Last verified: 2026-11-15 · Status: Stable
Metallic mining in Haiti runs on a ladder of exclusive titles from the 1976 decree. You start with a prospecting permit (up to 100 km2, 2 years), then a research permit (up to 50 km2, 2 years plus two renewals) and an exploitation permit (up to 25 km2), which becomes a 25 year concession once commercial production starts. The fees per km2 are still in 1976 gourdes (HTG 10, 50 and 250 a year), so the real fiscal terms sit in a mining convention negotiated with the State and published in Le Moniteur. The BME accepts a Haitian société anonyme or a foreign company for the prospecting request, but its procedure then requires a Haitian société anonyme with its registered office in Haiti and a negotiated mining convention.
USD figures use HTG 130.5300 per US dollar, the Banque de la République d'Haïti reference rate for 30 September 2026 in its daily series (https://www.brh.ht/wp-content/uploads/Serie-taux-25-26.pdf, row 30-Sep-26). Conversions are for orientation only.
Key facts
| Maximum area of a mining prospecting permit | 100 km2Décret du 3 mars 1976, art. 35, as of 2026-11-15 · in force |
|---|---|
| Mining prospecting permit term (not renewable) | 2 yearsDécret du 3 mars 1976, art. 35, as of 2026-11-15 · in force |
| Annual mining prospecting permit fee | 10 HTG per km2Décret du 3 mars 1976, art. 35, as of 2026-11-15 · in force |
| Maximum area of a mining research permit | 50 km2Décret du 3 mars 1976, art. 37, as of 2026-11-15 · in force |
| Mining research permit term | 2 years, renewable twice for 2 years yearsDécret du 3 mars 1976, art. 37, as of 2026-11-15 · in force |
| Annual mining research permit fee | 50 HTG per km2Décret du 3 mars 1976, art. 37, as of 2026-11-15 · in force |
| Annual mining exploitation permit fee | 250 HTG per km2Décret du 3 mars 1976, art. 39, as of 2026-11-15 · in force |
| Deadline to start work after a prospecting or research permit is granted | 3 monthsDécret du 3 mars 1976, art. 35 and 37, as of 2026-11-15 · in force |
The rule
Cost to do it: HTG 10 per km2 per year, paid in advance for the full term: a 100 km2 permit costs HTG 2,000 for 2 years (US$15.32).
Example: 100 km2 x HTG 10 x 2 years = HTG 2,000 / US$15.32Décret du 3 mars 1976 encourageant la prospection minière sur toute l'étendue du territoire et adaptant les structures juridiques existantes aux réalités de l'industrie minière (Le Moniteur No. 19 of 8 March 1976), art. 35, 1976-03-03 official text · verified 2026-11-15
Cost to do it: HTG 50 per km2 per year in advance: a 50 km2 permit costs HTG 2,500 a year (US$19.15).
Example: 50 km2 x HTG 50 = HTG 2,500 a year / US$19.15Décret du 3 mars 1976 encourageant la prospection minière sur toute l'étendue du territoire et adaptant les structures juridiques existantes aux réalités de l'industrie minière (Le Moniteur No. 19 of 8 March 1976), art. 36 and 37, 1976-03-03 official text · verified 2026-11-15
Cost to do it: HTG 250 per km2 per year: a 25 km2 permit costs HTG 6,250 a year (US$47.88).
Example: HTG 6,250 / US$47.88Décret du 3 mars 1976 encourageant la prospection minière sur toute l'étendue du territoire et adaptant les structures juridiques existantes aux réalités de l'industrie minière (Le Moniteur No. 19 of 8 March 1976), art. 38 and 39, 1976-03-03 official text · verified 2026-11-15
| Title | Max area | Term | Annual fee | Transferable | How you get it |
|---|---|---|---|---|---|
| Prospecting permit | 100 km2 | 2 years, not renewable | HTG 10 per km2 (US$0.08) | No | Application to the BME (art. 35) |
| Research permit | 50 km2, inside the prospecting area | 2 years, renewable twice for 2 years | HTG 50 per km2 (US$0.38) | No | Automatic if prospecting obligations are met (art. 36) |
| Exploitation permit | 25 km2, inside the research area | Until commercial production | HTG 250 per km2 (US$1.92) | Yes, with prior authorization (art. 31) | Automatic if the research report is filed (art. 38) |
| Mining concession | Inside the exploitation area; 100 km2 cap per holder | 25 years, renewable for 10 year periods | HTG 250 per km2 (US$1.92) | Yes, with prior authorization (art. 31) | Automatic conversion at commercial production; instituted by law or decree with the convention (art. 40, 44) |
The metallic mining title ladder (Décret du 3 mars 1976; USD at HTG 130.5300, BRH reference rate of 30 September 2026)
| Decree | Subject |
|---|---|
| Décret du 3 mars 1976 (Le Moniteur No. 19 of 8 March 1976) | Titles, eligibility, mining convention, holders' duties, transfers, closed zones and relations with landowners |
| Companion decree | 10 percent levy for INAREM on all amounts collected in its field |
| Companion decree | 25 cents per m3 levy on quarry material and river sand for INAREM |
| Companion decree | Purchase of alluvial gold entrusted to INAREM |
What the BME calls the Haitian mining code (four decrees of March 1976, as listed on the BME site)
Worked example
- A junior explorer takes a 100 km2 prospecting permit, then a 50 km2 research permit renewed twice, then a 25 km2 exploitation permit. State fees under the decree: prospecting 100 x HTG 10 x 2 years = HTG 2,000; research 50 x HTG 50 x 6 years = HTG 15,000; exploitation 25 x HTG 250 = HTG 6,250 a year. Total fees over the 8 years before exploitation are HTG 17,000 (US$130.24). The economics of the project are set by the mining convention, not by these fees.
- The same explorer misses the 3 month deadline to start work on its research permit. Under art. 37 (d), the permit is cancelled automatically and the fees paid in advance are not refunded, which also breaks the automatic path to an exploitation permit.
Step by step
- Check the BME potential maps and the mining cadastre unit for open ground, then send the BME a prospecting request with a georeferenced site map (WGS 84 UTM).
- File the company documents: articles and bylaws, board composition, technical references and CVs, and 2 years of consolidated financial statements; name an experienced geologist as the BME contact.
- On grant, pay the fees for the full term in advance and start work within 3 months (art. 35).
- Before the prospecting permit expires, file the detailed report and the research permit request with the list of target substances (art. 36, 37).
- Following the order of the BME procedure, after the prospecting report set up or convert to a Haitian société anonyme with its registered office in Haiti and negotiate the mining convention with the State (art. 21).
- File the final research report to obtain the exploitation permit, then the feasibility study; plan the law or decree that institutes the concession and convention (art. 38 to 44).
- Keep tax filings current: a formal payment demand can block the grant of an exploitation title or concession (Code Fiscal art. 329).
Common traps
- The fees are 1976 amounts. The BME notes they were set when US$1 equalled HTG 5 and should be updated under the draft new mining law, so model the convention terms, not the decree fees.
- Prospecting and research permits cannot be transferred, leased or mortgaged (art. 35, 37). Farm ins and joint ventures at those stages must be structured at the level of the holder's shares or by contract, not by assigning the permit.
- No mining title can be mortgaged, including exploitation permits and concessions (art. 39, 41). Lenders need other security.
- The financial clauses of the convention are subject to periodic review during the concession (art. 43), so stabilization must be negotiated expressly.
- Missing the 3 month start deadline cancels the permit with no refund (art. 35, 37), and only force majeure that is duly established stops the clock.
- The 100 km2 concession cap applies per holder (art. 42), so plan group structures with that limit in mind.
Sources
- Bureau des Mines et de l'Energie, Loi minière (Décret du 3 mars 1976, art. 35 to 45), archived copy of 14 July 2026, text identical to the live bme.gouv.ht page on 17 November 2026
- Bureau des Mines et de l'Energie, procédure d'octroi de permis de substances métalliques, archived copy of 14 July 2026, text identical to the live bme.gouv.ht page on 17 November 2026
- Code Fiscal, Le Moniteur Spécial N° 48-A of 30 September 2026 (Direction Générale des Impôts)
- Banque de la République d'Haïti, série des taux de change 2025 to 2026 (row 30-Sep-26)
Related pages
- sectors/oil-and-gas-exploration
- entities/choosing-an-entity
- taxes/corporate-income-tax
- taxes/property-taxes
- investing/investment-treaties-and-icsid
- /country/haiti/
- /calendar/
- Live dashboard
Related: Haiti country profile · live dashboard · central bank and release calendar · our posts on X
Get rule changes weekly
Free. One email a week from The LatAm Thread.
One more step after you press the button: we take you to Substack, where your email is already filled in. Confirm there to start. No spam, unsubscribe anytime, we never share your address. By subscribing you agree to the privacy policy.