Hydro and geothermal concessions

Last verified: 2026-11-15 · Status: Stable

Water and heat cannot be used to generate power without a concession approved by the Assembly, except by CEL and its controlled companies. Hydro concessions above 5 MW are bid, run up to 30 years and need a feasibility study and an approved environmental study. Geothermal has its own 2025 law with permit, exploration and concession stages and a registry at the DGEHM.

El Salvador is dollarized, so every amount here is already in US dollars, the unrestricted legal tender. Colón equivalents use the fixed legal rate of ¢8.75 per US$1 (Ley de Integración Monetaria, art. 1) and are for reference only.

Key facts

Maximum hydro concession above 5 MW30 yearsD.L. 843 art. 12, as of 2026-11-15 · in force
Maximum geothermal concession30 yearsD.L. 404 art. 24, as of 2026-11-15 · in force
Maximum exploration area50 km2D.L. 404 art. 19, as of 2026-11-15 · in force

The rule

1. Generating from hydro or geothermal resources needs a concession approved by the Assembly. CEL and companies it controls are outside the rule, and solar, wind and biomass need none.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 5, 1996-10-10 official text · verified 2026-11-15
2. Concessions up to 5 MW use the small scale procedure in a separate law.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 5 and 12, 1996-10-10 official text · verified 2026-11-15
3. Above 5 MW the Assembly approves by decree for up to 30 years, set from financial, environmental and social criteria in the feasibility study. Transfers need a request and specific approval by the Assembly.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 12, 1996-10-10 official text · verified 2026-11-15
4. The application needs legal capacity documents, a feasibility study with plans and an environmental study already approved. Admissibility is decided in eight days and refused only if the resource is taken or a requirement is missing.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 13 to 15, 1996-10-10 official text · verified 2026-11-15
5. Concessions go to public bid, with project data published in two national newspapers so that objectors can respond. Offers carry a guarantee of 10 percent of the offer.
Cost to do it: A US$1,000,000.00 (¢8,750,000.00) offer needs a US$100,000.00 (¢875,000.00) guarantee.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 16 and 17, 1996-10-10 official text · verified 2026-11-15
6. The best price wins, but a first applicant who lost keeps the right by paying 90 percent of the winning offer for hydro or 85 percent for geothermal. For geothermal, D.L. 404 of 2025 now sets its own award procedure and prevails over conflicting rules (art. 80), so check it first.
Example: Winning hydro offer ¢8,750,000.00: applicant match ¢7,875,000.00 / Winning hydro offer US$1,000,000.00: applicant match US$900,000.00Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 18, 1996-10-10 official text · verified 2026-11-15
7. The contract is signed by public deed within 30 days of publishing the result. Concessions end only by renunciation or breach.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 19 and 20, 1996-10-10 official text · verified 2026-11-15
8. A one time, non exclusive temporary permit allows study of a project, including on state property.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 24 and 25, 1996-10-10 official text · verified 2026-11-15
9. Exploiting these resources without a concession is a very serious infraction.Decreto Legislativo Nº 843, Ley General de Electricidad, Art. 105 a), 1996-10-10 official text · verified 2026-11-15
10. Anyone, national or foreign, doing geothermal prospecting, exploration or exploitation must hand the DGEHM its data, and the DGEHM keeps a Registro de Geotermia.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 6 and 8, 2025-09-10 official text · verified 2026-11-15
11. A prospecting permit lasts 12 months, extendable once for 12 more.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 14, 2025-09-10 official text · verified 2026-11-15
12. Exploration needs a DGEHM authorization, decided within 45 working days, for up to 50 square kilometres and 36 months, extendable once by up to 24 months. It gives no real right.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 15, 17, 18 and 19, 2025-09-10 official text · verified 2026-11-15
13. Exploitation needs an Assembly concession of up to 30 years. CEL and related entities are outside this rule.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 24, 2025-09-10 official text · verified 2026-11-15
14. A geothermal concession is a real right separate from surface ownership and enforceable against the state and third parties.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 25, 2025-09-10 official text · verified 2026-11-15
15. Geothermal concessions are normally bid on DGEHM terms. Without a bid, the holder of an exploration authorization who confirms a viable reservoir has a preferential right to request the concession directly within six months after the authorization ends, and state projects of national interest can be awarded directly. Either way the file goes to the Assembly with a draft decree and draft contract. Transfer, including by share sales or changes of partners, needs DGEHM review and Assembly approval, by public deed.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 22, 30, 31, 32, 43 and 52, 2025-09-10 official text · verified 2026-11-15
16. Residual geothermal fluids must be reinjected.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 10, 2025-09-10 official text · verified 2026-11-15
17. Serious infractions carry fines of 5,000 to 7,500 monthly minimum wages of the industry sector, and very serious ones 7,501 to 10,000, using the wage in force when the infraction is committed.Decreto Legislativo Nº 404, Ley de Energía Geotérmica, Art. 75, 2025-09-10 official text · verified 2026-11-15
StageTitleTermArea
ProspectingDGEHM permit12 months, plus 12Per application
ExplorationDGEHM authorization36 months, plus up to 24Up to 50 km2
ExploitationAssembly concessionUp to 30 yearsConcession area

Geothermal stages under D.L. 404 of 2025.

Worked example

  • In a hydro bid the winner offers US$1,000,000.00 (¢8,750,000.00). The first applicant can keep the project by paying US$900,000.00 (¢7,875,000.00), 90 percent of the winning offer. Each offer needs a 10 percent guarantee, here US$100,000.00 (¢875,000.00).

Step by step

  1. Secure a study permit, or geothermal prospecting permit.
  2. Obtain the environmental permit.
  3. File the feasibility study and wait for the public bid.
  4. Pay the price and sign the contract by public deed.
  5. Register with the DGEHM and start works on the contract schedule.

Common traps

  • Being first in line on a hydro project does not win; it gives a right to match at 90 percent of the winning offer.
  • The Assembly decides, so timing is political, not administrative.
  • Hydro law speaks of transfer of the concession; for geothermal, share sales and changes of partners also need DGEHM review and Assembly approval.
  • Check D.L. 404 first for geothermal: it is the later special law, has its own stages and prevails where it conflicts.
  • For geothermal, exploring first matters: a successful explorer can request the concession directly, and an area under exploration authorization cannot be put out to public bid meanwhile.
  • The small scale concession law was not read here, so confirm its steps for plants up to 5 MW.

Sources

Related pages

Related: El Salvador country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.