Countries › Peru › Guide › 12. Sectors › Electricity in Peru: concessions and authorisations, free and regulated prices, distributor tenders and the 2025 reform of Ley 28832
Electricity in Peru: concessions and authorisations, free and regulated prices, distributor tenders and the 2025 reform of Ley 28832
Last verified: 2026-10-28 · Status: Changing
Peru's power sector is open to private and foreign investors. Hydro and renewable plants above 500 kW, transmission that uses State property or easements and distribution above 500 kW need a definitive concession from the Ministry of Energy and Mines; thermal plants above 500 kW need an authorisation; smaller activities only need to be reported. Concessions and authorisations are granted for an indefinite term, except those awarded by public tender, which last at most 30 years. Large consumers buy at freely agreed prices, while regulated users are supplied through distributors that buy power in tenders under Ley 28832. Ley 32249 of January 2025 reshaped those tenders: long term contracts are capped at 15 years, purchases may be split into energy and capacity blocks, existing contracts cannot be extended or increased, and a market for ancillary services applies from 1 January 2026.
USD figures use S/ 3.452 per US dollar, the banking system selling rate published by the Superintendencia de Banca, Seguros y AFP for 27 October 2026, from the Banco Central de Reserva del Perú statistics series PD04640PD. UIT based amounts use the 2026 UIT of S/ 5,500 set by Decreto Supremo Nº 301-2025-EF, as cited in SUNAT Resolución de Superintendencia Nº 000016-2026/SUNAT. Conversions are for orientation only.
Key facts
| Installed capacity above which hydro and renewable generation needs a definitive concession | 500 kWDL 25844 art. 3 as replaced by DL 1002, as of 2026-10-28 · in force |
|---|---|
| Installed capacity above which thermal generation needs an authorisation | 500 kWDL 25844 art. 4 as replaced by DL 1002, as of 2026-10-28 · in force |
| Maximum term of definitive concessions awarded by public tender | 30 yearsDL 25844 art. 22 as replaced by DL 1221, as of 2026-10-28 · in force |
| Maximum term of distributor long term tender contracts | 15 yearsLey 28832 art. 5.1 as amended by Ley 32249, as of 2026-10-28 · in force |
| Maximum gap between regulated bar price and average contract prices | 10 %Ley 28832 second final provision as amended by Ley 32249, as of 2026-10-28 · in force |
| Unjustified idle hours in a calendar year that cause a definitive concession to lapse | 876 hoursDL 25844 art. 36 c) as replaced by DL 1221, as of 2026-10-28 · in force |
| Grandes Usuarios (free users or groups with contracted capacity of at least) | 10 MWLey 28832 art. 1.12, as of 2026-10-28 · in force |
The rule
Cost to do it: Filing fees are set in the MINEM procedures text (TUPA) and were not verified here; the main costs are studies, the EIA, guarantees and the public deed.
Example: A 150 MW solar plant in Arequipa needs a definitive generation concession; a 50 MW gas fired peaker needs an authorisation; a 400 kW rooftop plant needs neither and only reports to MINEM. / Thresholds are in installed capacity, not investment: a US$1 million 600 kW diesel unit needs an authorisation, while a 450 kW unit does not.Decreto Ley Nº 25844, Ley de Concesiones Eléctricas (dated 6 November 1992), Osinergmin consolidated copy, art. 3 and 4 as replaced by Decreto Legislativo Nº 1002 (2 May 2008), art. 6 and 7 as replaced by Decreto Legislativo Nº 1221 (24 September 2015), Art. 3, 4, 6 and 7, 1992-11-06 official text · verified 2026-10-28 · changed: DL 1002 lowered the hydro concession threshold from 20 MW (set by Ley 28832 in 2006) to 500 kW and added renewables above 500 kW; DL 1221 created the single national register of concessions.
Cost to do it: Filing fees are set in the MINEM procedures text (TUPA) and were not verified here; the main costs are studies, the EIA, guarantees and the public deed.
Example: A developer holding a temporary concession granted by ministerial resolution published on 1 March 2026 has until 1 March 2028 to complete its studies. / A transmission line won in a MINEM tender with a 30 year term reverts under its contract terms, unlike a hydro plant with an indefinite concession.Decreto Ley Nº 25844, Ley de Concesiones Eléctricas (dated 6 November 1992), Osinergmin consolidated copy, art. 22 as replaced by Decreto Legislativo Nº 1221 and art. 23 as replaced by Ley Nº 29178 (3 January 2008), Art. 22 and 23, 1992-11-06 official text · verified 2026-10-28 · changed: DL 1221 added the 30 year cap for tender based concessions.
Cost to do it: Notary fees for the public deed and registry fees at SUNARP; guarantees of performance set by the regulation.
Example: If the resolution is received on 2 November 2026, the public deed must be signed by 1 January 2027. / Missing the works schedule on a hydro project can end the concession, so EPC delays are a regulatory risk as well as a commercial one.Decreto Ley Nº 25844, Ley de Concesiones Eléctricas (dated 6 November 1992), Osinergmin consolidated copy, art. 29 as replaced by Ley Nº 27239 (22 December 1999) and art. 36 as replaced by Decreto Legislativo Nº 1221 (24 September 2015), Art. 29 and 36, 1992-11-06 official text · verified 2026-10-28
Cost to do it: No fee; non filing within 15 days is fined.
Example: A cement plant buying 20 MW from a generator signs a free price contract and the generator files it with Osinergmin within 15 days. / Free price contracts must show generation and network charges separately, which makes benchmarking against regulated bar prices possible.Decreto Ley Nº 25844, Ley de Concesiones Eléctricas (dated 6 November 1992), Osinergmin consolidated copy, art. 8 as replaced by Ley Nº 27239, Art. 8, 1999-12-22 official text · verified 2026-10-28
Cost to do it: Tender participation costs (bid bonds and studies) are set in each tender's terms.
Example: A distributor needing supply from 2030 must launch a long term tender by 2027 at the latest, for a contract of up to 15 years. / A generator with 300 MW of firm capacity and 100 MW contracted from third parties cannot sell more than 400 MW of firm capacity to distributors and free users.Ley Nº 28832, Ley para asegurar el desarrollo eficiente de la generación eléctrica (published 23 July 2006), as amended by Ley Nº 32249 (El Peruano 19 January 2025), Art. 3.1, 4.4, 5, 7.3 and 8, 2025-01-19 official text · verified 2026-10-28 · changed: Ley 32249 rewrote art. 4.4, 5, 7.3 and 8 and art. 31 on isolated systems, added art. 32 and a new chapter eight on ancillary services, and repealed art. 2.2 of DL 1002 (the five yearly renewable target).
Cost to do it: No fee; ancillary services become a paid product with its own market.
Example: A battery owner in Lima can seek a MINEM title as an ancillary services provider and sell frequency control in the market that applies from 1 January 2026. / Contracts signed before the reform keep their volumes but cannot be extended, so new supply goes to new tenders.Ley Nº 28832 second final provision and art. 33 as amended and added by Ley Nº 32249; Ley Nº 32249 first, second and fifth final provisions, Second final provision; art. 33; Ley 32249 final provisions 1, 2 and 5, 2025-01-19 official text · verified 2026-10-28 · changed: Ley 32249 replaced the bar price comparison reference and created the ancillary services market (in force 1 January 2026).
| Tender | Minimum lead time | Maximum contract term |
|---|---|---|
| Long term | 3 years | 15 years |
| Medium term | 2 years | 5 years |
| Short term | 1 year | 3 years |
Distributor supply tenders after Ley 32249 (Ley 28832 art. 5)
| Activity | Title | Threshold |
|---|---|---|
| Hydro generation | Definitive concession | Above 500 kW |
| Renewable generation (solar, wind, biomass, geothermal, tidal) | Definitive concession | Above 500 kW |
| Thermal generation | Authorisation | Above 500 kW |
| Transmission using State property or easements | Definitive concession | Any size |
| Public service distribution | Definitive concession | Demand above 500 kW |
| Anything below the thresholds | None; report to MINEM | Up to 500 kW |
Which title an electricity project needs (DL 25844 art. 3, 4 and 7)
Worked example
- A foreign developer plans a 200 MW wind farm in Ica. It first seeks a temporary concession for studies (two years), obtains environmental certification, then applies for a definitive concession; once granted it signs the contract and raises it to a public deed within 60 calendar days. It can sell to free users at agreed prices, filing each contract with Osinergmin within 15 days, or bid in distributor tenders for contracts of up to 15 years at firm prices.
Step by step
- Classify the project under DL 25844 art. 3 and 4 to know whether it needs a concession, an authorisation or only a report.
- For studies, apply for a temporary concession (two years plus one only for force majeure).
- Obtain the environmental certification before the definitive title (see the investing page on environmental certification).
- Apply for the definitive concession, publish the application as required, sign the contract and raise it to a public deed within 60 calendar days; register it.
- Sell through free price contracts (file within 15 days) or bid in distributor tenders on the published ten year schedule.
- From 2026, consider ancillary services as a separate revenue line under the new market.
Common traps
- Missing the works schedule is a cause of lapse for definitive concessions; the only escape valves are force majeure accepted by MINEM or a single guaranteed rescheduling with an extra guarantee (DL 25844 art. 36 b), so build realistic schedules into the application.
- Contracts of distributors signed before Ley 32249 cannot be extended or increased, so incumbents cannot simply roll over volumes.
- Selling more firm capacity than you own or have contracted breaches Ley 28832 art. 3.1.
- The Osinergmin copy of DL 25844 shows amendments up to about 2020; check later changes to any article you rely on.
Sources
- DL 25844 Ley de Concesiones Eléctricas, Osinergmin consolidated copy on gob.pe
- Ley 28832, Osinergmin copy on gob.pe
- Ley 32249, Congress consolidated text
Related pages
- sectors/renewable-energy
- sectors/mining-energy-and-key-sectors
- investing/public-private-partnerships
- investing/environmental-certification-and-prior-consultation
- regulation/regulatory-compliance-essentials
- /country/peru/
- Live dashboard
Related: Peru country profile · live dashboard · central bank and release calendar · our posts on X