Oil and gas belong to the State, which explores through public companies and may delegate to private firms by participation or service contract, generally through a public tender. Oil contracts run up to four years of exploration plus two, then up to 20 years of exploitation. Transfers need ministry approval, and part of the current text was struck by the Constitutional Court in form, so check each article.

Ecuador is dollarized: the US dollar is the currency in use, so local currency and USD amounts are the same and no conversion is applied.

Key facts

Oil exploration period, before extension4 yearsLey de Hidrocarburos art. 23, as of 2026-11-15 · in force
Oil exploitation period, before extension20 yearsLey de Hidrocarburos art. 23, as of 2026-11-15 · in force
Gas exploitation period, before extension25 yearsLey de Hidrocarburos art. 23, as of 2026-11-15 · in force
Marginal field ceiling, share of national output1 %Acuerdo MAE-VH-2026-0016-AM, as of 2026-04-24 · in force

The rule

1. The State explores and exploits through public companies and may, as an exception, delegate to national or foreign companies or consortia of proven experience, by participation contracts, service contracts or other forms in use in the industry that do not conflict with Ecuadorian law.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, art. 2, 2021-11-29 official text · verified 2026-10-30 · changed: Art. 2 was replaced by RO 587 3S of 29 November 2021. Sentencia 110-21-IN/22, RO E.C. 160 of 11 January 2023, struck the article on form with effects to the future.
2. When awarding or changing a contract, accumulated State benefits cannot fall below those obtained up to the year before the change.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, art. 2, 2021-11-29 official text · verified 2026-10-30
3. In a participation contract the contractor takes all investment, cost and risk and, once production starts, receives a share of output at the offered percentages. That share, valued at the sale price and never below the reference price, is its gross income for income tax. If it returns or abandons the area, the State owes nothing.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, art. 12-A, 2021-11-29 official text · verified 2026-10-30
4. In a service contract the contractor invests its own resources and is paid a fee per net barrel delivered at the measuring point. The fee covers amortization, costs and a reasonable profit, and it is the contractor's gross income. All production stays with the State.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, arts. 16 and 49, 2010-07-27 official text · verified 2026-10-30
5. Awards are by tender through a ministry tender committee, except for contracts with State companies or their subsidiaries of other countries, mixed companies with a State majority, and specific works or services. Committee decisions are final.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, art. 19, 2010-07-27 official text · verified 2026-10-30
6. A 2026 ministry instruction sets how foreign State companies, their subsidiaries and consortia are rated for legal capacity, experience and related criteria, before proposals go to the committee (COLH).Acuerdo MAE-MAE-2026-0029-AM, Registro Oficial 255, 31 March 2026, arts. 1 and 2, 2026-03-31 official text · verified 2026-10-30 · changed: New instruction published 31 March 2026.
7. Oil exploration lasts up to four years, extendable by two. Work must begin within six months of registration in the Registro de Hidrocarburos, and registration is due within 30 days of signing. Oil exploitation lasts up to 20 years, extendable if it suits the State.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, art. 23, 2010-07-27 official text · verified 2026-11-15
8. Natural gas contracts have the same exploration period, then a market development and infrastructure period of five years, extendable, and an exploitation period of up to 25 years, extendable.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, art. 23, 2010-07-27 official text · verified 2026-11-15
9. Marginal field tenders require that a field or group of fields not exceed 1% of national output. A field is first rated marginal, and EP Petroecuador areas are returned on a provisional basis to allow the tender.Acuerdo MAE-VH-2026-0016-AM, Registro Oficial 272, 24 April 2026, arts. 2 to 8, 2026-04-24 official text · verified 2026-10-30 · changed: New instruction published 24 April 2026.
10. When producing fields run by EP Petroecuador are delegated by participation contract, the ministry, after COLH recommendation and approval, fixes the entry bonus for each tender and each block by area size, productive features, required investment and other technical features. It is paid when the contract is signed. A 2024 challenge to this article was not admitted by the Constitutional Court on 10 January 2025, which also refused to suspend it.Reglamento Codificado de Aplicación de la Ley de Hidrocarburos, Decreto Ejecutivo 947, Cuarto Suplemento del Registro Oficial, 28 November 2023 (text as transcribed in Constitutional Court auto, case 83-24-IN), art. 31, 2023-11-28 official text · verified 2026-11-15
11. Assignment of a contract or rights without ministry authorization is void and is a ground for forfeiture, and the State receives a transfer premium under the regulation. Trades on a stock exchange and reorganizations within a group are exempt from prior authorization, and transfers among parents, affiliates and subsidiaries carry no premium but must be reported.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, arts. 74 and 79, 2021-11-29 official text · verified 2026-10-30
12. Contracts may migrate to other models by agreement if it suits the State, with committee approval. Migration to participation requires more investment and better terms for the State.Ley de Hidrocarburos, Decreto Supremo 2967, Registro Oficial 711, 15 November 1978, consolidated to 11 January 2023, art. 31-A, 2021-11-29 official text · verified 2026-10-30
13. The ministry reports that the Ronda Intracampos III covers Lumbaqui (Block 11), Tetete Sur (Block 95) and Pañayacu Norte (Block 98) under participation contracts. Orion Energy and Gente Oil filed offers on 16 July 2026 for Blocks 95 and 11. The stated schedule has contracts signed in December 2026 and blocks delivered in January 2027.Ministerio de Ambiente y Energía, official notice, notice on offers received, 2026-07-16 official text · verified 2026-10-30
FeatureParticipationService
Investment and riskContractorContractor
PaymentShare of outputFee per net barrel
Who owns outputSplit per contractState
RoyaltiesPaid out of the State's shareNot paid by the contractor
Sovereignty marginNone stated25% of gross income

Participation versus service contract

Worked example

  • A company weighing a block under a service contract: on 100 barrels at US$80, gross income is US$8,000. The State first keeps US$2,000 as the 25% margin, then deducts its transport and sale costs, and then pays the fee from the rest. The contractor's revenue is capped by that remainder, so the fee must be modeled against low prices.

Step by step

  1. Check whether the area is in a tender or runs through a State to State route.
  2. Pass prequalification on experience and finances.
  3. Bid the State share and investment program.
  4. Sign and register within 30 days.
  5. Start work within six months.
  6. Get ministry approval for any transfer.

Common traps

  • The consolidated text read runs to January 2023. Arts. 2, 12-A, 31-A, 79 and others carry a note that Sentencia 110-21-IN/22 struck them on form with effects to the future, and the 2026 instructions still cite them. Have counsel confirm the operative text before relying on them.
  • Laws still name the Secretaría de Hidrocarburos, while recent acts are signed by the ministry and its vice ministry.
  • ITT Block 43 cannot get new contracts after the 2023 vote: see macro/oil-mining-and-energy.
  • Round dates have moved before. The ministry's notice does not confirm an award as of this page's date.

Sources

Related pages

Related: Ecuador country profile · live dashboard · central bank and release calendar · our posts on X

Get rule changes weekly

Free. One email a week from The LatAm Thread.

One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.