Countries › Haiti › Guide › 12. Sectors › Electricity in Haiti: ANARSE licences, exploitation rights, concessions, tariffs and penalties under the 2016 decree

Electricity in Haiti: ANARSE licences, exploitation rights, concessions, tariffs and penalties under the 2016 decree

Last verified: 2026-11-09 · Status: Stable

Since the decree of 6 January 2016, private companies may produce, transmit, distribute and sell electricity in Haiti, but each activity needs a licence, an exploitation right or a concession from the regulator, ANARSE. The decree is project finance friendly: lenders can take security over the title and step in on default, early withdrawal without fault pays unamortized investment plus 10 percent, and tariffs follow price caps with a 5 percent adjustment trigger. It is also criminal law: operating without a title costs up to 3 years in prison and a HTG 5 million fine, and an environmental non objection is required before any licence.

USD figures use HTG 130.7542 per US dollar, the Banque de la République d'Haïti reference rate published for 8 November 2026 and retrieved on 9 November 2026. Conversions are for orientation only.

Key facts

Maximum voltage of a distribution network57 kVDécret du 6 janvier 2016, art. 4 (2), as of 2026-11-09 · in force
Minimum voltage of a transmission network60 kVDécret du 6 janvier 2016, art. 4 (11), as of 2026-11-09 · in force
Renewal of licences and exploitation rightsNot renewable; new title only after a competitive process Décret du 6 janvier 2016, art. 34, as of 2026-11-09 · in force
Premium on unamortized investment paid on early withdrawal without fault10 %Décret du 6 janvier 2016, art. 37, as of 2026-11-09 · in force
Formula deviation that lets operators adjust tariffs5 %Décret du 6 janvier 2016, art. 60, as of 2026-11-09 · in force
Regular review of tariff adjustment formulas5 yearsDécret du 6 janvier 2016, art. 60, as of 2026-11-09 · in force
Minimum notice before ANARSE changes a licence or cahier des charges30 daysDécret du 6 janvier 2016, art. 42, as of 2026-11-09 · in force
Ministry of the Environment audit deadline for electricity projects30 daysDécret du 6 janvier 2016, art. 44, as of 2026-11-09 · in force
Fine for destroying or sabotaging power installations50000000 HTGDécret du 6 janvier 2016, art. 72, as of 2026-11-09 · in force

The rule

1. The 2016 decree governs every activity in the power chain: production, transmission, distribution and sale of electricity by any person in Haiti. Each activity needs one of three State titles: a licence, an exploitation right (droit d'exploitation) or a public service concession. A licence is granted by the regulator, ANARSE, and is formalized in a convention between ANARSE and the operator. An exploitation right is an exclusive convention that lets one operator use the public domain inside a defined territory to produce, transmit, distribute and sell power under a cahier des charges.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 1, 4 (3) and (6), 5, 6 and 7, 2016-01-06 official text · verified 2026-11-09
2. The voltage line between the two network businesses is fixed in the decree. Distribution covers lines, substations and transformers at 57 kV or less up to the final customer. Transmission covers lines and equipment at 60 kV or more, plus any lines ANARSE lists as transmission. Sale to third parties or final customers (commercialisation) is a separate licensed activity.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 4 (1), (2) and (11), 2016-01-06 official text · verified 2026-11-09
3. ANARSE grants licences and exploitation rights on nine criteria: ability to meet the cahier des charges, experience and the good standing of shareholders and managers, ability of the company or its shareholders to finance the project, safety, environment and urban planning compliance, civil liability cover, generation and distribution capacity in line with sector policy, system safety, and environmental protection and land use. The State may also delegate management of its own plants and networks through a public service concession, awarded under the public procurement and concession rules, or through an exploitation right.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 8 and 9, 2016-01-06 official text · verified 2026-11-09
4. A production licence is granted on individual request or after an ANARSE tender. The criteria are the energy source, site and land use, efficiency and timeliness, installed and nominal capacity, and the applicant's capacity to finance the project without a State guarantee. The production contract with ANARSE must cover access to land, rights and obligations, construction and operation, financing, tariff conditions, sanctions and dispute resolution. Any increase in installed capacity needs ANARSE approval.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 10 to 13 and 15, 2016-01-06 official text · verified 2026-11-09
5. Producers that already held a contract valid under Haitian law when the decree came into force are deemed authorized if they appear on a list set by order of the Minister of Public Works, Transport and Communications. Contracts with terms contrary to the decree had to be brought into line within 3 months of publication. Other contracts valid at that date remain valid until they expire.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 17 and 83, 2016-01-06 official text · verified 2026-11-09
6. A transmission licence is limited to the territory for which it was granted. The holder runs and develops the transmission grid, balances supply and demand, must keep commercial information confidential and may not discriminate between grid users within available capacity. The State, through ANARSE and with the transmission operators, coordinates dispatch, maintenance and flow regulation on interconnected grids. The transmission operator contracts with producers and eligible customers through competitive, transparent and non discriminatory procedures.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 18 to 24, 2016-01-06 official text · verified 2026-11-09
7. A distribution licence sets the exclusivity conditions inside its territory, and the holder runs and develops the distribution grid under its cahier des charges. Distribution licences are granted on the geographic zone, the power to be distributed, the installations, efficiency, fair treatment of consumers, local socio economic impact and proven financing capacity. A commercialisation licence covers a defined geographic area and is granted on the operator's capacity to meet its cahier des charges, its financial and technical capacity, and the experience and good standing of its managers.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 25 to 29, 2016-01-06 official text · verified 2026-11-09
8. An exploitation right covers integrated production, transmission, distribution and sale inside a perimeter. Its contract and annexed cahier des charges fix the territory, the term and the public service obligations. The holder must connect new operators that ask and accept the interconnection agreement, which ANARSE approves. Connection and grid reinforcement costs are negotiated between the parties under principles set by ANARSE. The holder also runs dispatch and prepares a generation development plan for its network.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 30 to 32, 2016-01-06 official text · verified 2026-11-09
9. Terms are set case by case, based on the size of the investment and the tariffs. Licences and exploitation rights are not renewable, either tacitly or automatically: at expiry a new title can be awarded only through a competitive process organised by ANARSE. The title gives the right to occupy the public and private domain of the State and local authorities needed for the installations, and land needed for works may be declared of public utility and expropriated.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 33, 34 and 36, 2016-01-06 official text · verified 2026-11-09
10. If the State withdraws a licence or terminates an exploitation right before its term for a reason other than the operator's breach, the operator is compensated. The compensation must at least equal the share of investments not yet amortized at the date of withdrawal, plus 10 percent of that amount as damages, and the detailed rules go in the production contract or exploitation right. The operator owns the installations during the term, and the contract sets what happens to them at expiry, including dismantling or transfer and the price.
Cost to do it: Minimum compensation on early withdrawal without fault: unamortized investment plus 10 percent of it.
Example: Unamortized investment HTG 1,307,542,000: minimum compensation HTG 1,438,296,200 / Unamortized investment US$10,000,000: minimum compensation US$11,000,000Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 37 and 38, 2016-01-06 official text · verified 2026-11-09
11. The decree is built for project finance. Rights under a licence or exploitation right can be pledged or assigned as security, and the installations and occupation rights can be mortgaged, but only to secure loans taken to finance building, modifying or running the installations. Security for a group of lenders can be granted to one of them or to an agent. Enforcement of the pledge or assignment transfers the installations and occupation rights to the new holder. The title may also give the financing lenders a step in right: if the holder defaults, they can take over the title or substitute an entity of their choice, even in bankruptcy or liquidation of the original holder.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 39 and 40, 2016-01-06 official text · verified 2026-11-09
12. Any agreement transferring the rights under a licence or exploitation right to a third party needs the prior approval of the granting authority. ANARSE may change licences, exploitation rights or their cahier des charges only for objective, non discriminatory and documented reasons, with at least 30 days for holders to respond. ANARSE may withdraw a title only for repeated, serious and manifest breach of legal, regulatory or contractual obligations.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 41 to 43, 2016-01-06 official text · verified 2026-11-09
13. Every electricity project needs a prior environmental and social impact study with its investment, financing, implementation and management plan. The Ministry of the Environment audits any project that presents a risk within 30 days of the request, and its non objection notice is mandatory before ANARSE grants the licence or exploitation right. Works in protected areas such as reserves and parks need a separate authorization from the environmental authority.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 44 and 48, 2016-01-06 official text · verified 2026-11-09
14. Licensed operators may be authorized to set up lines, supports and underground cables on private property declared of public utility, to fix supports to walls and roofs reachable from outside, to run lines over private property and to trim or cut trees, subject to safety and urban planning rules. Owners must be notified first except in emergencies, and no compensation is due for these easements. An owner must give the operator 3 months' notice by registered letter before demolition, raising, fencing or building works.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 50 and 52, 2016-01-06 official text · verified 2026-11-09
15. Tariffs for sale, purchase, network access and transit follow five principles: financial balance of the sector, its development, equal treatment within the same consumer category, recovery of costs and public service obligations, and the operator's return on investment. ANARSE sets price caps and adjustment formulas with a productivity incentive, and reviews their structure every 5 years or after a sudden fundamental change in costs. When the formulas show a deviation of more than 5 percent either way, operators may adjust tariffs after giving ANARSE 30 days' notice with calculations for review and approval.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 59 and 60, 2016-01-06 official text · verified 2026-11-09
16. Every supply needs a written contract, and contracts with public service customers follow a form approved by ANARSE. Customers with identical consumption profiles in the same exploitation right must be treated equally. Connection prices follow a price schedule approved by ANARSE. Every operator pays ANARSE a fee, for the State, based on turnover. Operators fall under ordinary tax and customs law, but specific financial, tax and customs advantages may be granted depending on the cahier des charges, the investment required and the network works.Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 64 to 68, 2016-01-06 official text · verified 2026-11-09
17. No generation, transmission or distribution installation may be put into service without an ANARSE certificate of conformity. The operator is liable for damage caused to a customer's property by a surge or other anomaly on its network, established by a justice of the peace report and an ANARSE technical opinion.
Cost to do it: Fine for commissioning without a certificate of conformity: HTG 1,000,000 to HTG 5,000,000 (US$7,647.94 to US$38,239.69), plus 3 to 6 months in prison.
Example: HTG 1,000,000 to HTG 5,000,000 / US$7,647.94 to US$38,239.69Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 54, 78 and 82, 2016-01-06 official text · verified 2026-11-09
18. The decree has a full criminal penalty scale. Operating without a licence or concession: 1 to 3 years and HTG 5 million. Connecting directly to a grid without a contract: 6 to 12 months plus damages to the operator. Sabotaging or blowing up a plant or network: 5 to 10 years and HTG 50 million. Cutting supply without valid reason: 3 to 6 months and HTG 500,000. Granting oneself a title illegally: 1 to 3 years and HTG 1 million. Power theft or meter tampering: 6 to 12 months and HTG 250,000 to HTG 1 million. Major grid disturbance from non approved internal installations: 3 to 6 months and HTG 10 million. Faulty work endangering people: 6 to 12 months and HTG 1 million to HTG 10 million. Interfering with grid installations in breach of art. 55: 6 to 12 months and HTG 1 million to HTG 15 million.
Cost to do it: Largest fine: HTG 50,000,000 (US$382,396.89) for sabotage or destruction of power installations.
Example: HTG 50,000,000 / US$382,396.89Décret du 6 janvier 2016 régissant le Secteur de l'Énergie Électrique (Le Moniteur No. 23 of 3 February 2016), art. 69 to 81, 2016-01-06 official text · verified 2026-11-09
TitleWhat it coversWho grants itKey terms
Licence (production, transmission, distribution or commercialisation)One activity; production licences may be site specific, network licences cover a territoryANARSE, on request or by tender (art. 10, 11)Convention with ANARSE; capacity increases need approval; not renewable (art. 13, 15, 34)
Exploitation right (droit d'exploitation)Integrated production, transmission, distribution and sale in a perimeterANARSE (art. 30)Exclusive; cahier des charges fixes term and public service duties; must interconnect new operators (art. 30, 31)
Public service concessionManagement of State plants and networks delegated to a private partyThe State, under the public procurement and concession rules (art. 9)Concession contract; same security and step in rules where the title provides (art. 39, 40)

The three titles under the 2016 electricity decree

OffencePrisonFine (HTG)Fine (USD)
Operating without a licence or concession (art. 69)1 to 3 yearsHTG 5,000,000US$38,239.69
Direct connection to a grid without a contract (art. 70)6 to 12 monthsDamages claimed by the operator
Destroying, sabotaging or blowing up a plant or network (art. 72)5 to 10 yearsHTG 50,000,000US$382,396.89
Cutting supply to consumers without valid reason (art. 73)3 to 6 monthsHTG 500,000US$3,823.97
Illegally granting oneself a title, or working on installations without mandate (art. 74)1 to 3 yearsHTG 1,000,000US$7,647.94
Power theft, fraudulent connection, broken meter seals (art. 75)6 to 12 monthsHTG 250,000 to HTG 1,000,000US$1,911.98 to US$7,647.94
Building under lines or occupying grid rights of way (art. 76)6 to 12 months; 1 to 5 years for whoever authorizes itHTG 500,000 to HTG 1,500,000 (HTG 1,500,000 to HTG 5,000,000 for the authorizer)US$3,823.97 to US$11,471.91
Major grid disturbance from non approved internal installations (art. 77)3 to 6 monthsHTG 10,000,000US$76,479.38
Commissioning without a certificate of conformity (art. 78)3 to 6 monthsHTG 1,000,000 to HTG 5,000,000US$7,647.94 to US$38,239.69
Faulty work exposing people and property to serious danger (art. 79)6 to 12 monthsHTG 1,000,000 to HTG 10,000,000US$7,647.94 to US$76,479.38
Obstructing authorized works or easements (art. 80)6 to 12 monthsHTG 500,000 to HTG 1,000,000US$3,823.97 to US$7,647.94
Interfering with grid installations or metering (art. 81, art. 55)6 to 12 monthsHTG 1,000,000 to HTG 15,000,000US$7,647.94 to US$114,719.07

Criminal penalties under the 2016 electricity decree (fines and prison may be combined; USD at HTG 130.7542)

Worked example

  • A developer builds a 10 MW plant under an ANARSE production licence. Five years in, the State withdraws the licence for policy reasons, with no breach by the developer. Unamortized investment at that date is US$10,000,000 (HTG 1,307,542,000). Under art. 37 the compensation must cover that amount plus 10 percent, so at least US$11,000,000 (HTG 1,438,296,200). The production contract should spell out the amortization method, because the decree leaves those rules to the contract.
  • A distributor's tariff formula shows that fuel and FX costs moved 6 percent above the cap since the last adjustment. Because the deviation exceeds 5 percent, art. 60 lets it adjust tariffs after sending ANARSE 30 days' notice with its calculations. A 4 percent deviation would have to wait for the 5 year formula review or a fundamental change in costs.

Step by step

  1. Map the project to a title: production licence for an IPP selling power, transmission or distribution licence for network assets, exploitation right for an integrated mini grid in a defined perimeter, concession for taking over State assets.
  2. Commission the environmental and social impact study early and file it with the Ministry of the Environment; its non objection, due within 30 days of the audit request, is a condition of the ANARSE title (art. 44).
  3. Prepare the ANARSE file against the art. 8 and art. 12 criteria: site and land rights, technology, capacity, financing plan without State guarantee, safety and insurance, and shareholder and management credentials.
  4. Negotiate the production contract or exploitation right: land access, tariff formula, sanctions, dispute resolution (art. 13), amortization basis for early withdrawal compensation (art. 37), fate of assets at expiry (art. 38), and lender security and step in clauses (art. 39, 40).
  5. Before signing any grid connection contract, check it has no exclusivity or preferential access clause and send it to ANARSE on signature (art. 16, 47).
  6. Obtain the ANARSE certificate of conformity before energizing anything (art. 54), then put supply contracts on the ANARSE approved form and bill only on metered consumption (art. 64, 65).
  7. Diary the ANARSE fee, the 5 year tariff formula review and the title expiry, since there is no automatic renewal (art. 34, 60, 67).

Common traps

  • There is no tacit or automatic renewal. Financing tenors longer than the title term carry rebid risk, because a new title at expiry requires a competitive process (art. 34).
  • Lender security is allowed only for loans that finance the installations (art. 39). Security for corporate or acquisition debt over the title itself is not covered by the decree.
  • Transferring rights under a licence or exploitation right needs prior approval of the granting authority (art. 41), which matters for share deals and refinancings structured as assignments.
  • The early withdrawal compensation of art. 37 does not apply when the title is withdrawn for the operator's repeated and serious breach (art. 43).
  • Distribution licences define exclusivity inside their territory (art. 25), but grid access for producers must stay non discriminatory (art. 16, 47). Do not assume exclusivity in generation.
  • Prison terms apply to de jure and de facto managers personally (art. 69), not only to the company.
  • ANARSE's annual fee is set on turnover (art. 67), but the decree itself does not state the rate. Get the rate in writing before pricing the tariff.

Sources

Related pages

Related: Haiti country profile · live dashboard · central bank and release calendar · our posts on X