Countries › Guatemala › Guide › 12. Sectors › Distributed renewable generation and rooftop self supply in Guatemala: the 2026 CNEE norm, connection steps, the 5 percent guarantee and net credits

Distributed renewable generation and rooftop self supply in Guatemala: the 2026 CNEE norm, connection steps, the 5 percent guarantee and net credits

Last verified: 2026-10-31 · Status: Changing

Resolution CNEE-230-2026 replaced most of the 2014 norm for renewable plants injecting up to 5 MW into a distribution network: the distributor now issues a capacity and connection opinion (DCC), the CNEE authorizes, and the parties sign an interconnection contract. The developer posts a guarantee of 5 percent of its estimated investment, pays processing and network costs, and on the norm's stated periods a clean file takes about 55 days to contract and one needing studies about 100. Users who only offset their own bill stay under the surviving 2014 articles: no authorization, no payment for surplus, and a kWh credit against later consumption.

USD figures use Q7.64187 per US dollar, the Banco de Guatemala reference rate for 31 October 2026, retrieved from the Banguat exchange rate web service on the verification date. Conversions are for orientation only.

Key facts

Maximum net injection under the distributed generation norm5 MWResolución CNEE-230-2026 art. 1, as of 2026-10-31 · in force
Guarantee over estimated investment at the developer's charge5 %Resolución CNEE-230-2026 art. 13, as of 2026-10-31 · in force
Time for the CNEE to decide a connection authorization20 daysResolución CNEE-230-2026 art. 13, Paso 5, as of 2026-10-31 · in force
Period for existing plants to sign the new contract5 yearsResolución CNEE-230-2026 art. 26, as of 2026-10-31 · in force
Last date for paper filing if the platform is not ready2027-07-31 dateResolución CNEE-230-2026 art. 28, as of 2026-10-31 · in force
Treatment of surplus for own use generatorsEnergy credit against later consumption; no cash payment textResolución CNEE-227-2014 art. 40, as of 2026-10-31 · in force
Time for the distributor to install the two way meter28 daysResolución CNEE-227-2014 art. 37, as of 2026-10-31 · in force

The rule

1. Scope and who may apply. The norm governs connection and use of the distribution system and the operation, control and sale of renewable plants that inject up to 5 MW net. The applicant must own or lawfully possess the property where the plant sits. Distributors must allow connection and make the changes needed, as the Reglamento already required. Free access is guaranteed: refusing information, ignoring queue order or deadlines, asking for requirements with no technical basis, or discriminating is a serious fault sanctioned by the CNEE.
Cost to do it: Processing costs are set by each distributor's filing with the CNEE under art. 28; no amount appears in the norm.
Example: A 4 MW solar plant on a leased farm qualifies if the lease proves lawful possession; a 7 MW plant does not fall under this norm. / A foreign fund's local company can apply: the norm speaks of any individual or legal person.Resolución CNEE-230-2026 (16 July 2026), Norma Técnica para la Conexión, Operación, Control y Comercialización de la Generación Distribuida Renovable; Acuerdo Gubernativo Nº 256-97, Norm art. 1, 2, 7 and 23; Reglamento art. 16 bis, 2026-07-16 official text · verified 2026-10-31 · changed: Replaces most of Resolución CNEE-227-2014 (25 August 2014). Art. 30 repeals art. 5, 6, 9 to 14 and 16 to 35 of that norm; the rest stays in force, including the self supply articles.
2. The connection path. An optional preliminary report takes 10 days and reserves nothing. Step 1: file the DCC request; the distributor checks it in 5 days and the applicant has 5 days to fix gaps, or the request is treated as withdrawn. Queue order is fixed when the file is declared complete. Step 2: initial evaluation in 10 days; if minor works suffice, the DCC follows in 5 days. Step 3: if not, the applicant says within 5 days whether it continues and an options meeting is called within 10 days; an unjustified absence means rejection. Step 4: studies, with premises within 10 business days and a DCC within 20 days, or a report by the applicant within 20 days and the DCC 10 days later. Step 5: the distributor files with the CNEE within 5 days and the CNEE decides within 20 days. Step 6: the interconnection contract is signed within 10 days. Step 7: commissioning, with 5 days' notice for tests and 5 days for each later act.
Cost to do it: Applicant pays processing costs, minor works, network upgrades, studies when the distributor does them, and any works on the affected transmission system (art. 5.2 h, i and j).
Example: A rooftop style 800 kW plant that passes step 2 goes straight to the DCC and CNEE: 5 + 10 + 5 + 5 + 20 + 10 = 55 days to contract, on the norm's periods. / A 5 MW plant that needs studies by the distributor: 5 + 10 + 5 + 10 + 5 + 10 + 20 + 5 + 20 + 10 = 100 days to contract, before construction.Resolución CNEE-230-2026, Art. 11 and 13, 2026-07-16 official text · verified 2026-10-31
3. The 5 percent guarantee. At the interconnection contract stage the applicant must give the distributor a guarantee of 5 percent of the estimated investment at its charge, to secure the schedule stated in the DCC request. It must stay in force throughout the works. If the developer fails to build, the distributor may call it and must spend the proceeds on network works in the area. Studies must also stay valid: their validity is set in the premises and cannot be under three months.
Cost to do it: On an estimated investment of Q7,641,870 (US$1,000,000) the guarantee is Q382,093.50 (US$50,000), plus the issuer's premium.
Example: A project with Q7,641,870 at its charge posts Q382,093.50. / On US$1 million the guarantee is US$50,000; on US$5 million it is US$250,000.Resolución CNEE-230-2026, Art. 13, Paso 4 and Paso 6; art. 4.1 i), 2026-07-16 official text · verified 2026-10-31 · changed: The guarantee is new in CNEE-230-2026; it is not in the 2014 articles.
4. Selling and running the plant. The interconnection contract is not a power purchase agreement. The applicant may sell the energy under the general rules; a distributed generator in the wholesale market must follow the coordination norms, and its dispatch may not interfere with the AMM's economic dispatch. The distributor operates and dispatches the distributed plants on its network, and they pay for this through a charge the CNEE will define in the tariff schedules. Batteries forming part of the plant may not charge from the grid, only from the plant. Maintenance disconnections need 48 hours' notice, save for emergencies. Technical standards are IEEE 1547 and, for inverters, UL 1741 or the IEC equivalent.
Cost to do it: The operation and dispatch charge in art. 24 was not yet set in the text reviewed; model it as an open cost. The applicant also pays tolls to the transporter (art. 5.2 m).
Example: A 3 MW solar plant with a battery charges only from its panels; it cannot arbitrage grid prices. / A developer's revenue model should list a separate line for the art. 24 charge once the CNEE publishes it.Resolución CNEE-230-2026, Art. 2, 5.1 d), 5.2, 8, 15, 17, 19, 20 and 24, 2026-07-16 official text · verified 2026-10-31
5. Transition. Plants with a CNEE connection authorization have five years from entry into force to adapt their agreements or sign the new contract. Connection requests already filed continue under the old rules unless the applicant opts in. Distributors had 60 days to apply the norm and file their grid code, digital platform plan, costs and model contract with the CNEE; if the platform is not ready, paper filing is allowed until 31 July 2027. Distributors must also publish a six monthly indicative map of network capacity, which is not binding. A dispute goes to the CNEE within 5 days of notice, with a hearing within 5 days and a decision within 10 days after it. The norm enters into force 15 days after publication.
Cost to do it: No fee is stated for a CNEE dispute.
Example: A project that filed in June 2026 can stay under the 2014 process, or opt into the 2026 one. / An operating 2 MW plant has until five years after the norm took effect to sign the new contract.Resolución CNEE-230-2026, Art. 4.2 o), 14, 26, 27, 28, 29 and 31, 2026-07-16 official text · verified 2026-10-31 · changed: Trade press and law firm notes report publication in the Diario de Centro América on 27 July 2026 and entry into force on 17 August 2026 (secondary, not read in the gazette).
6. Own use with surplus: no sale, only a credit. A user with renewable generation inside its own consumption premises that does not want to sell tells the distributor by form and needs no authorization, but must install protection that stops injection during a network fault. The distributor inspects within 15 days and installs a two way meter within 28 days of the notice, paid by the distributor for regulated users and by the user for large users. There is no payment for energy sent to the grid: a month of net injection becomes a kWh credit against later consumption, while the fixed charge and any capacity charges still apply.
Cost to do it: The installation and protection cost is the user's; the meter is free for regulated users. No authorization fee.
Example: A shop that consumes 3,000 kWh and generates 3,400 kWh in a month pays no energy charge, carries 400 kWh forward, and still pays the fixed charge. / A hotel's US$200,000 solar roof earns no cash for surplus, so size it to consumption.Resolución CNEE-227-2014 (25 August 2014), Norma Técnica de Generación Distribuida Renovable y Usuarios Autoproductores con Excedentes de Energía, Art. 3 (definition) and 36 to 40, kept in force by CNEE-230-2026 art. 30, 2014-08-25 official text · verified 2026-10-31
StepWhoPeriod
Preliminary report (optional)Distributor10 days; not binding
1. DCC request checkedDistributor, then applicant5 days; 5 days to fix; 5 days to recheck
2. Initial evaluationDistributor10 days; DCC in 5 days if minor works suffice
3. Options meetingApplicant, then distributor5 days to continue; meeting within 10 days
4. StudiesDistributor or applicantPremises in 10 business days; 20 days to DCC, or 20 + 10 days
5. CNEE authorizationDistributor, then CNEE5 days to file; 20 days to decide
6. Interconnection contract and guaranteeBoth10 days
7. CommissioningBoth5 days' notice; 5 days for report; 5 days for approval

Connection path under CNEE-230-2026 art. 13, using the norm's stated periods.

Worked example

  • A company plans a 2 MW solar plant with Q7,641,870 (US$1,000,000) of grid and plant investment at its charge, and needs a network reconductoring studied by the distributor.
  • Guarantee at contract stage: 5 percent, Q382,093.50 (US$50,000).
  • Time to contract on the norm's periods: about 100 days, plus any gaps in the file. Environmental documents are filed with the DCC request (art. 12).
  • Costs to model: processing fee, studies, upgrades, tolls to the transporter, and the art. 24 operation charge that the CNEE has yet to set.
  • Sales are separate: the interconnection contract is not a power purchase agreement, so the buyer must be arranged apart.

Step by step

  1. 1. Confirm title or lawful possession of the site and the net injection of 5 MW or less.
  2. 2. For hydro, register the water levels with the Dirección General de Energía before the DCC request (art. 5.2 l).
  3. 3. Check the distributor's published capacity map, then ask for the preliminary report if useful.
  4. 4. File the DCC request with legal and environmental documents and pay the processing cost.
  5. 5. Follow the steps in art. 13, sign the contract, post the 5 percent guarantee and commission the plant.
  6. 6. Own use only: file the notice with the distributor, install protection, and let the distributor inspect and fit the two way meter.

Common traps

  • Relying on the old toll exemption. Art. 35 of the 2014 norm said distributed generators paid no distributor or secondary system tolls, but CNEE-230-2026 art. 30 repealed art. 16 to 35. Art. 5.2 m) now says the applicant pays the transporter's tolls.
  • Treating the preliminary report as a reservation. Art. 11 says it reserves no capacity and grants no right.
  • Missing a 5 day window. If gaps are not fixed in 5 days the request counts as withdrawn, and missing the options meeting means rejection, so queue position can be lost.
  • Reading the capacity map as a promise. Art. 4.2 o) calls it indicative and not binding.
  • Pairing batteries with grid arbitrage. Art. 15 bars charging from the distribution system.
  • Counting days. The norm mostly says días, and only Paso 4 says días hábiles. The calculation of the 60 day and 15 day periods was not stated, so confirm any deadline with the distributor.

Sources

Related pages

Related: Guatemala country profile · live dashboard · central bank and release calendar · our posts on X