The LatAm Thread

Countries › Guatemala › Guide › 3. Investing › Renewable energy incentives in Guatemala: Decreto 52-2003 duty, VAT and 10 year income tax relief and how to qualify

Renewable energy incentives in Guatemala: Decreto 52-2003 duty, VAT and 10 year income tax relief and how to qualify

Last verified: 2026-10-31 · Status: Stable

Generators using solar, wind, hydro, geothermal, biomass or tidal energy can import project equipment free of duties and VAT during preinvestment and construction, for up to 10 years. Income tax is exempt for 10 years from commercial operation, on project income only. The route is Ministry of Energy and Mines qualification, then a SAT exemption resolution.

USD figures use Q7.64187 per US dollar, the Banco de Guatemala reference rate for 31 October 2026, retrieved from the Banguat exchange rate web service on the verification date. Conversions are for orientation only.

Key facts

Banguat reference rate used for conversions7.64187 GTQ per USDDecreto 94-2000 art. 4, as of 2026-10-31 · in force
Renewable project income tax exemption from commercial operation10 yearsDecreto 52-2003 art. 5 letter b, as of 2026-10-31 · in force
Longest period for import relief10 yearsDecreto 52-2003 art. 5 letter a, as of 2026-10-31 · in force
SAT term before deemed grant30 business daysAcuerdo Gubernativo 211-2005 art. 19 and 20, as of 2026-10-31 · in force
Ministry directorate review term20 daysAcuerdo Gubernativo 211-2005 art. 4, as of 2026-10-31 · in force

The rule

1. Beneficiaries are municipalities, INDE, mixed companies and individuals and companies carrying out projects with renewable energy resources. Renewable resources are solar, wind, hydro, geothermal, biomass, tidal and others the Ministry of Energy and Mines qualifies.Decreto Nº 52-2003 del Congreso, Ley de Incentivos para el Desarrollo de Proyectos de Energía Renovable, Art. 4 and 5, 2003-11-10 official text · verified 2026-10-31
2. Imports: exemption from duties, including VAT, and consular charges on machinery and equipment used exclusively for generation in the project area, requested from SAT before import, and valid only in the preinvestment and construction periods, not above 10 years.
Example: VAT of 12 percent on Q40,000,000 of equipment is Q4,800,000. / About US$628,119.Decreto Nº 52-2003 del Congreso, Art. 5 letter a, 2003-11-10 official text · verified 2026-10-31
3. Income tax: exemption for 10 years from the date commercial operation starts, only for persons developing the project directly and only for the project's share of income, not other activities. The law also exempts from IEMA, an older tax that no longer exists.Decreto Nº 52-2003 del Congreso, Art. 5 letters b and c, 2003-11-10 official text · verified 2026-10-31
4. To use the incentives, send the Ministry of Energy and Mines a request with project documents showing the preinvestment, construction and operation timetable, a statement of compliance with the Ley General de Electricidad, and a list of materials and equipment. The Ministry issues a certificate that the project uses renewable sources and lists the goods subject to exemption.
Cost to do it: No filing fee appears in the law or regulation sections reviewed; preparing studies is the main cost.Decreto Nº 52-2003 del Congreso; Acuerdo Gubernativo Nº 211-2005, Law art. 5; regulation art. 3 and 4, 2005-06-16 official text · verified 2026-10-31
5. The Ministry's directorate studies the file within 20 days and gives its opinion. The holder then asks SAT to apply the incentives, attaching the certificate. SAT must decide within 30 business days; if it does not, the request is treated as granted and the holder can show exempt status for income tax.Acuerdo Gubernativo Nº 211-2005, Art. 4, 17, 19 and 20, 2005-06-16 official text · verified 2026-10-31
6. Goods imported free of duty can be transferred to third parties only with Ministry approval and after paying the customs taxes. Holders with several activities must separate them.Acuerdo Gubernativo Nº 211-2005, Art. 13 and 21, 2005-06-16 official text · verified 2026-10-31
7. Project owners hold emission reduction certificates and can sell them, under the law's art. 6 and the regulation's registry.Decreto Nº 52-2003; Acuerdo Gubernativo Nº 211-2005, Law art. 6; regulation art. 22 to 24, 2003-11-10 official text · verified 2026-10-31
8. Energy sector investors are outside the foreign capital treatment of Decreto 46-2022, so this is their incentive route.Decreto Nº 46-2022 del Congreso, Art. 2, 2022-09-19 official text · verified 2026-10-31

Worked example

  • A 20 MW solar project imports Q40,000,000 (US$5,234,321) of panels and inverters with a Ministry certificate: it avoids 12 percent VAT of Q4,800,000 (US$628,119) plus any duty on the tariff line. If operations yield Q5,000,000 (US$654,290) of annual profit, income tax of Q1,250,000 (US$163,573) a year at 25 percent is exempt for 10 years from the date commercial operation starts. Profit from an O and M contract for a third party is outside the exemption.

Step by step

  1. 1. Register the project and permits under the Ley General de Electricidad; see sectors/energy-mining-and-key-sectors.
  2. 2. File with the Ministry of Energy and Mines, listing goods and periods.
  3. 3. Obtain the certificate, then file with SAT before any import.
  4. 4. Keep a register of imported goods (regulation art. 12) and report as art. 14 and 16 require.
  5. 5. Record the commercial operation date; the 10 years start there, not at financial close.
  6. 6. Extend the request during construction if the equipment list changes (regulation art. 6).

Common traps

  • The law requires the exemption request before import, so do not ship equipment first.
  • Deemed grant in art. 20 refers to the income tax side, letters b and c, not imports.
  • Holding companies and investors do not share the exemption; it goes to the direct developer.
  • Reselling surplus equipment needs Ministry approval and tax payment first.

Sources

Related pages

Related: Guatemala country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.