Countries › Mexico › Guide › 12. Sectors › Electricity generation and the wholesale power market in Mexico
Electricity generation and the wholesale power market in Mexico
Last verified: 2026-10-26 · Status: Changing
Private companies may build and own power plants in Mexico, but only within the Ministry of Energy's binding plan and with the State keeping a majority of generation through CFE. Plants of 0.7 MW or more need a generation permit from the National Energy Commission (CNE), which must decide within 60 business days, plus a separate interconnection contract and, before any works start, an approved energy social impact assessment. Sellers into the wholesale market are dispatched by CENACE, joint projects with CFE run for at most 30 years with CFE holding at least 54 percent in mixed investment, and fines for operating without a permit reach 10 percent of prior year gross income.
USD conversions use MXN 18.6638 per US dollar, the US Federal Reserve H.10 noon buying rate in New York for 23 October 2026 (FRED series DEXMXUS), the latest observation available when this page was verified. Legal conversions in Mexico use the Banxico FIX, which differs slightly. Conversions are for orientation only. Fines set in UMA use the 2026 daily UMA of MXN 117.31 published by INEGI in the DOF of 9 January 2026.
Key facts
| Plant capacity from which a CNE generation permit is required | 0.7 MWLSE art. 19, as of 2026-10-26 · in force |
|---|---|
| Maximum time for CNE or SENER to decide a permit or authorization | 60 business daysReglamento LSE art. 25, as of 2026-10-26 · in force |
| Maximum time for SENER to decide the energy social impact assessment | 90 calendar daysLSE art. 139, as of 2026-10-26 · in force |
| Minimum CFE stake in mixed investment generation projects | 54 %LSE art. 40, section I, as of 2026-10-26 · in force |
| Maximum term of joint State and private generation projects | 30 yearsReglamento LSE art. 73, as of 2026-10-26 · in force |
| Fine for generating without a permit | 10 % of prior year gross incomeLSE art. 184, section I, item l), as of 2026-10-26 · in force |
| Time to sign the interconnection or connection contract once offered | 10 business daysLSE art. 49, as of 2026-10-26 · in force |
The rule
Cost to do it: Permit fees are not quantified here because the Ley Federal de Derechos (art. 56) still refers to the former regulator and permit categories. Budget for the engineering, interconnection studies and legal work behind the application.
Example: A 0.6 MW rooftop solar array on a warehouse in Querétaro is an exempt generator and needs no CNE permit; expanding it to 0.8 MW makes it subject to the permit requirement. / The thresholds are in megawatts, not money: a 0.8 MW array needs a permit whether it costs USD 600,000 or USD 900,000.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025; Reglamento de la Ley del Sector Eléctrico, DOF 3 October 2025, LSE arts. 16 to 20; Reglamento arts. 19 and 24, 2025-03-18 official text · verified 2026-10-26 · changed: The LSE of 18 March 2025 repealed the Ley de la Industria Eléctrica of 11 August 2014 and moved generation permits from the former Energy Regulatory Commission (CRE) to the new CNE.
Cost to do it: No fee. The cost is timing: a project outside the plan may not get interconnection capacity.
Example: A developer planning a 200 MW wind farm in Oaxaca checks the May plan and the transmission program to see whether the regional grid has expansion works scheduled before committing to land and turbines. / On a project of about USD 250 million, a plan mismatch can delay revenue by years, so the plan review comes before any capital commitment.Constitución Política, arts. 25, 27 sixth paragraph and 28, reformed DOF 31 October 2024; Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025; Reglamento de la Ley del Sector Eléctrico, DOF 3 October 2025, LSE arts. 12 and 13; Reglamento art. 12, 2025-03-18 official text · verified 2026-10-26
Cost to do it: Expect parallel spending on the CENACE interconnection studies and guarantee deposits authorized by the CNE (LSE art. 49) while the permit is pending.
Example: An application filed on 2 March is due for decision about three months later once weekends and official holidays are excluded from the 60 business days. / No currency amount applies; the deadline is procedural.Reglamento de la Ley del Sector Eléctrico, DOF 3 October 2025, Reglamento arts. 19, 24 to 28, 2025-10-03 official text · verified 2026-10-26
Cost to do it: Grid reinforcement works or contributions are paid by the developer under CNE methodologies; guarantee deposits and periodic fees before commercial operation are authorized by the CNE.
Example: A 50 MW solar park in Sonora whose CENACE study requires a new 115 kV bay can build the bay itself to CFE specifications and then owes no contribution for it. / A substation bay can cost several million US dollars; building it directly avoids paying the same amount as a contribution.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 48 to 50 and 184, section I, item m), 2025-03-18 official text · verified 2026-10-26
Cost to do it: Fine range for market offer breaches: MXN 15,015,680 (about USD 804,535) to MXN 60,297,340 (about USD 3,230,711) in 2026.
Example: A generator that withholds capacity from its CENACE offers faces a fine from MXN 15,015,680 to MXN 60,297,340, doubled for repeat offenses. / That is roughly USD 804,535 to USD 3,230,711 at the October 2026 rate.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 21 to 23, 35 to 37, 73 to 78, 120 and 184, section II, item d), 2025-03-18 official text · verified 2026-10-26
Cost to do it: No statutory fee; partner selection follows guidelines issued by CFE's board and published in the DOF.
Example: In a 500 MW mixed investment combined cycle plant, CFE must hold at least 54 percent, so a private investor can hold at most 46 percent, for example MXN 4,600 million of a MXN 10,000 million equity base. / That private stake would be about USD 246,466,422 of an equity base of about USD 535,796,569.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025; Reglamento de la Ley del Sector Eléctrico, DOF 3 October 2025, LSE arts. 38 to 40; Reglamento arts. 71 to 74, 2025-10-03 official text · verified 2026-10-26
Cost to do it: Starting works without MIS approval: MXN 40,354,640 (about USD 2,162,188) to MXN 121,063,920 (about USD 6,486,563). Breach of MIS conditions: MXN 1,994,270 (about USD 106,852) to MXN 20,177,320 (about USD 1,081,094).
Example: A developer that clears land for a 30 MW plant before SENER approves its MIS risks a fine of at least MXN 40,354,640 and losing the permit. / The minimum fine alone is about USD 2,162,188, more than the civil works budget of many mid size solar plants.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 135 to 141, 184 section I item g) and 186; transitory art. Décimo Segundo, 2025-03-18 official text · verified 2026-10-26
Cost to do it: No fee is set for migration in the law; the cost is renegotiating supply arrangements before the legacy permit ends.
Example: A legacy self supply society whose permit expires in 2030 has to plan migration or new supply contracts for its partner load centers before that date, because the permit will lapse without renewal. / No currency amount applies; the risk is loss of the supply arrangement at expiry.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE transitory arts. Quinto to Noveno and Décimo Primero, 2025-03-18 official text · verified 2026-10-26 · changed: Since 19 March 2025 legacy permits under the 1975 and 2014 laws can no longer be extended at expiry.
Cost to do it: 2026 ranges: MXN 15,015,680 (about USD 804,535) to MXN 60,297,340 (about USD 3,230,711) for permit or market rule breaches; MXN 3,050,060 (about USD 163,421) to MXN 15,015,680 (about USD 804,535) for case by case supply breaches.
Example: A generator with MXN 800 million of gross income last year that operates a 5 MW plant without a permit faces a fine of MXN 80 million. / That is about USD 4,286,373.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 184 to 187, 2025-03-18 official text · verified 2026-10-26
| Route | Size | Permit | Who buys the output | Rule |
|---|---|---|---|---|
| Distributed generation | Below 0.7 MW, on a distribution circuit | None (exempt generator) | Own use or sale through CFE as basic supplier under CNE contract models | LSE arts. 24 to 27 |
| Isolated self supply | 0.7 MW or more, not grid connected | CNE generation permit | Only the permit holder, on site | LSE arts. 30 and 31 |
| Interconnected self supply | 0.7 MW or more; simplified procedure for 0.7 to 20 MW | CNE generation permit and interconnection contract | Permit holder on site; surplus only to CFE or injected without payment | LSE arts. 30 and 32 |
| Wholesale market generation | 0.7 MW or more | CNE generation permit and interconnection contract | Market participants through CENACE dispatch | LSE arts. 35 to 37 |
| Long term production with CFE | Any, within the binding plan | Contract with CFE | CFE only | LSE art. 39 |
| Mixed investment with CFE | Any, within the binding plan | Contract with CFE; CFE at least 54 percent | CFE preferentially; rest marketed through CFE | LSE art. 40 |
Routes to generate electricity in Mexico, verified 26 October 2026 against the LSE and its regulation.
Worked example
- A Spanish developer plans a 100 MW solar plant in Zacatecas selling into the wholesale market. It confirms the project fits the SENER plan, files the MIS (SENER decides within 90 calendar days), applies for the CNE generation permit (60 business days) and in parallel requests the CENACE interconnection study. If it cleared land before MIS approval, the fine would start at MXN 40,354,640 (about USD 2,162,188).
- A Mexican manufacturer with a legacy 2014 law self supply permit expiring in 2029 cannot extend it. It can migrate to interconnected self supply under the LSE or register its plants as qualified users and buy from a qualified services supplier.
Step by step
- 1. Check the SENER Electricity Sector Development Plan (published each May) and the transmission and distribution expansion programs for the region.
- 2. Choose the route: distributed generation, self supply, wholesale market or a joint scheme with CFE.
- 3. Prepare and file the energy social impact assessment with SENER; do not start any works until it is approved (90 calendar days).
- 4. File the CNE generation permit application (decision within 60 business days) and, separately, the CENACE interconnection request.
- 5. Sign the interconnection contract within 10 business days of the offer and post the guarantees authorized by the CNE.
- 6. Register a market participant (or appoint a representative), then operate under CENACE instructions and file the yearly social management plan report.
Common traps
- Treating the CNE permit as grid access. Interconnection priority never depends on having a permit (LSE art. 49).
- Starting earthworks before the social impact approval: fines from 344,000 times the daily UMA and denial of the permit (LSE art. 186).
- Assuming a legacy permit can be renewed. Permits under the 1975 and 2014 laws end at expiry (LSE transitory arts. Quinto and Noveno).
- Amending a pending application substantively without withdrawing it; the authority keeps evaluating the original filing (Reglamento art. 26).
- Selling surplus from an interconnected self supply plant to anyone other than CFE (LSE art. 32).
Sources
- Ley del Sector Eléctrico, DOF 18 March 2025, Chamber of Deputies text
- Ley del Sector Eléctrico (copy consulted)
- Reglamento de la Ley del Sector Eléctrico, DOF 3 October 2025, Chamber of Deputies text
- Reglamento de la Ley del Sector Eléctrico (copy consulted)
- Constitución Política, last reform DOF 7 October 2026, Chamber of Deputies text
- Constitución Política (copy consulted)
- IMSS Acuerdo ACDO.AS2.HCT.270126/9.P.DIR citing the 2026 UMA of MXN 117.31
- US Federal Reserve H.10 via FRED, Mexican pesos to one US dollar (DEXMXUS)
Related pages
- sectors/overview
- sectors/self-supply-distributed-generation-and-storage
- sectors/geothermal-and-biofuels
- investing/restricted-and-reserved-activities
- regulation/overview
- taxes/tax-incentives