Countries › Bolivia › Guide › 12. Sectors › Rooftop solar, distributed generation and renewable projects
Rooftop solar, distributed generation and renewable projects
Last verified: 2026-11-15 · Status: Changing
Regulated consumers may generate renewable power for their own use and inject surplus under net metering. Since February 2026, plants of 1 to 6 MW can inject into medium voltage networks with a regulator authorization and no generation licence. Distributors may also own renewables up to 15 percent of their maximum demand.
Key facts
| Nanogeneration ceiling | 10 kWD.S. 4477 art. 3 a), text of D.S. 5167 art. 2 II, as of 2026-11-11 · in force |
|---|---|
| Microgeneration ceiling | 50 kWD.S. 4477 art. 3 b), text of D.S. 5167 art. 2 II, as of 2026-11-11 · in force |
| Minigeneration ceiling | 500 kWD.S. 4477 art. 3 c), text of D.S. 5167 art. 2 II, as of 2026-11-11 · in force |
| Medium scale floor | 1 MWD.S. 5549 art. 3 I, as of 2026-02-18 · in force |
| Medium scale ceiling | 6 MWD.S. 5549 art. 3 I, as of 2026-02-18 · in force |
| Distributor renewable ownership ceiling | 15 % of maximum demandD.S. 5616 (ministry summary), as of 2026-05-01 · in force |
| Macrogeneration (self producer) ceiling | 6000 kWResolución AETN 336/2026, as of 2026-06-02 · in force |
The rule
Cost to do it: Connection works are at the generator's cost. Installer registration with AETN is free (inscripción sin costo) under Resolución AETN 301/2026, according to the AETN distributed generation page.D.S. 4477 as amended by D.S. 5167 and D.S. 5549; Resolución AETN 301/2026, Art. 4 a) and c), art. 6 II, 2026-02-18 official text · verified 2026-11-11
| Size | Who | Sale of energy | Title |
|---|---|---|---|
| Up to 10 kW | Regulated consumer | Net metering | Distributor approval and registration |
| Over 10 to 50 kW | Regulated consumer | Net metering | Distributor approval and registration |
| Over 50 to 500 kW | Regulated consumer | Net metering | Distributor approval and registration |
| Over 500 kW to 6,000 kW | Regulated consumer, self production only | Own use, remote withdrawal | AETN inscription and distributor registration as self producer |
| 1 to 6 MW | Any person | Stabilized price under contract | Regulator authorization, no licence if the three conditions hold |
| Above that, or into the trunk grid | Generator | Wholesale market or contract | Ley 1604 regime (concession, licence or registration by activity and size) |
Routes by size
Worked example
- A factory in Santa Cruz with a 400 kW roof system consumes 50,000 kWh in a month, generates 42,000 kWh and injects 12,000 kWh of that at weekends. Under net metering, the balance runs on consumed energy against injected energy, and the regulator's method values the result. Before sizing, ask the distributor how its tariff blocks treat this.
Step by step
- Pick a tier and check that the installer is registered with AETN.
- File the project with the distributor.
- Install and pass inspection.
- Sign the contract with the distributor.
- For 1 to 6 MW, check feeder capacity and get the regulator's authorization.
Common traps
- The 1 to 6 MW exemption falls away if energy reaches the trunk grid, directly or indirectly, or if the plant joins dispatch.
- Medium scale prices are regulated: Resolución AETN 180/2026 sets stabilized prices for solar PV by yield and land cost. We did not read the annex figures, so take the price for your site from the resolution before modelling revenue.
- Only regulated consumers qualify below medium scale, so a pure investor needs a consumer's site or the medium scale route.
- D.S. 5549 also gave CNDC 30 working days to adapt its rules. Confirm the CNDC procedures exist before financing.
- Distributed generators cannot use the Tarifa Dignidad discount (D.S. 4477, Disposición Adicional Segunda).
Sources
- D.S. 4477 (AETN copy)
- D.S. 5167 (AETN copy of the Gaceta text)
- D.S. 5549 (AETN copy of the Gaceta text)
- Resolución AETN 380/2024, distributed generation payment regulation
- Resolución AETN 180/2026, medium scale payment regulation
- Resolución AETN 336/2026 notice
- AETN distributed generation page
- Ministry of Hydrocarbons and Energy note on D.S. 5616
- Ministry of Hydrocarbons and Energy note on the Green Energy bill
Related pages
- sectors/electricity-market
- sectors/sectors-reform-tracker
- investing/investment-incentives-map
- /country/bolivia/
- /calendar/
- Live dashboard
Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.
