Quarrying sand, gravel, limestone and other non metallic materials in Haiti needs a 5 year renewable permit from the Bureau des Mines et de l'Energie under a 1984 decree, capped at 10 hectares per permit and 30 hectares per holder. The 2026 Code Fiscal sets the money side: HTG 50,000 a year for a sand quarry permit, HTG 1 million a year for industrial sand and river quarrying, HTG 500,000 for industrial groundwater use, and per truck eco fees. You also need the Ministry of the Environment's non objection, title deeds, proof of tax compliance and a memorandum of agreement with the State.
USD figures use HTG 130.5300 per US dollar, the Banque de la République d'Haïti reference rate for 30 September 2026 (row 30-Sep-26 of the BRH 2025 2026 rate series). Conversions are for orientation only.
Key facts
| Quarry exploitation permit term | 5 years, renewable yearsDécret du 4 mars 1984, art. 12, as of 2026-11-15 · in force |
|---|---|
| Maximum area of one quarry permit | 10 haDécret du 4 mars 1984, art. 17, as of 2026-11-15 · in force |
| Maximum total quarry area per holder | 30 haDécret du 4 mars 1984, art. 17, as of 2026-11-15 · in force |
| Annual fee for a sand quarry exploitation permit | 50000 HTGCode Fiscal 2026, art. 168, as of 2026-11-15 · in force |
| Annual fee for industrial sand and river quarrying | 1000000 HTGCode Fiscal 2026, art. 169, as of 2026-11-15 · in force |
| Annual fee for industrial groundwater exploitation | 500000 HTGCode Fiscal 2026, art. 169, as of 2026-11-15 · in force |
| Eco fee per load of quarry sand on trucks of 8 tonnes or more | 150 HTGCode Fiscal 2026, art. 170, as of 2026-11-15 · in force |
The rule
Cost to do it: HTG 50,000 a year (US$383.05).
Example: HTG 50,000 / US$383.05Décret remplaçant le Décret du 19 décembre 2022 portant Code Fiscal (Le Moniteur Spécial N° 48-A of 30 September 2026), art. 168, 2026-09-30 official text · verified 2026-11-15
Cost to do it: Sand and river quarries HTG 1,000,000 (US$7,661.07); groundwater HTG 500,000 (US$3,830.54) a year.
Example: HTG 1,000,000 / HTG 500,000 / US$7,661.07 / US$3,830.54Décret remplaçant le Décret du 19 décembre 2022 portant Code Fiscal (Le Moniteur Spécial N° 48-A of 30 September 2026), art. 169, 2026-09-30 official text · verified 2026-11-15
Cost to do it: HTG 150 (US$1.15) per heavy sand load; HTG 15 (US$0.11) per m3 of fill.
Example: HTG 150 per load / US$1.15Décret remplaçant le Décret du 19 décembre 2022 portant Code Fiscal (Le Moniteur Spécial N° 48-A of 30 September 2026), art. 170 and 171, 2026-09-30 official text · verified 2026-11-15
| Item | Amount | USD | When | Collected by | Article |
|---|---|---|---|---|---|
| Sand quarry exploitation permit | HTG 50,000 a year | US$383.05 | Annually | BME | 168 |
| Industrial sand and river quarrying | HTG 1,000,000 a year | US$7,661.07 | 1 to 31 October | Not stated | 169 (1) a |
| Industrial groundwater exploitation | HTG 500,000 a year | US$3,830.54 | 1 to 31 October | Not stated | 169 (1) b |
| Quarry sand, truck of 8 tonnes or more | HTG 150 per load | US$1.15 | Per load | BME | 170 |
| Quarry sand, truck under 8 tonnes | HTG 100 per load | US$0.77 | Per load | BME | 170 |
| Fill material (bancs d'empoint) | HTG 15 per m3 | US$0.11 | Per m3 | BME | 170 |
| Other quarry substances, 4 tonne truck | HTG 100 per load | US$0.77 | Per load | Not stated | 171 |
| Other quarry substances, 2 tonne truck | HTG 50 per load | US$0.38 | Per load | Not stated | 171 |
Quarry and groundwater fees in the 2026 Code Fiscal (USD at HTG 130.5300, BRH rate for 30 September 2026)
Worked example
- A sand quarry holds a permit and ships 20 loads a day on 10 tonne trucks for 300 working days. Fees: the permit fee of HTG 50,000 plus 6,000 loads x HTG 150 = HTG 900,000, for HTG 950,000 a year (US$7,278.02). If the operation is industrial, art. 169 adds HTG 1,000,000 (US$7,661.07) payable in October; the Code does not say whether the art. 168 permit fee is then also due, so confirm with the BME and the DGI.
- A bottling plant draws groundwater industrially. It owes HTG 500,000 a year under art. 169, payable between 1 and 31 October, on top of ordinary corporate taxes.
Step by step
- Secure the land: title deeds, survey plan and survey report for an area of at most 10 hectares (30 hectares across all your permits).
- Commission the environmental and social impact study and obtain the Ministry of the Environment's non objection certificate.
- Get tax compliance papers in order: NIF, communal patente, quitus and tax registration for the activity.
- File the permit application with the BME in three copies, with the georeferenced map, working plan, rehabilitation undertaking, technical form and proof of capacity; the BME visits the site.
- Pay the permit fee and negotiate the protocole d'accord with the State on operating and tax conditions.
- Put a load register in place so the per truck eco fees can be paid and reconciled with the BME.
- Diary the 1 to 31 October window for industrial fees and the 5 year permit renewal.
Common traps
- The BME's own quarry page still describes the 2012 finance law charges, including 10 percent on sales of quarry products. That 10 percent charge is not in the 2026 Code Fiscal, and art. 541 repeals any tax not carried into the Code. Confirm the current charges with the DGI before pricing.
- The BME page dates the quarry decree to 4 March 1984 in one place and 2 March 1984 in another. Cite the Le Moniteur reference (No. 26 of 2 April 1984) in contracts.
- The 30 hectare cap counts permits held directly or indirectly (art. 17), so related companies' permits are added together.
- Riverbed and shoreline extraction falls under the quarry decree (art. 2) and usually triggers the strictest environmental review.
- Ministry officials and employees cannot hold quarry permits (art. 8), which matters when vetting local partners.
Sources
- Bureau des Mines et de l'Energie, carrières: cadre légal (Décret du 4 mars 1984, Le Moniteur No. 26 of 2 April 1984), archived copy of 10 June 2026, text identical to the live page https://bme.gouv.ht/index.php?p=carriere
- Bureau des Mines et de l'Energie, procédure d'octroi d'un permis d'exploitation de carrière, archived copy of 14 July 2026, text identical to the live page https://bme.gouv.ht/index.php?p=procedurecarriere
- Code Fiscal (Décret remplaçant le Décret du 19 décembre 2022 portant Code Fiscal), Le Moniteur Spécial N° 48-A of 30 September 2026 (Direction Générale des Impôts)
- Banque de la République d'Haïti, taux de change de référence, série 2025 2026 (row 30-Sep-26: HTG 130.5300)
Related pages
- sectors/overview
- sectors/mining-titles-and-permits
- regulation/regulatory-compliance-essentials
- taxes/local-taxes-patente
- taxes/property-taxes
- real-estate/land-and-property-system
- /country/haiti/
- /calendar/
- Live dashboard
Related: Haiti country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.