Countries › Uruguay › Guide › 3. Investing › Public private partnerships in Uruguay: what can be built, how projects are tendered, private initiatives, guarantees, lender rights and arbitration
Public private partnerships in Uruguay: what can be built, how projects are tendered, private initiatives, guarantees, lender rights and arbitration
Last verified: 2026-10-27 · Status: Stable
Under Ley Nº 18.786 a public body can hire a private company to design, build, operate and finance infrastructure for up to 35 years, in roads, rail, ports, airports, energy, waste, irrigation and social infrastructure such as prisons, schools and hospitals, but never the core educational, health or prison services themselves. Projects need a value for money study cleared by the Planning Office and the Ministry of Economy, tenders are published at least 90 days before bids are due, and a private proposer of an initiative gets up to a 10 percent scoring advantage and reimbursement of its study costs if it loses. Disputes go to binding arbitration at law, lenders can take pledges over project cash flows, and total PPP liabilities are capped at 9 percent of GDP.
USD figures use UYU 40.210 per US dollar, the Banco Central del Uruguay quotation for DLS. USA BILLETE on 27 October 2026, and the Unidad Indexada (UI) at UYU 6.6792 for 27 October 2026, both retrieved from the BCU quotations service on the verification date. Amounts the law sets in UI or pesos are quoted as written; conversions are for orientation only.
Key facts
| PPP maximum term including extensions | 35 yearsLey Nº 18.786 art. 4 literal G, as of 2026-10-27 · in force |
|---|---|
| Private initiative proposer: maximum scoring advantage | 10 %Ley Nº 18.786 art. 37, as of 2026-10-27 · in force |
| Minimum publication of the call before bids are due | 90 calendar daysDecreto Nº 17/012 art. 21 (Decreto Nº 251/015), as of 2026-10-27 · in force |
| Bid bond minimum validity | 180 daysDecreto Nº 17/012 art. 25, as of 2026-10-27 · in force |
| Cap on modifications imposed by the administration | 20 % of original budgetLey Nº 18.786 art. 47, as of 2026-10-27 · in force |
| Cap on agreed revisions (30 percent during construction) | 50 % of original budgetLey Nº 18.786 art. 48, as of 2026-10-27 · in force |
| Administration step in maximum period | 24 monthsLey Nº 18.786 art. 52, as of 2026-10-27 · in force |
| Cap on total PPP firm and contingent liabilities (NPV) | 9 % of prior year GDPLey Nº 18.786 art. 62 (Ley Nº 19.924 art. 693), as of 2026-10-27 · in force |
| Cap on annual PPP payments to contractors | 0.7 % of prior year GDPLey Nº 18.786 art. 62 (Ley Nº 19.924 art. 693), as of 2026-10-27 · in force |
| State may guarantee a minimum return | No Ley Nº 18.786 art. 6, as of 2026-10-27 · in force |
| PPP contract disputes go to arbitration | Yes Ley Nº 18.786 art. 54, as of 2026-10-27 · in force |
| BCU quotation, DLS. USA BILLETE | 40.21 UYU per USDBanco Central del Uruguay quotation, as of 2026-10-27 · in force |
| Unidad Indexada (UI) value | 6.6792 UYUBanco Central del Uruguay quotation, as of 2026-10-27 · in force |
The rule
Cost to do it: No filing fee is set in the law or decree; the proposer bears the prefeasibility and feasibility studies, reimbursable only if it does not win.Ley Nº 18.786 art. 34 to art. 38; Decreto Nº 17/012 art. 45 and art. 46, Ley art. 35, 36, 37 and 38; Decreto art. 45 and 46, 2011-07-19 official text · verified 2026-10-27
Example: On a works budget of UYU 4,021,000,000, unilateral modifications are capped at UYU 804,200,000 and agreed revisions during construction at UYU 1,206,300,000. / About US$100 million of works, US$20 million and US$30 million.Ley Nº 18.786, Art. 39, art. 47, art. 48 and art. 50, 2011-07-19 official text · verified 2026-10-27
| Stage | Term | Source |
|---|---|---|
| CND formal check of a private initiative | 15 business days, plus up to 15 calendar days to fix gaps | Decreto Nº 17/012 art. 45 |
| CND technical evaluation of the initiative | 30 calendar days | Decreto Nº 17/012 art. 46 |
| Publication of the call | At least 90 calendar days before bids | Decreto Nº 17/012 art. 21 |
| Tribunal de Cuentas review of the provisional award | 30 calendar days, silence is favourable | Ley Nº 18.786 art. 23 |
| Earliest final award | 30 business days after provisional award notice | Ley Nº 18.786 art. 23 |
| Performance guarantee | Within 30 business days of the provisional award | Decreto Nº 17/012 art. 27 |
| Step in by the administration | Up to 24 months | Ley Nº 18.786 art. 52 |
PPP procedure and the terms set by law and decree
Worked example
- A foreign developer proposes a prison maintenance and operation PPP (construction and building services only, since prison security and rehabilitation services cannot be included under Ley Nº 18.786 art. 3). It files the initiative with prefeasibility at the CND, which evaluates it within 30 days (Decreto Nº 17/012 art. 46). If accepted and called, the developer bids with up to a 10 percent advantage; if another bidder wins, the winner repays the developer's accepted feasibility costs (Ley Nº 18.786 art. 37). As contractor it can pledge future availability payments to its lenders (art. 55) and any dispute goes to arbitration at law (art. 54).
Step by step
- 1. Check the asset type is within art. 3 and that the service is not a reserved core service.
- 2. Decide whether to wait for a public call or file a private initiative with the CND with a prefeasibility study (art. 35).
- 3. Follow the State procurement website for PPP calls; prepare for at least 90 days of bid period and a competitive dialogue if used (art. 19 and 20; Decreto art. 21).
- 4. Post a bid bond valid for at least 180 days (Decreto art. 25), then the performance guarantee within 30 business days of the provisional award (Decreto art. 27).
- 5. Arrange project finance with cash flow pledges or a security trust (art. 55), and set up reporting to the contracting body, which reports to the PPP Unit twice a year (art. 39).
Common traps
- No minimum return can be guaranteed by contract, so demand risk must be priced or covered by availability payments (Ley Nº 18.786 art. 6).
- The provisional award is not final: the Tribunal de Cuentas review and a 30 business day wait come first (art. 23).
- If the proposer of a private initiative does not deliver the feasibility study on time, it loses all reimbursement and advantage rights (art. 37).
- Lenders wanting to enforce after a termination for breach must notify the administration within 10 days of learning of it (art. 57).
- Arbitral awards under PPP contracts cannot be appealed, so the arbitration clause and seat deserve close drafting (art. 54).
Sources
- Ley Nº 18.786, Public Private Partnership Law (IMPO)
- Decreto Nº 17/012, PPP regulation (IMPO)
- Ley Nº 17.555, earlier private initiative rules (IMPO)
- Banco Central del Uruguay, quotations
Related pages
- investing/foreign-investment-regime
- investing/selling-to-the-state
- disputes/commercial-arbitration
- sectors/key-sectors-and-rules
- macro/public-finances-budget-and-debt
- /country/uruguay/
- Live dashboard
Related: Uruguay country profile · live dashboard · central bank and release calendar · our posts on X