Countries › Bolivia › Guide › 12. Sectors › Mining licences, contracts and pre 2014 rights
Mining licences, contracts and pre 2014 rights
Last verified: 2026-10-31 · Status: Changing
Bolivia grants no mining concessions. Private miners explore under a licence of up to 8 years and exploit under an administrative mining contract of 30 years, extendable once. Areas cannot be sold, leased or mortgaged. Foreigners face a 50 km border ban, and older rights had until 30 April 2026 to apply to convert.
USD figures use Bs 12.09 per US dollar, the official rate (TCO) published by the Banco Central de Bolivia for 31 October to 3 November 2026. UFV amounts use Bs 3.36631 per UFV from the same BCB page. The rate now floats, so boliviano amounts stay the same while their dollar value changes. Conversions are for orientation only.
Key facts
| Mining contract term, private | 30 yearsLey 535 art. 142, as of 2026-10-31 · in force |
|---|---|
| Extension | 30 yearsLey 535 art. 142, as of 2026-10-31 · in force |
| Maximum contract area | 250 cuadrículas (6,250 ha)Ley 535 art. 141, as of 2026-10-31 · in force |
| Maximum exploration licence area | 500 cuadrículas (12,500 ha)Ley 535 art. 158, as of 2026-10-31 · in force |
| Exploration licence term | 5 years, plus 3Ley 535 art. 159, as of 2026-10-31 · in force |
| Start of work after contract | 12 monthsLey 535 art. 144, as of 2026-10-31 · in force |
| Foreign exclusion from border | 50 kmLey 535 art. 28, as of 2026-10-31 · in force |
| Assembly term on new contracts | 90 daysLey 535 art. 132, as of 2026-10-31 · in force |
| Prior rights that had not applied to adapt | 1166 rightsR.M. 069/2026 recitals, as of 2026-04-30 · in force |
The rule
| Title | Purpose | Size limit | Term | Grantor |
|---|---|---|---|---|
| Cateo | Surface prospecting | None | No right | None |
| Exploration licence | Prospecting and exploration | 500 cuadrículas | 5 + 3 years | AJAM |
| Aerial prospecting licence | Air survey | 8,000 cuadrículas | 6 months | AJAM |
| Administrative mining contract | Chain activities | 250 cuadrículas | 30 + 30 years | AJAM, Assembly |
| Association contract | With State company | By contract | By contract | State company, Assembly |
| Production contract | COMIBOL areas | By contract | By contract | COMIBOL |
| Operating licence | Stand alone plants | Plant | By law | AJAM |
| Trading licence | Stand alone trade | None | By law | AJAM |
Mining titles compared
Worked example
- A foreign backed Bolivian company takes a 200 cuadrícula exploration licence (5,000 hectares). After drilling it selects 100 cuadrículas (2,500 hectares) and uses its preferential right to apply for a contract. At the 2026 patent of Bs 815 per cuadrícula it pays Bs 81,500 (US$6,741.11) a year (see sectors/mining-royalty-and-patent), and consultation and Assembly approval still lie ahead.
Step by step
- Search AJAM's cadastre and get the free area certificate.
- Set up a company that fits art. 29 and 33, with domicile where the mine sits.
- Apply for the exploration licence and pay the patent within 20 working days of AJAM's order.
- Run the work plan and file six monthly reports.
- Use the preferential right and apply for a contract.
- Complete prior consultation and the environmental licence.
- Send the contract for Assembly approval.
- Register it and start work within 1 year.
Common traps
- Selling the mining company is not the same as assigning a contract, but take advice: Constitution art. 371 and Ley 535 art. 136 limit transfers.
- Check if a seller holds an unadapted old right. After 30 April 2026 reversion can apply.
- Do not place a mine or its company within 50 km of the border using foreign capital without checking art. 28.
- Do not plan a lease of the mine to a cooperative. Leases are barred and cooperatives face limits on private contracts.
- Some older copies print the pre 2016 text of art. 142. Use the AJAM copy, which carries amendment notes.
- A short bill to allow private and cooperative contracts is reported in the press, not enacted. See the reform tracker.
Sources
- Constitución Política del Estado (INRA copy)
- Ley 535 (AJAM copy with amendment notes)
- R.M. 069/2026
- AJAM
Related pages
- sectors/mining-royalty-and-patent
- sectors/mineral-trading-and-gold-exports
- sectors/mining-environment-consultation-and-closure
- sectors/lithium-and-evaporites
- real-estate/foreign-ownership-and-the-border-zone
- /country/bolivia/
- /calendar/
- Live dashboard
Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.