Countries › Haiti › Guide › 12. Sectors › Oil and gas exploration in Haiti: hydrocarbon prospecting and research permits, the BME procedure and the exploration record
Oil and gas exploration in Haiti: hydrocarbon prospecting and research permits, the BME procedure and the exploration record
Last verified: 2026-11-15 · Status: Stable
Haiti has no producing oil or gas fields. Exploration runs under the same 1976 decree as mining, through two permits from the Bureau des Mines et de l'Energie: prospecting (up to 500 km2, 5 years plus 2) and research (up to 500 km2, 5 years renewable for 3 year periods). The fees are HTG 25 and HTG 50 per km2 a year, still in 1976 gourdes, so the commercial terms sit in a convention negotiated with the State. The BME records 11 wells drilled from 1945 to 1977 with no confirmed hydrocarbons, and two exploration permits signed between 2015 and 2019.
USD figures use HTG 130.7437 per US dollar, the Banque de la République d'Haïti reference rate shown for 16 November 2026 on the BRH taux du jour page, retrieved on 17 November 2026. That page shows only the latest rate and BRH publishes no dated series online. Conversions are for orientation only.
Key facts
| Maximum area of a hydrocarbon prospecting permit | 500 km2Décret du 3 mars 1976, art. 47, as of 2026-11-15 · in force |
|---|---|
| Hydrocarbon prospecting permit term | 5 years plus a 2 year extension yearsDécret du 3 mars 1976, art. 47, as of 2026-11-15 · in force |
| Annual hydrocarbon prospecting permit fee | 25 HTG per km2Décret du 3 mars 1976, art. 47, as of 2026-11-15 · in force |
| Maximum area of a hydrocarbon research permit | 500 km2Décret du 3 mars 1976, art. 48, as of 2026-11-15 · in force |
| Hydrocarbon research permit term | 5 years, renewable for 3 year periods yearsDécret du 3 mars 1976, art. 48, as of 2026-11-15 · in force |
| Annual hydrocarbon research permit fee | 50 HTG per km2Décret du 3 mars 1976, art. 48, as of 2026-11-15 · in force |
| Deadline to start work after a hydrocarbon research permit is granted | 6 monthsDécret du 3 mars 1976, art. 48, as of 2026-11-15 · in force |
The rule
Cost to do it: HTG 25 per km2 per year: a 500 km2 permit costs HTG 12,500 a year (US$95.61).
Example: HTG 12,500 / US$95.61Décret du 3 mars 1976 encourageant la prospection minière sur toute l'étendue du territoire et adaptant les structures juridiques existantes aux réalités de l'industrie minière (Le Moniteur No. 19 of 8 March 1976), art. 47 (and art. 35 by reference), 1976-03-03 official text · verified 2026-11-15
Cost to do it: HTG 50 per km2 per year in advance: a 500 km2 permit costs HTG 25,000 a year (US$191.21).
Example: HTG 25,000 / US$191.21Décret du 3 mars 1976 encourageant la prospection minière sur toute l'étendue du territoire et adaptant les structures juridiques existantes aux réalités de l'industrie minière (Le Moniteur No. 19 of 8 March 1976), art. 48, 1976-03-03 official text · verified 2026-11-15
| Permit | Max area | Term | Annual fee | Transferable | Start of work |
|---|---|---|---|---|---|
| Prospecting | 500 km2 | 5 years plus 2 year extension | HTG 25 per km2 (US$0.19) | No (mining prospecting regime, art. 35) | Within 3 months under the mining prospecting regime (art. 35, applied by art. 47) |
| Research | 500 km2, inside the prospecting area | 5 years, renewable for 3 year periods | HTG 50 per km2 (US$0.38), in advance | No | Within 6 months (art. 48) |
Hydrocarbon permits under the 1976 decree (USD at HTG 130.7437)
| Period | What happened |
|---|---|
| 1939 to 1981 | Geological studies, gravity and magnetic surveys and drilling by several foreign companies |
| 1945 to 1977 | 11 wells drilled (8 onshore, 3 offshore) in the Cul de Sac plain, Artibonite plain, Central Plateau and Gonâve island; no confirmed hydrocarbons |
| Leads named by the BME | Gonâve island, Rochelois bank (Miragoâne), Central Plateau and Cul de Sac plain |
| 2015 to 2019 | Three companies applied for exploration permits; two obtained signed permits and one started field work at Bellevue, Boucan Carré |
Exploration record as published by the Bureau des Mines et de l'Energie
Worked example
- A company takes a 500 km2 prospecting permit for the full 7 years: 500 x HTG 25 x 7 = HTG 87,500 (US$669.25). It then takes a 500 km2 research permit for 5 years: 500 x HTG 50 x 5 = HTG 125,000 (US$956.07), paid in advance. The State fees are trivial next to seismic and drilling costs, which is why the convention, not the decree, decides the fiscal take.
Step by step
- Review the BME exploration record and data for the target basin, and check the mining cadastre for existing permits.
- Send the BME a prospecting request with a georeferenced perimeter map (WGS 84 UTM), company documents, technical references and 2 years of consolidated financial statements; name a technical director as the BME contact.
- Pay the fees and start work within the deadline; keep a log of any force majeure event, since only that stops the clock.
- Before the prospecting permit ends, file the detailed report and, if the results justify it, the research permit request with the list of target substances.
- Incorporate or convert to a Haitian société anonyme with its seat in Haiti and negotiate the convention with the State, including fiscal terms, stabilization and dispute resolution.
- Get written BME authorization before exporting any bulk sample for testing.
Common traps
- The decree has no production sharing or modern petroleum contract model. Everything commercial, from royalty to cost recovery, has to be negotiated into the convention.
- Research permits cannot be assigned or transmitted (art. 48), so a farm in partner cannot take a direct interest in the permit.
- Missing the 6 month start deadline cancels the research permit with no refund (art. 48).
- The BME itself says the HTG 50 per km2 research fee needs updating, so expect fee changes in any new law.
- From the research stage, a foreign company needs a Haitian société anonyme with its seat in Haiti, which brings Haitian corporate, tax and audit obligations.
Sources
- Bureau des Mines et de l'Energie, loi sur les hydrocarbures and permit procedure (Décret du 3 mars 1976, art. 47 and 48)
- Bureau des Mines et de l'Energie, énergies fossiles ou conventionnelles (exploration record)
- Bureau des Mines et de l'Energie, Loi minière (art. 35 to 45)
- Code Fiscal, Le Moniteur Spécial N° 48-A of 30 September 2026 (Direction Générale des Impôts)
- Banque de la République d'Haïti, taux du jour (shows only the latest reference rate)
Related pages
- sectors/mining-titles-and-permits
- taxes/excise-duties
- entities/choosing-an-entity
- investing/investment-treaties-and-icsid
- /country/haiti/
- /calendar/
- Live dashboard
Related: Haiti country profile · live dashboard · central bank and release calendar · our posts on X