Countries › Mexico › Guide › 12. Sectors › Self supply, distributed generation, storage and clean energy certificates in Mexico
Self supply, distributed generation, storage and clean energy certificates in Mexico
Last verified: 2026-10-26 · Status: Changing
Companies can generate their own power in Mexico: below 0.7 MW with no permit as distributed generation, and from 0.7 MW as self supply with a CNE permit, simplified for interconnected plants of 0.7 to 20 MW. Surplus from interconnected self supply may only be sold to CFE or injected without payment, and intermittent plants that inject must bring their own storage backup or pay CFE for it. Stand alone batteries of 0.7 MW or more need a CNE storage permit, and suppliers, qualified market users and self supplied users must meet clean energy certificate obligations, with fines of 6 to 50 UMA for each missing certificate.
USD conversions use MXN 18.6638 per US dollar, the US Federal Reserve H.10 noon buying rate in New York for 23 October 2026 (FRED series DEXMXUS), the latest observation available when this page was verified. Legal conversions in Mexico use the Banxico FIX, which differs slightly. Conversions are for orientation only. Fines set in UMA use the 2026 daily UMA of MXN 117.31 published by INEGI in the DOF of 9 January 2026.
Key facts
| Maximum capacity of distributed generation (exempt, no permit) | 0.7 MW (below)LSE arts. 19 and 25, as of 2026-10-26 · in force |
|---|---|
| Upper capacity for the simplified interconnected self supply permit | 20 MWLSE art. 30, as of 2026-10-26 · in force |
| Stand alone storage capacity from which a CNE storage permit is required | 0.7 MWReglamento LSE art. 193, as of 2026-10-26 · in force |
| Validity of a clean energy certificate | 30 monthsLSE art. 146, as of 2026-10-26 · in force |
| Minimum fine per missing clean energy certificate | 6 UMALSE art. 184, section IV, as of 2026-10-26 · in force |
| Maximum fine per missing clean energy certificate | 50 UMALSE art. 184, section IV, as of 2026-10-26 · in force |
The rule
Cost to do it: No generation permit fee. Costs are the equipment, a bidirectional meter and the CFE interconnection paperwork.
Example: A hotel in Mérida installs 450 kW of rooftop solar and signs a CNE model contract with CFE to be paid for energy it exports; it needs no CNE permit. / A 450 kW rooftop system is sized by capacity, so it stays permit free regardless of cost.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 19, 24 to 29, 2025-03-18 official text · verified 2026-10-26
Cost to do it: A CNE generation permit is required; fees under the Ley Federal de Derechos are not quantified here because art. 56 still refers to the former regulator.
Example: An auto parts plant in Coahuila builds an 18 MW solar plant on its own site, connected to the grid: it qualifies for the simplified procedure because it is below 20 MW. / A 25 MW plant at the same site would need the ordinary permit procedure, whatever its cost.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 30, 31, 33 and 34, 2025-03-18 official text · verified 2026-10-26
Cost to do it: If the plant is intermittent and exports, the cost of storage backup or of the backup charge payable to CFE must be built into the business case.
Example: A food processor with 12 MW of solar that exports midday surplus must either install batteries or pay CFE for backup, and can only sell the surplus to CFE. / No statutory amount; backup charges are set under CNE methodologies.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 32 and 33, 2025-03-18 official text · verified 2026-10-26
Cost to do it: CNE storage permit; no fee is quantified here for the same reason as generation permits.
Example: A 10 MW battery at an industrial park substation, not tied to any plant, needs a CNE storage permit; the same battery inside a permitted solar plant does not. / No currency threshold; the 0.7 MW test is technical.Reglamento de la Ley del Sector Eléctrico, DOF 3 October 2025; Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, Reglamento arts. 19, 24, 29, 193 to 195; LSE arts. 50 and 85, 2025-10-03 official text · verified 2026-10-26
Cost to do it: Fine per missing certificate in 2026: MXN 703.86 to MXN 5,865.50 (about USD 38 to USD 314).
Example: A self supplied user short by 10,000 certificates faces a fine of MXN 7,038,600 to MXN 58,655,000. / That is roughly USD 377,126 to USD 3,142,715.Ley del Sector Eléctrico (LSE), new law DOF 18 March 2025, in force 19 March 2025, LSE arts. 142 to 149 and 184, section IV, item c), 2025-03-18 official text · verified 2026-10-26
Cost to do it: No fee; the economic effect comes through the yearly CEL requirement.
Example: A supplier budgeting for 2028 reads the CEL requirement SENER sets in the first four months of 2026, which covers 2027 to 2029. / No currency amount applies.Ley de Planeación y Transición Energética, new law DOF 18 March 2025, Arts. 25 and 26; transitory art. Sexto, 2025-03-18 official text · verified 2026-10-26 · changed: The 2025 law repealed the Ley de Transición Energética of 24 December 2015.
| Option | Capacity | Permit | Surplus | Clean energy duty |
|---|---|---|---|---|
| Distributed generation | Below 0.7 MW | None | Sold through CFE as basic supplier, or a qualified supplier if metering is separate | Not an obligated party as generator |
| Isolated self supply | 0.7 MW or more | CNE permit | None, all consumed on site | End user supplied by self supply is obligated |
| Interconnected self supply | 0.7 MW or more (simplified 0.7 to 20 MW) | CNE permit and interconnection contract | Free injection or sale only to CFE; own backup if intermittent | End user supplied by self supply is obligated |
| Stand alone storage | 0.7 MW or more | CNE storage permit | Market sales through a participant | Not eligible for CELs |
Own generation options compared, verified 26 October 2026.
Worked example
- A beverage bottler in Jalisco consuming 60 GWh a year builds a 15 MW interconnected solar plant. It files for the simplified CNE permit, signs an interconnection contract, installs a 5 MW battery as backup because it will export at midday, and sells surplus only to CFE. If SENER's CEL requirement leaves it 3,000 certificates short, the fine would be MXN 2,111,580 to MXN 17,596,500 (about USD 113,138 to USD 942,814), so it buys certificates instead.
Step by step
- 1. Size the plant against the 0.7 MW and 20 MW thresholds.
- 2. Below 0.7 MW: request interconnection from CFE as distributor and, if exporting, sign the CNE model contract with CFE.
- 3. From 0.7 MW: apply for the CNE generation permit (simplified if 0.7 to 20 MW and interconnected) and the interconnection contract; check whether a social impact assessment applies.
- 4. If intermittent and exporting, add storage or agree backup with CFE before injecting.
- 5. Track the CEL requirement SENER publishes in January to April and buy or generate certificates before each compliance period.
Common traps
- Selling self supply surplus to a neighbor or affiliate. Only CFE may buy it (LSE art. 32).
- Overlooking CEL obligations for self supplied users; they are obligated parties (LSE art. 144).
- Assuming batteries earn CELs. They do not (Reglamento art. 195).
- Treating the 20 MW simplified band as an exemption. A permit is still required, only the procedure is simpler (LSE art. 30).
Sources
- Ley del Sector Eléctrico, DOF 18 March 2025, Chamber of Deputies text
- Ley del Sector Eléctrico (copy consulted)
- Reglamento de la Ley del Sector Eléctrico, DOF 3 October 2025, Chamber of Deputies text
- Reglamento de la Ley del Sector Eléctrico (copy consulted)
- Ley de Planeación y Transición Energética, DOF 18 March 2025, Chamber of Deputies text
- Ley de Planeación y Transición Energética (copy consulted)
- IMSS Acuerdo citing the 2026 UMA of MXN 117.31
- US Federal Reserve H.10 via FRED (DEXMXUS)
Related pages
- sectors/electricity-generation-and-power-market
- sectors/overview
- real-estate/water-rights
- taxes/tax-incentives
- /country/mexico/
- /calendar/
- Live dashboard
Related: Mexico country profile · live dashboard · central bank and release calendar · our posts on X