the infrastructure ministry physical investment budget3 %Decreto 21-2025 art. 44, as of 2026-11-15 · in force

The rule

1. The law now governs every stage of partnership projects for economic infrastructure, at State and municipal level, and the modality is distinct from concessions under the procurement law and municipal concessions under the Código Municipal. The reform was published on 29 December 2025 and took effect eight days later.Decreto Nº 21-2025 del Congreso (Diario de Centro América, 29 December 2025), reforming Decreto Nº 16-2010, Art. 1 and 46, 2025-12-29 official text · verified 2026-11-15 · changed: Reformed by Decreto 21-2025, published 29 December 2025: wider scope, new agency, longer terms, private initiatives and a narrower role for Congress.
2. The Agencia Nacional de Infraestructura (ANI) is a decentralized entity with its own legal personality and assets, the governing body for formulating and managing projects. For this law the name ANADIE is replaced by ANI.Decreto Nº 21-2025 del Congreso, Art. 7 (new art. 7 of Decreto 16-2010) and art. 42, 2025-12-29 official text · verified 2026-11-15 · changed: ANADIE renamed ANI by Decreto 21-2025.
3. Projects can be public initiatives, or unsolicited initiatives presented to the Agency by any individual or company, national or foreign. The successful private party must reimburse pre tender study costs to the Agency, to the proposer of an unsolicited initiative, or to whoever funded the studies under a refundable support agreement. Payment can be by availability, use or demand, construction milestones, demand subsidy, others set by regulation or contract, or mixed.
Cost to do it: Proposers fund their own studies and recover them only through the reimbursement in the tender terms.Decreto Nº 21-2025 del Congreso, New art. 2 Bis and art. 44 letter o of Decreto 16-2010; decree art. 3 and 25, 2025-12-29 official text · verified 2026-11-15
4. Every contract must state a maximum term, which with extensions cannot exceed 50 years, and omitting it voids the contract.Decreto Nº 21-2025 del Congreso, New art. 4 letter h of Decreto 16-2010; decree art. 5, 2025-12-29 official text · verified 2026-11-15 · changed: Cap raised to 50 years by Decreto 21-2025. The 2010 text capped contracts at 30 years.
5. Project phases are identification, admissibility, prioritization, structuring, public debt evaluation, prequalification, tender, formalization, construction, operation and reversion. Debt for a project must be approved by Congress before tender. For complex projects the Council can open a competitive dialogue before prequalification or tender.Decreto Nº 21-2025 del Congreso, New art. 35 and 40 Bis of Decreto 16-2010; decree art. 18 and 24 (decree art. 19 repeals former art. 36), 2025-12-29 official text · verified 2026-11-15
6. Contracts are approved by the Agency's Council, signed by the contracting entity, the Agency and the private party, and only those providing public services then go to Congress. Others close with Council approval, and municipal and mancomunidad contracts follow their own route.Decreto Nº 21-2025 del Congreso, New art. 62 of Decreto 16-2010; decree art. 27 and 40, 2025-12-29 official text · verified 2026-11-15 · changed: Before the reform every contract went to Congress.
7. Tenders, without exception, are public and international, and any national or foreign person who meets the bases, the law and its regulation may bid. The winner must form within 30 days of notice a Guatemalan company with a single purpose and registered shares, with the words Sociedad de Alianzas para el Desarrollo de Infraestructura Económica in its name.Decreto Nº 16-2010 del Congreso (issued 13 April 2010), not amended on these points by Decreto 21-2025, Art. 42 and 58, 2010-04-13 official text · verified 2026-11-15
8. Contracts must state how control of the project company can pass to financiers for a restructuring. If its shares are publicly offered, anyone reaching 25 percent or more of paid capital needs Agency approval, and without it the company cannot admit them.Decreto Nº 21-2025 del Congreso, New art. 65 letter a of Decreto 16-2010; decree art. 28, 2025-12-29 official text · verified 2026-11-15
9. Disputes can go to conciliation or arbitration at law, before the ad hoc commission, a local center, or international arbitration if the private party waives the local route in time. A party with foreign investment wanting international jurisdiction must go to ICSID. Awards follow the New York Convention. Starting a dispute does not stop performance unless the contract says so. A technical dispute board can be included, and contract nullity cannot go to the board or to conciliation.Decreto Nº 21-2025 del Congreso, New art. 94, 95, 100 and 102 of Decreto 16-2010; decree art. 31 to 34, 2025-12-29 official text · verified 2026-11-15
10. An impact study is due to be approved by the environment ministry and the planning secretariat within 30 days; silence counts as positive and the Agency may then ask for a no objection record, due within 10 business days. Ministries and municipalities have 12 months to adapt their rules.Decreto Nº 21-2025 del Congreso, New art. 37 of Decreto 16-2010; decree art. 41, 2025-12-29 official text · verified 2026-11-15
11. The Agency's private capital fund was assigned Q50 million for operations, Q100 million for preinvestment, Q400 million for contingencies and Q2,000 million for project guarantees from Treasury cash balances for the year, plus at least 3 percent of the Ministry of Communications physical investment budget each year. The Executive had 90 days to reform the regulation.Decreto Nº 21-2025 del Congreso, Art. 43, 44 and 45, 2025-12-29 official text · verified 2026-11-15
Contracting entityWith public serviceWithout public service
State body, decentralized or autonomous entityCouncil, signature, then CongressCouncil, signature, then Council
MunicipalityMunicipal council, signature, Agency CouncilSame
MancomunidadMancomunidad, signature, Agency CouncilSame

Who approves a contract after Decreto 21-2025.

Worked example

  • Q2,000 million of guarantee allocation is about US$261,716,046. A sponsor offering an unsolicited road side logistics hub files with ANI and pays for studies costing, say, Q7,641,870 (US$1,000,000). If a rival wins the tender, the bases must require the winner to reimburse those costs. If the sponsor wins, it forms the single purpose company within 30 days and, because no public service is provided, closes on Council approval without Congress.

Step by step

  1. 1. Check the project pipeline and rules with ANI.
  2. 2. Decide whether the project provides a public service: that decides whether Congress votes.
  3. 3. Budget for prequalification, the bid and a Guatemalan single purpose company.
  4. 4. Fix the arbitration route and waiver timing in the contract; a foreign investor's international route is ICSID.
  5. 5. Ask ANI which regulation version applies.

Common traps

  • Older guides and the 2010 text quote a 30 year cap and approval of every contract by Congress. The 2025 reform changed both.
  • The approval table in new art. 62 is hard to read in the gazette scan, so confirm the approval route for your contracting entity with ANI before relying on it.
  • Public debt for a project still needs Congress before tender, even when the contract does not.
  • No consolidated text or reformed regulation was found. Read the 2010 law together with Decreto 21-2025.
  • Art. 38 of the reform changed Código Municipal art. 110 and cut INFOM's lending to municipalities. In February 2026 Congress approved Decreto 5-2026 to restore that lending, so check the current text before relying on municipal funding terms.

Sources

Related pages

Related: Guatemala country profile · live dashboard · central bank and release calendar · our posts on X