Countries › Ecuador › Guide › 12. Sectors › Renewables and self generation in Ecuador: the 100 MW private route, preferential prices and self supply
Renewables and self generation in Ecuador: the 100 MW private route, preferential prices and self supply
Last verified: 2026-11-15 · Status: Changing
Private projects outside the Master Plan up to 100 MW can go ahead with ministry approval, while larger ones go to public selection. Only non conventional renewables up to 10 MW get both preferential dispatch and price; storage backed renewables and transition plants up to 100 MW get priority and a preferential price. Businesses can install self supply systems, owned by themselves or third parties, and new Autonomous Energy Districts can run their own grids.
Ecuador is dollarized: the US dollar is the currency in use, so local currency and USD amounts are the same and no conversion is applied. Amounts tied to the basic wage use US$482 a month, the 2026 figure set by Acuerdo MDT-2025-195 (Registro Oficial Suplemento 187, 18 December 2025).
Key facts
The rule
1. Private initiative projects not in the Master Plan may go ahead at the promoter's risk with express ministry approval, if they do not exceed 100 MW for non conventional renewables or 100 MW for transition energy. Larger ones go to public selection, with benefits for the promoter.
Ley Orgánica para Impulsar la Iniciativa Privada en la Generación de Energías, Registro Oficial Octavo Suplemento 673, 28 October 2024, Disposición Reformatoria Primera, amending the Ley Orgánica del Servicio Público de Energía Eléctrica (LOSPEE, RO 418 3S, 16 January 2015), no. Seis, replacing LOSPEE art. 52, 2024-10-28 official text · verified 2026-11-15 · changed: LOSPEE art. 52 was replaced by no. Seis of the Disposición Reformatoria Primera of the law in RO 673 8S of 28 October 2024. 2. Among private projects outside the Master Plan, only non conventional renewable projects up to 10 MW get both preferential dispatch and preferential price. Clean technology and non conventional renewable projects with storage and a grid interconnection of up to 100 MW, and transition projects up to 100 MW, get priority and a preferential price as set by the regulator.
Ley Orgánica para Impulsar la Iniciativa Privada en la Generación de Energías, Registro Oficial Octavo Suplemento 673, 28 October 2024, Disposición Reformatoria Primera, amending the Ley Orgánica del Servicio Público de Energía Eléctrica (LOSPEE, RO 418 3S, 16 January 2015), no. Seis, replacing LOSPEE art. 52, 2024-10-28 official text · verified 2026-11-15 3. For private projects outside the Plan a promoter has a right to improve its offer if others appear in a public selection.
Ley Orgánica para Impulsar la Iniciativa Privada en la Generación de Energías, Registro Oficial Octavo Suplemento 673, 28 October 2024, Disposición Reformatoria Primera, amending the Ley Orgánica del Servicio Público de Energía Eléctrica (LOSPEE, RO 418 3S, 16 January 2015), no. Cuatro, adding a final paragraph to LOSPEE art. 40, 2024-10-28 official text · verified 2026-11-15 4. Non conventional renewable projects up to 10 MW outside the Master Plan may be delegated directly; if the promoter takes the preferential price and dispatch it must sign regulated contracts, and otherwise it sells under the transaction types of the regulation. Renewable projects above 10 MW and up to 100 MW, and transition projects up to 100 MW, may be authorized to take preferential price conditions under the regulation issued for that purpose.
Reglamento General a la LOSPEE, Decreto Ejecutivo 856, RO Suplemento 21, 20 August 2019; art. 22 as replaced by Decreto Ejecutivo 32, RO Suplemento 62, 18 June 2025 (ARCONEL consolidated copy to 18 June 2025), art. 22, letter a), nos. a.1 and a.2 (first paragraph), 2025-06-18 official text · verified 2026-11-15 5. Transition generation covers low emission technologies such as natural gas, liquefied petroleum gas, associated gas, nuclear and green hydrogen. The ministry sets the maximum emissions level for a plant to count as transition energy, based on reports of the environmental authority.
Decreto Ejecutivo 515, Registro Oficial Noveno Suplemento 380, 30 September 2026, amending the Reglamento General a la LOSPEE, art. 7, replacing the second and third paragraphs of Reglamento art. 22, letter a), no. a.2, 2026-09-30 official text · verified 2026-11-15 · changed: Art. 22 no. a.2 second and third paragraphs were replaced by art. 7 of Decreto Ejecutivo 515 (RO 380 9S, 30 September 2026), which added liquefied petroleum gas and associated gas and the ministry emissions ceiling. 6. A project may include storage or complementary services. Urban waste generation may be delegated directly, with a firm commitment from the municipality, and has preferential terms.
Reglamento General a la LOSPEE, Decreto Ejecutivo 856, RO Suplemento 21, 20 August 2019; art. 22 as replaced by Decreto Ejecutivo 32 (RO S 62, 18 June 2025); urban waste article added by Decreto Ejecutivo 176 (RO S 507, 28 February 2024) (ARCONEL consolidated copy), art. 22, final paragraph, and unnumbered art. Generación eléctrica a partir de residuos urbanos, 2025-06-18 official text · verified 2026-11-15 7. To get a Qualification Certificate the applicant posts a bank guarantee or insurance policy of 20 basic wages for projects up to 10 MW and 40 basic wages between 10 and 100 MW. The guarantee is called if it withdraws or fails to sign in time.
Cost to do it: US$9,640 (20 × US$482) or US$19,280 (40 × US$482) at the 2026 basic wage set by Acuerdo MDT-2025-195 (RO Suplemento 187, 18 December 2025).
Example: 50 MW project: 40 × US$482 = US$19,280 / US$19,280
Decreto Ejecutivo 515, Registro Oficial Noveno Suplemento 380, 30 September 2026, amending the Reglamento General a la LOSPEE, art. 43, adding the unnumbered art. Del Certificado de Calificación after Reglamento art. 129, 2026-09-30 official text · verified 2026-11-15 8. A project cannot be split into parts of up to 100 MW to avoid public selection. The ministry looks at corporate and economic links between promoters.
Decreto Ejecutivo 515, Registro Oficial Noveno Suplemento 380, 30 September 2026, amending the Reglamento General a la LOSPEE, art. 52, adding Reglamento art. 132.1, 2026-09-30 official text · verified 2026-11-15 · changed: Added by art. 52 of Decreto Ejecutivo 515 (RO 380 9S, 30 September 2026). 9. Regulated and non regulated consumers may install generation solely for self supply, connected to the distribution or transmission grid. The system may belong to the consumer or to a third party, if the energy goes only to that consumer, and third parties may be hired to finance, install and operate it, respecting the distributors' exclusive right to sell. Excess treatment is set in the Reglamento and regulator rules.
Ley Orgánica para el Fortalecimiento de los Sectores Estratégicos de Minería y Energía, Registro Oficial Quinto Suplemento 234, 2 March 2026, amending the LOSPEE (RO 418 3S, 16 January 2015), art. 23, replacing the unnumbered LOSPEE art. after art. 44, 2026-03-02 official text · verified 2026-11-15 · changed: Replaced by art. 23 of the law in RO 234 5S of 2 March 2026. 10. Regulated consumers with self supply pay grid use or availability charges, and there is no adjacency limit for their systems. The distribution or transmission company authorizes regulated consumers, and the regulator authorizes large consumers and self generators' own consumption. Third party owned self supply systems count as public service providers.
Decreto Ejecutivo 515, Registro Oficial Noveno Suplemento 380, 30 September 2026, amending the Reglamento General a la LOSPEE, art. 11, replacing Reglamento art. 24, 2026-09-30 official text · verified 2026-11-15 · changed: Reglamento art. 24 was replaced by art. 11 of Decreto Ejecutivo 515 (RO 380 9S, 30 September 2026). 11. Autonomous Energy Districts are private, mixed or popular economy entities owning a grid with local or remote generation for their own demand, which may offer excess to the national grid. They need a ministry title.
Ley Orgánica para el Fortalecimiento de los Sectores Estratégicos de Minería y Energía, Registro Oficial Quinto Suplemento 234, 2 March 2026, amending the LOSPEE (RO 418 3S, 16 January 2015), art. 15 (LOSPEE art. 3, definition 27) and art. 24 (adding LOSPEE art. 45.2), 2026-03-02 official text · verified 2026-11-15 · changed: Added by art. 24 of the law in RO 234 of 2 March 2026. 12. At the end of an enabling title, assets used for the public service revert to the State at no cost through the energy ministry, or the holder must remove them at its own cost if the State has no interest. Excluded from reversion are real estate and assets installed by end users for self supply, self generators, cogenerators, non conventional renewable generators up to 10 MW and all private initiative assets of projects that are not part of the Master Plan. For hydroelectric operating authorizations and concessions, all assets used for the public service transfer to the State at no cost and without exception.
Ley Orgánica para el Fortalecimiento de los Sectores Estratégicos de Minería y Energía, Registro Oficial Quinto Suplemento 234, 2 March 2026, amending the LOSPEE (RO 418 3S, 16 January 2015), art. 19, replacing LOSPEE art. 33, 2026-03-02 official text · verified 2026-11-15 · changed: LOSPEE art. 33 was replaced by art. 19 of the law in RO 234 5S of 2 March 2026, which added private initiative projects outside the Master Plan to the reversion exclusions (RO 673 of 28 October 2024 had excluded self supply assets, self generators, cogenerators and renewables up to 10 MW). Project routes by size
Worked example
- A 40 MW solar and battery project with its own grid link qualifies for direct delegation, priority and a preferential price under the regulator's rules, but not for preferential dispatch, which stops at 10 MW. It posts a US$19,280 guarantee (40 × US$482) to get the Qualification Certificate.
Step by step
- Size the project against 10 and 100 MW.
- File with the ministry and get the Qualification Certificate.
- Post the guarantee.
- Secure resource, environmental and grid studies.
- Sign the title.
- For self supply, ask the distributor or regulator.
Common traps
- Above 10 MW the law gives priority and a preferential price only to storage backed renewables with a grid link and to transition plants; preferential dispatch stays limited to renewables up to 10 MW.
- Splitting projects below 100 MW is barred.
- Whether a gas plant counts as transition energy depends on the emissions limit that the ministry sets.
- The preferential price level is set by ARCONEL regulation and is not stated here.
- LOSPEE art. 52 still says the infrastructure of private projects outside the Master Plan reverts to the State at the end of the concession, while art. 33 as replaced in March 2026 excludes those assets from reversion; hydroelectric assets transfer without exception. Read the reversion clause of the enabling title.
Sources
Related pages
Related: Ecuador country profile · live dashboard · central bank and release calendar · our posts on X