Countries › Guatemala › Guide › 12. Sectors › Distributed renewable generation and rooftop self supply in Guatemala: the 2026 CNEE norm, connection steps, the 5 percent guarantee and net credits
Distributed renewable generation and rooftop self supply in Guatemala: the 2026 CNEE norm, connection steps, the 5 percent guarantee and net credits
Last verified: 2026-10-31 · Status: Changing
Resolution CNEE-230-2026 replaced most of the 2014 norm for renewable plants injecting up to 5 MW into a distribution network: the distributor now issues a capacity and connection opinion (DCC), the CNEE authorizes, and the parties sign an interconnection contract. The developer posts a guarantee of 5 percent of its estimated investment, pays processing and network costs, and on the norm's stated periods a clean file takes about 55 days to contract and one needing studies about 100. Users who only offset their own bill stay under the surviving 2014 articles: no authorization, no payment for surplus, and a kWh credit against later consumption.
USD figures use Q7.64187 per US dollar, the Banco de Guatemala reference rate for 31 October 2026, retrieved from the Banguat exchange rate web service on the verification date. Conversions are for orientation only.
Key facts
| Maximum net injection under the distributed generation norm | 5 MWResolución CNEE-230-2026 art. 1, as of 2026-10-31 · in force |
|---|---|
| Guarantee over estimated investment at the developer's charge | 5 %Resolución CNEE-230-2026 art. 13, as of 2026-10-31 · in force |
| Time for the CNEE to decide a connection authorization | 20 daysResolución CNEE-230-2026 art. 13, Paso 5, as of 2026-10-31 · in force |
| Period for existing plants to sign the new contract | 5 yearsResolución CNEE-230-2026 art. 26, as of 2026-10-31 · in force |
| Last date for paper filing if the platform is not ready | 2027-07-31 dateResolución CNEE-230-2026 art. 28, as of 2026-10-31 · in force |
| Treatment of surplus for own use generators | Energy credit against later consumption; no cash payment textResolución CNEE-227-2014 art. 40, as of 2026-10-31 · in force |
| Time for the distributor to install the two way meter | 28 daysResolución CNEE-227-2014 art. 37, as of 2026-10-31 · in force |
The rule
Cost to do it: Processing costs are set by each distributor's filing with the CNEE under art. 28; no amount appears in the norm.
Example: A 4 MW solar plant on a leased farm qualifies if the lease proves lawful possession; a 7 MW plant does not fall under this norm. / A foreign fund's local company can apply: the norm speaks of any individual or legal person.Resolución CNEE-230-2026 (16 July 2026), Norma Técnica para la Conexión, Operación, Control y Comercialización de la Generación Distribuida Renovable; Acuerdo Gubernativo Nº 256-97, Norm art. 1, 2, 7 and 23; Reglamento art. 16 bis, 2026-07-16 official text · verified 2026-10-31 · changed: Replaces most of Resolución CNEE-227-2014 (25 August 2014). Art. 30 repeals art. 5, 6, 9 to 14 and 16 to 35 of that norm; the rest stays in force, including the self supply articles.
Cost to do it: Applicant pays processing costs, minor works, network upgrades, studies when the distributor does them, and any works on the affected transmission system (art. 5.2 h, i and j).
Example: A rooftop style 800 kW plant that passes step 2 goes straight to the DCC and CNEE: 5 + 10 + 5 + 5 + 20 + 10 = 55 days to contract, on the norm's periods. / A 5 MW plant that needs studies by the distributor: 5 + 10 + 5 + 10 + 5 + 10 + 20 + 5 + 20 + 10 = 100 days to contract, before construction.Resolución CNEE-230-2026, Art. 11 and 13, 2026-07-16 official text · verified 2026-10-31
Cost to do it: On an estimated investment of Q7,641,870 (US$1,000,000) the guarantee is Q382,093.50 (US$50,000), plus the issuer's premium.
Example: A project with Q7,641,870 at its charge posts Q382,093.50. / On US$1 million the guarantee is US$50,000; on US$5 million it is US$250,000.Resolución CNEE-230-2026, Art. 13, Paso 4 and Paso 6; art. 4.1 i), 2026-07-16 official text · verified 2026-10-31 · changed: The guarantee is new in CNEE-230-2026; it is not in the 2014 articles.
Cost to do it: The operation and dispatch charge in art. 24 was not yet set in the text reviewed; model it as an open cost. The applicant also pays tolls to the transporter (art. 5.2 m).
Example: A 3 MW solar plant with a battery charges only from its panels; it cannot arbitrage grid prices. / A developer's revenue model should list a separate line for the art. 24 charge once the CNEE publishes it.Resolución CNEE-230-2026, Art. 2, 5.1 d), 5.2, 8, 15, 17, 19, 20 and 24, 2026-07-16 official text · verified 2026-10-31
Cost to do it: No fee is stated for a CNEE dispute.
Example: A project that filed in June 2026 can stay under the 2014 process, or opt into the 2026 one. / An operating 2 MW plant has until five years after the norm took effect to sign the new contract.Resolución CNEE-230-2026, Art. 4.2 o), 14, 26, 27, 28, 29 and 31, 2026-07-16 official text · verified 2026-10-31 · changed: Trade press and law firm notes report publication in the Diario de Centro América on 27 July 2026 and entry into force on 17 August 2026 (secondary, not read in the gazette).
Cost to do it: The installation and protection cost is the user's; the meter is free for regulated users. No authorization fee.
Example: A shop that consumes 3,000 kWh and generates 3,400 kWh in a month pays no energy charge, carries 400 kWh forward, and still pays the fixed charge. / A hotel's US$200,000 solar roof earns no cash for surplus, so size it to consumption.Resolución CNEE-227-2014 (25 August 2014), Norma Técnica de Generación Distribuida Renovable y Usuarios Autoproductores con Excedentes de Energía, Art. 3 (definition) and 36 to 40, kept in force by CNEE-230-2026 art. 30, 2014-08-25 official text · verified 2026-10-31
| Step | Who | Period |
|---|---|---|
| Preliminary report (optional) | Distributor | 10 days; not binding |
| 1. DCC request checked | Distributor, then applicant | 5 days; 5 days to fix; 5 days to recheck |
| 2. Initial evaluation | Distributor | 10 days; DCC in 5 days if minor works suffice |
| 3. Options meeting | Applicant, then distributor | 5 days to continue; meeting within 10 days |
| 4. Studies | Distributor or applicant | Premises in 10 business days; 20 days to DCC, or 20 + 10 days |
| 5. CNEE authorization | Distributor, then CNEE | 5 days to file; 20 days to decide |
| 6. Interconnection contract and guarantee | Both | 10 days |
| 7. Commissioning | Both | 5 days' notice; 5 days for report; 5 days for approval |
Connection path under CNEE-230-2026 art. 13, using the norm's stated periods.
Worked example
- A company plans a 2 MW solar plant with Q7,641,870 (US$1,000,000) of grid and plant investment at its charge, and needs a network reconductoring studied by the distributor.
- Guarantee at contract stage: 5 percent, Q382,093.50 (US$50,000).
- Time to contract on the norm's periods: about 100 days, plus any gaps in the file. Environmental documents are filed with the DCC request (art. 12).
- Costs to model: processing fee, studies, upgrades, tolls to the transporter, and the art. 24 operation charge that the CNEE has yet to set.
- Sales are separate: the interconnection contract is not a power purchase agreement, so the buyer must be arranged apart.
Step by step
- 1. Confirm title or lawful possession of the site and the net injection of 5 MW or less.
- 2. For hydro, register the water levels with the Dirección General de Energía before the DCC request (art. 5.2 l).
- 3. Check the distributor's published capacity map, then ask for the preliminary report if useful.
- 4. File the DCC request with legal and environmental documents and pay the processing cost.
- 5. Follow the steps in art. 13, sign the contract, post the 5 percent guarantee and commission the plant.
- 6. Own use only: file the notice with the distributor, install protection, and let the distributor inspect and fit the two way meter.
Common traps
- Relying on the old toll exemption. Art. 35 of the 2014 norm said distributed generators paid no distributor or secondary system tolls, but CNEE-230-2026 art. 30 repealed art. 16 to 35. Art. 5.2 m) now says the applicant pays the transporter's tolls.
- Treating the preliminary report as a reservation. Art. 11 says it reserves no capacity and grants no right.
- Missing a 5 day window. If gaps are not fixed in 5 days the request counts as withdrawn, and missing the options meeting means rejection, so queue position can be lost.
- Reading the capacity map as a promise. Art. 4.2 o) calls it indicative and not binding.
- Pairing batteries with grid arbitrage. Art. 15 bars charging from the distribution system.
- Counting days. The norm mostly says días, and only Paso 4 says días hábiles. The calculation of the 60 day and 15 day periods was not stated, so confirm any deadline with the distributor.
Sources
- Resolución CNEE-230-2026 (CNEE)
- Resolución CNEE-227-2014, Norma Técnica de Generación Distribuida Renovable (CNEE)
- Reglamento de la Ley General de Electricidad (CNEE)
- Secondary cross check of dates: pv magazine Latinoamérica, 12 August 2026
- Banco de Guatemala exchange rate web service
Related pages
- sectors/electricity-market-agents-and-large-users
- sectors/energy-mining-and-key-sectors
- investing/renewable-energy-incentives
- /country/guatemala/
- /calendar/
- Live dashboard
Related: Guatemala country profile · live dashboard · central bank and release calendar · our posts on X