The LatAm Thread

Countries › Bolivia › Guide › 12. Sectors › Electricity market: generation, transmission, distribution and tariffs

Electricity market: generation, transmission, distribution and tariffs

Last verified: 2026-11-15 · Status: Changing

Bolivia's 1994 electricity law splits the grid into generation, transmission and distribution, with licences for the first two and concessions for distribution. Foreign firms must operate through a local S.A., and since April 2026 most projects under 2,000 kW (6,000 kW for renewables) need no licence. The Constitution keeps the chain under the State, and a bill sent to the Assembly on 30 September 2026 would replace the 1994 law.

USD figures use Bs 12.09 per US dollar, the official rate (TCO) published by the Banco Central de Bolivia for 31 October to 3 November 2026. The rate now floats, so boliviano amounts stay the same while their dollar value changes. Conversions are for orientation only.

Key facts

Self production without licence, below2000 kWRes. AETN 180/2026; D.S. 24043 RCLLP art. 4 b), as of 2026-11-11 · in force
Supply to third parties without title, below2000 kWRes. AETN 180/2026; D.S. 24043 RCLLP art. 4 a), as of 2026-11-11 · in force
Renewable production without title, below6000 kWRes. AETN 180/2026; D.S. 24043 RCLLP art. 4 c), as of 2026-11-11 · in force
Maximum distribution concession40 yearsLey 1604 art. 2, as of 2026-11-11 · in force
Regulation fee ceiling1 % of salesLey 1604 art. 14, as of 2026-11-11 · in force
Ceiling on average monthly change in regulated distribution tariffs5 %D.S. 5647 (ministry note of 30 Sep 2026), as of 2026-11-15 · in force
Foreign company vehicleBolivian S.A. subsidiary textLey 1604 art. 10, as of 2026-11-11 · in force
Private generation allowedYes, under licence and CPE art. 378 textCPE art. 378; Ley 1604 art. 23, as of 2026-11-11 · in force

The rule

1. Energy is a strategic resource. Generation, transport and distribution are a State power exercised through public, mixed, nonprofit, cooperative, private, community and social companies. The chain cannot be subject only to private interests or be concessioned, and the law regulates private participation.Constitución Política del Estado, Art. 378, 2009-02-07 official text · verified 2026-11-11
2. Firms work under free competition. In the interconnected system, companies must be unbundled and limited to generation, transmission or distribution, with limits on cross ownership.Ley 1604 de Electricidad, Art. 7 and 15, 1994-12-21 official text · verified 2026-11-11
3. Distributors may own renewable generation up to 15 percent of their maximum demand in the interconnected system, as allowed by art. 15 d) of Ley 1604. The ministry says the decree also bars cross subsidies between generation and distribution, requires separate accounts, and limits injections into the trunk transmission system except where the authority allows them.D.S. 5616 (as described by the Ministry of Hydrocarbons and Energies), Ministry note of 1 May 2026; Ley 1604 art. 15 d), 2026-04-27 official text · verified 2026-11-11 · changed: New decree of 27 April 2026.
4. Foreign companies must form a subsidiary as a Bolivian sociedad anónima to work in the industry, except branches that already held older concessions.
Cost to do it: S.A. formation cost and capital are on entities/sociedad-anonima.Ley 1604 de Electricidad, Art. 10, 1994-12-21 official text · verified 2026-11-11
5. Licences are required for generation above regulated minimums, for transmission, and for transmission tied to generation. Studies of plants that use natural resources need a provisional licence.Ley 1604 de Electricidad, Art. 23 and 24, 1994-12-21 official text · verified 2026-11-11
6. No title or licence is needed below these power limits: supply to third parties 2,000 kW; self production for own use 2,000 kW; renewable production, including medium scale distributed generators (GDME), 6,000 kW; distribution by a self producer that is not a public service 500 kW; integrated activities in isolated systems 2,000 kW; distribution outside distributors' concession areas 2,000 kW. The resolution revoked Res. SSDE 044/2008, which had set all limits at 2,000 kW.Resolución AETN 180/2026 (limits under art. 4 of the Reglamento de Concesiones, Licencias y Licencias Provisionales, D.S. 24043), Resuelve Primero and Segundo (PDF page 30), 2026-04-01 official text · verified 2026-11-11 · changed: Res. AETN 180/2026 of 1 April 2026 raised the renewable limit to 6,000 kW, set 500 kW for self producer distribution and revoked Res. SSDE 044/2008 (all limits 2,000 kW).
7. Distribution concessions, and concessions for integrated activities in isolated systems, run for up to 40 years. Provisional licences for studies last up to 3 years and can be extended once for the same maximum.Ley 1604 de Electricidad, Art. 2 (definitions of Concesión and Licencia Provisional), 1994-12-21 official text · verified 2026-11-11
8. Electricity companies pay a regulation fee of up to 1 percent of sales before indirect taxes.
Cost to do it: Up to 1 percent of sales.
Example: On sales of Bs 12,090,000, up to Bs 120,900. / On sales of US$1,000,000, up to US$10,000.Ley 1604 de Electricidad, Art. 14, 1994-12-21 official text · verified 2026-11-11
9. Titles may also carry a right payment set in the tender or by regulation, which funds rural electrification.Ley 1604 de Electricidad, Art. 8, 1994-12-21 official text · verified 2026-11-11
10. Transfers outside supply contracts are valued at marginal cost set by the dispatch committee, CNDC. Maximum prices apply to transmission, distribution, node supply and regulated consumers. The discount rate is 10 percent real a year, and the ministry can move it by up to 2 points.Ley 1604 de Electricidad, Art. 45 and 48, 1994-12-21 official text · verified 2026-11-11
11. Exports, imports and international links follow Executive policy and the law.Ley 1604 de Electricidad, Art. 9, 1994-12-21 official text · verified 2026-11-11
12. Licences can be revoked for failing to build on time, changing purpose without approval or breaching duties.Ley 1604 de Electricidad, Art. 33, 1994-12-21 official text · verified 2026-11-11
13. The ministry says D.S. 5647, promulgated in June 2026, sets a ceiling of 5 percent on the average monthly change in regulated distribution tariffs, allows semiannual stabilization factors, and creates compensation funds for the agents of the interconnected system (SIN). It says the stabilization fund is administered by the electricity authority and absorbs cost changes that are not billed at once.D.S. 5647 (as described by the Ministry of Hydrocarbons and Energies), Ministry notes of 30 September and 2 July 2026, 2026-07-02 official text · verified 2026-11-15 · changed: Decree promulgated in June 2026 set a 5 percent ceiling on average monthly distribution tariff changes and added stabilization factors and compensation funds.
14. The Presidency says D.S. 5750 updates how electricity prices are calculated: the exchange rate input becomes the average for the whole month instead of the rate of the 25th, to avoid abrupt moves. It rejected reports that the decree means a monthly tariff increase.D.S. 5750 (as described by the Presidency), Presidency press note of 14 October 2026, 2026-10-14 official text · verified 2026-11-15 · changed: October 2026 decree switched the exchange rate used in electricity price calculations from the rate of the 25th to a monthly average.
15. The ministry says the bill sent on 30 September 2026 proposes an open market model, lets private firms build international links, a role it says was held by ENDE, returns energy policy to the ministry, and makes the electricity authority and CNDC independent.Electricity bill (pending), Ministry note of 30 September 2026, 2026-09-30 official text · verified 2026-11-11
16. Electricity exports reached US$32 million in the first half of 2026, up 291.9 percent.BCB, Balance of Payments report, first half 2026, Cuadro I.3, 2026-09-30 official text · verified 2026-11-11
ActivityTitleTermNorm
Generation to third parties from 2,000 kWLicenceNot stated in Ley 1604Ley 1604 art. 23; Res. AETN 180/2026
Self production from 2,000 kWLicenceNot stated in Ley 1604Ley 1604 art. 23; Res. AETN 180/2026
Renewable production from 6,000 kWLicenceNot stated in Ley 1604Ley 1604 art. 23; Res. AETN 180/2026
TransmissionLicenceNot stated in Ley 1604Ley 1604 art. 23
DistributionConcessionUp to 40 yearsLey 1604 art. 2
Plant studies using natural resourcesProvisional licenceUp to 3 years, one extensionLey 1604 art. 2 and 24
Distributed generationRegistration or authorizationSee renewables pageD.S. 4477

Which title for which activity

Worked example

  • A 20 MW generator selling Bs 60,450,000 (US$5,000,000) a year pays up to Bs 604,500 (US$50,000) of regulation fee at the 1 percent ceiling, before income tax and remittance withholding.

Step by step

  1. Form the S.A.
  2. Choose the site and check environmental and land rules.
  3. Obtain a provisional licence for studies where needed.
  4. Apply to AETN for the licence and sign the contract.
  5. Join the wholesale market under CNDC rules.
  6. Watch the bill, which may change the structure mid project.

Common traps

  • Unbundling means a generator cannot hold a stake in a transmission company, so a developer cannot own a shared line through its generation vehicle without checking art. 15.
  • Ley 1604 calls the regulator the Superintendency. It is now AETN.
  • Older summaries still quote 300 kW limits for supply to third parties and renewables. Res. AETN 180/2026 sets 2,000 kW and 6,000 kW, and AETN can move the limits again by resolution.
  • Some reports call D.S. 5750 a monthly tariff rise; the Presidency says it only changes the exchange rate input to a monthly average. The decree text was not reachable online, so read the official text before relying on it for a contract.
  • We did not read the electricity bill itself; its content here comes from the ministry note.
  • We found no 2026 official figures for installed capacity or peak demand, so none are shown.

Sources

Related pages

Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X