Building, extending, altering or demolishing anything in Chile needs a permit from the municipal works department (Dirección de Obras Municipales), which has 25 business days to decide, 15 with an independent reviewer's report. Fees are set by law, for example 1.5 percent of the budget for new buildings, with 30 percent off when an independent reviewer is used, and nothing can be occupied before the final works reception. Outside urban limits, construction is limited to farm use and a few authorised exceptions.
USD figures use the Central Bank exchange rate of CLP 986.58 per US dollar published in the Diario Oficial for 23 October 2026 (CVE 2891564). UF figures use the SII value of CLP 41,221.08 for 26 October 2026, UTM figures the October 2026 value of CLP 72,151 and UTA figures the December 2025 value of CLP 834,504. Conversions are for orientation only.
Key facts
| Business days for the municipality to decide on a building permit | 25 business daysLGUC art. 118, as of 2026-10-26 · in force |
|---|---|
| Business days with an independent reviewer's report | 15 business daysLGUC art. 118, as of 2026-10-26 · in force |
| Municipal fee for new works and extensions | 1.5 % of budgetLGUC art. 130, as of 2026-10-26 · in force |
| Municipal fee for subdivisions and land divisions | 2 % of land fiscal assessmentLGUC art. 130, as of 2026-10-26 · in force |
| Fee reduction with an independent reviewer | 30 %LGUC art. 116 bis, as of 2026-10-26 · in force |
| Permit lapses if works not begun or stopped for | 3 yearsOGUC art. 1.4.17, as of 2026-10-26 · in force |
The rule
Cost to do it: New building with a budget of CLP 2,000,000,000: municipal fee CLP 30,000,000, or CLP 21,000,000 with an independent reviewer.
Example: Budget CLP 2,000,000,000: fee CLP 30,000,000; with a reviewer CLP 21,000,000. / Budget about US$2,027,205: fee about US$30,408, or US$21,286 with a reviewer (plus the reviewer's own fee).DFL Nº 458 of 1975, Art. 116 bis and art. 130, 1976-04-13 official text · verified 2026-10-26
Cost to do it: 1,000 UF is about CLP 41,221,080 (about US$41,782).DFL Nº 458 of 1975, Art. 55, 1976-04-13 official text · verified 2026-10-26
| Work | Fee |
|---|---|
| Subdivisions and land divisions | 2.0 percent of the land's fiscal assessment |
| New works and extensions | 1.5 percent of budget |
| Alterations, repairs, minor and provisional works | 1.0 percent of budget |
| Standard plans approved by the Ministry | 1.0 percent of budget |
| Reconstruction | 1.0 percent of budget |
| Project changes | 0.75 percent of budget |
| Demolitions | 0.5 percent of budget |
| Telecom antenna towers | 5 percent of installation budget |
| Boundary changes | 2.0 percent of the fiscal assessment of the part changed |
| Filing of sworn declaration | 0.75 percent of budget |
Municipal fees for permits (LGUC art. 130)
Worked example
- A developer plans a CLP 2,000,000,000 office building (about US$2,027,205). The municipal fee is CLP 30,000,000; by hiring a registered independent reviewer it falls to CLP 21,000,000 and the review deadline drops from 25 to 15 business days. The permit lapses if excavation has not started within three years.
Step by step
- Obtain the certificado de informaciones previas from the municipality to see the zoning rules for the plot.
- Check whether the project needs environmental assessment before the permit (see investing/project-permits-and-environmental-assessment).
- Consider an independent reviewer: 30 percent lower fees and a shorter deadline.
- Apply for final reception before occupation and before selling units; Ley Nº 21.850's VAT exemption also depends on the reception date (see real-estate/vat-on-real-estate).
Common traps
- Occupying a building before final reception breaches LGUC art. 145, and homes cannot be switched to other uses without a municipal change of use authorisation.
- Silence means rejection, not approval: after the deadline the applicant can only treat the application as rejected and challenge it.
- Rural land cannot be used for urban developments without the art. 55 authorisations.
- Planning rules are changing under Ley Nº 21.807 of 16 February 2026, which amends the LGUC planning procedures.
Sources
- DFL Nº 458 of 1975, Ley General de Urbanismo y Construcciones (Ley Chile)
- Decreto Supremo Nº 47 of 1992, Ordenanza General de Urbanismo y Construcciones (Ley Chile)
- Ley Nº 21.807 of 16 February 2026, planning system reform (Ley Chile)
- Banco Central de Chile exchange rates for 23 October 2026, Diario Oficial CVE 2891564
- SII, Unidad de Fomento 2026
- SII, UTM and UTA 2026
- SII, UTM and UTA 2025
Related pages
- investing/project-permits-and-environmental-assessment
- real-estate/rural-land-and-subdivision
- start/reform-tracker