No company can own Bolivian oil or gas in the ground or at the wellhead. Private firms work under contracts with YPFB, for up to 40 years, won in international tenders and approved by the Assembly. The government has announced a new hydrocarbons law and a deputy's reform bill is pending, so check their status before pricing any bid.

USD figures use Bs 12.09 per US dollar, the official rate (TCO) published by the Banco Central de Bolivia for 31 October to 3 November 2026. UFV amounts use Bs 3.36631 per UFV from the same BCB page. The rate now floats, so boliviano amounts stay the same while their dollar value changes. Conversions are for orientation only.

Key facts

Maximum contract term40 yearsLey 3058 art. 65, as of 2026-10-31 · in force
State roleAll production and sale belong to the State through YPFB textCPE art. 359 and 361, as of 2026-10-31 · in force
Initial exploration, Traditional Zone7 yearsLey 3058 art. 36, as of 2026-10-31 · in force
Initial exploration, Non Traditional Zone10 yearsLey 3058 art. 36, as of 2026-10-31 · in force
Maximum parcels, Traditional Zone40 parcelsLey 3058 art. 34, as of 2026-10-31 · in force
Maximum parcels, Non Traditional Zone400 parcelsLey 3058 art. 34, as of 2026-10-31 · in force
Parcel size2500 hectaresLey 3058 art. 138, as of 2026-10-31 · in force

The rule

1. Hydrocarbons are inalienable property of the Bolivian people. The State owns all production and alone may sell it, and all sale revenue belongs to the State. No contract may breach this.Constitución Política del Estado, Art. 359, 2009-02-07 official text · verified 2026-10-31
2. YPFB is an autarkic public company, immune from attachment, and the only body empowered to run the hydrocarbon chain and its sale.Constitución Política del Estado, Art. 361, 2009-02-07 official text · verified 2026-10-31
3. YPFB may sign service contracts with public, mixed or private firms, Bolivian or foreign, which act in its name for pay. These contracts cannot mean losses for YPFB or the State.Constitución Política del Estado, Art. 362 I, 2009-02-07 official text · verified 2026-10-31
4. Exploration and exploitation contracts need prior authorization and express approval of the Assembly, or they are void.Constitución Política del Estado, Art. 362 II, 2009-02-07 official text · verified 2026-10-31
5. Foreign firms in the chain are under Bolivian law and authorities. No foreign court, international arbitration or diplomatic claim is recognized.Constitución Política del Estado, Art. 366, 2009-02-07 official text · verified 2026-10-31
6. The 2006 nationalization decree obliged producers to deliver all their output to YPFB from 1 May 2006, and YPFB took over its sale and set volumes and prices. YPFB's audited notes describe a 180 day term from promulgation, and YPFB took ownership and sale under the new contracts from 1 May 2007.D.S. 28701, Art. 1 and 2, as summarized in YPFB audited notes (Note 1 and 4), 2006-05-01 official text · verified 2026-11-11 · changed: On 11 November 2026 the source moved from an unofficial copy to YPFB's audited notes; the claim that firms not signing new contracts in 180 days had to stop operating was dropped because no official text could be read.
7. Ley 3058 lets any person, Bolivian or foreign, sign Production Sharing, Operation or Association contracts with YPFB for exploration and exploitation, for up to 40 years. These forms predate the Constitution, so read them with art. 362.Ley 3058 de Hidrocarburos, Art. 65, 2005-05-17 official text · verified 2026-10-31
8. The holder delivers all production to YPFB and receives a fee or a share as the contract states. No contract can confer ownership of deposits, or of hydrocarbons at the wellhead or up to the measuring point.Ley 3058 de Hidrocarburos, Art. 16 and 66, 2005-05-17 official text · verified 2026-10-31
9. Free areas go out in international public tenders, leaving out areas reserved for YPFB. The ministry sets the award criteria, starting with work units for the first exploration phase.Ley 3058 de Hidrocarburos, Art. 35, 2005-05-17 official text · verified 2026-10-31
10. A contract area can reach 40 parcels in Traditional Zones and 400 in Non Traditional Zones. A parcel is a square of 5,000 m per side, or 2,500 hectares.Ley 3058 de Hidrocarburos, Art. 34 and 138, 2005-05-17 official text · verified 2026-10-31
11. Initial exploration runs up to 7 years in Traditional Zones and 10 in Non Traditional Zones, in three phases. For areas over 10 parcels, at least 20 percent and then 30 percent of the original excess goes back after phases 1 and 2.Ley 3058 de Hidrocarburos, Art. 36, 2005-05-17 official text · verified 2026-10-31
12. After a commercial discovery, an additional exploration period of up to 7 years can apply, keeping up to 30 percent of the original area.Ley 3058 de Hidrocarburos, Art. 37, 2005-05-17 official text · verified 2026-10-31
13. Commerciality is declared to YPFB. The holder then has 2 years to file the field development plan and 5 years from its approval to develop the field.Ley 3058 de Hidrocarburos, Art. 38 and 39, 2005-05-17 official text · verified 2026-10-31
14. Contracts are signed before a Government Notary and must include a performance guarantee, given by the parent for subsidiaries, and a bank guarantee for exploration work units.
Cost to do it: Notary fees and guarantee amounts depend on each contract and on regulation; we found no published amounts.Ley 3058 de Hidrocarburos, Art. 67, 2005-05-17 official text · verified 2026-10-31
15. Contracts cannot be assigned, directly or indirectly, without YPFB's acceptance and ministry authorization, plus the approval used for the contract itself.Ley 3058 de Hidrocarburos, Art. 68 and 70, 2005-05-17 official text · verified 2026-10-31
16. At the end of a contract the holder leaves installations in working order for YPFB and bears environmental liabilities up to transfer. Contracts provide for compensating productive investment not yet depreciated. A holder that has met its duties can leave during exploration by notice.Ley 3058 de Hidrocarburos, Art. 41 and 42, 2005-05-17 official text · verified 2026-10-31
17. Oil activity may take place in protected areas when the strategic environmental study approves it and conservation aims are not at risk. Prior consultation with indigenous peoples applies under ILO Convention 169.Ley 3058 de Hidrocarburos, Art. 32 and 115, 2005-05-17 official text · verified 2026-10-31
18. The government announced a new hydrocarbons law in April 2026 to remove discretion in existing contracts and attract new firms, and said it would go to the Assembly within days. At 17 November 2026 the Chamber of Deputies list of bills in progress shows no government hydrocarbons bill; the only full reform listed is PL 756/2025-2026, a deputy's bill for an integral reform of Ley 3058. Its cover letter is dated 1 September 2026 and carries the Chamber Presidency receipt stamp of 2 September 2026. Current law applies until a new one is published.PL 756/2025-2026 (pending) and Ministry of Hydrocarbons and Energy announcement, Bill cover letter and Chamber Presidency receipt stamp (page 1 of the scan); ministry note of 20 April 2026, 2026-09-02 official text · verified 2026-11-15 · changed: On 15 November 2026 the rule link moved from the bill's web page to the signed bill scan, whose first page shows the 2 September 2026 Presidency receipt stamp; on 11 November 2026 the press report on an imminent government bill had been replaced by the official Chamber of Deputies bill list and the ministry note.
StageTraditional ZoneNon Traditional Zone
Phase 1Years 1 to 3Years 1 to 5
Phase 2Years 4 and 5Years 6 to 8
Phase 3Years 6 and 7Years 9 and 10
Additional periodUp to 7 more years after a commercial discoveryUp to 7 more years after a commercial discovery
Area return20% after phase 1 and 30% after phase 2, of original excess over 10 parcelsSame

Exploration timeline

ZoneParcelsHectares
Traditional40100,000
Non Traditional4001,000,000

Size of maximum contract areas

Worked example

  • A company bids for a 40 parcel block in a Traditional Zone, or 100,000 hectares. If it wins, its first phase runs up to 3 years. If the block stays at 40 parcels, the excess over 10 parcels is 30 parcels, so at least 6 parcels (15,000 hectares) go back after phase 1 and at least 9 more (22,500 hectares) after phase 2.

Step by step

  1. Confirm the area is free and not reserved to YPFB.
  2. Form the Bolivian vehicle or branch you will use and check entities/branch-of-a-foreign-company.
  3. Bid in the international tender.
  4. Negotiate the contract and sign before a Government Notary.
  5. Obtain Assembly authorization and approval.
  6. Obtain environmental licences and complete consultation.
  7. Run the work program, report to YPFB and declare commerciality.

Common traps

  • A contract signed without Assembly approval is void, with no court ruling needed.
  • Ley 3058 art. 69 refers disputes to Bolivian law and the Constitution bars international arbitration in this chain, so do not assume the rules of investing/investment-treaties cover you. Take advice on disputes/investment-arbitration.
  • Indirect transfers also need consent, so a share sale at parent level can fall under art. 70.
  • Ley 3058 still cites the 1967 Constitution and the Superintendency. Read every article with the 2009 Constitution.
  • Reserves data matters for bids. Ask YPFB for the latest certified reserves before pricing a block, and do not rely on press figures.

Sources

Related pages

Related: Bolivia country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.