Environmental impact authorization in Mexico: which projects need SEMARNAT approval, MIA modalities, review terms, public consultation and 2026 fees
Last verified: 2026-10-26 · Status: Stable
Projects in thirteen federal categories, from pipelines, energy, mining, chemicals and cement to coastal real estate and works in protected areas, need a prior environmental impact authorization from the Ministry of Environment (SEMARNAT) before any work starts. Most file an environmental impact statement (MIA) in particular or regional modality, decided within 60 days, extendable by up to 60 more, with possible suspension of up to 60 days for clarifications; low impact projects covered by standards or authorized industrial parks file a lighter preventive report decided in 20 days. Federal fees in 2026 run from MXN 17,975 for a preventive report to MXN 189,771 for a high complexity regional MIA, and working without authorization risks fines, closure and permit revocation.
USD conversions use MXN 18.6638 per US dollar, the US Federal Reserve H.10 noon buying rate in New York for 23 October 2026 (FRED series DEXMXUS), the latest observation available when this page was verified. Peso amounts set in UMA use the 2026 daily UMA of MXN 117.31, in force since 1 February 2026 (INEGI publication in the DOF of 9 January 2026, as cited in IMSS Technical Council agreement ACDO.AS2.HCT.270126/9.P.DIR). Conversions are for orientation only.
Key facts
| Maximum extension of the MIA review term in complex projects | 60 daysLGEEPA art. 35 BIS, as of 2026-10-26 · in force |
|---|---|
| Term for SEMARNAT to decide whether a preventive report suffices | 20 daysLGEEPA art. 31, as of 2026-10-26 · in force |
| Federal duty for a preventive report, 2026 | 17975.34 MXNLFD art. 194-H, section I, as of 2026-10-26 · in force |
| Federal duty for a particular MIA, high grade, 2026 | 145021.5 MXNLFD art. 194-H, section II c), as of 2026-10-26 · in force |
| Federal duty for a regional MIA, high grade, 2026 | 189771.14 MXNLFD art. 194-H, section III c), as of 2026-10-26 · in force |
| Maximum LGEEPA administrative fine (days of minimum wage read as UMA) | 50000 UMALGEEPA art. 171, section I, as of 2026-10-26 · in force |
| Notice deadline for emergency works started without evaluation | 72 hoursReglamento EIA art. 7, as of 2026-10-26 · in force |
The rule
Cost to do it: Environmental consultants prepare the study; the federal fee depends on the modality (see the fee rule).
Example: A solar plant on former farmland in an arid zone needs a federal authorization both as an electricity industry project and for the land use change. / A US developer building a beach resort that affects dunes or mangroves needs a federal MIA under sections IX and X, plus municipal construction permits.Ley General del Equilibrio Ecológico y la Protección al Ambiente (LGEEPA), DOF 28 January 1988, art. 28 reformed DOF 23 February 2005, last reform DOF 19 January 2026; Reglamento en materia de evaluación del impacto ambiental, DOF 30 May 2000, last reform DOF 31 October 2014, LGEEPA arts. 28 and 33; Reglamento art. 5, 2005-02-23 official text · verified 2026-10-26
Cost to do it: Preventive report fee: MXN 17,975.34 (about USD 963), far below a regional MIA.
Example: An auto parts plant inside an authorized industrial park can usually file a preventive report rather than a full MIA (art. 31, section III). / A 600 hectare shrimp farm must file a regional MIA because it exceeds 500 hectares.LGEEPA arts. 30 and 31 (reformed DOF 13 December 1996); Reglamento arts. 9 to 11, LGEEPA arts. 30 and 31; Reglamento arts. 10 and 11, 1996-12-13 official text · verified 2026-10-26
Cost to do it: Newspaper publication of the extract is at the developer's cost; budget consultant time for clarifications.
Example: An MIA filed on 1 February with no clarifications should be decided about 60 days later; with a 60 day suspension and a 60 day extension, the outer term is about 180 days. / On a USD 200 million plant, plan the EIA as a critical path item of roughly two to six months after filing, plus preparation of the study.LGEEPA arts. 34, 35 and 35 BIS (reformed and added DOF 13 December 1996); Reglamento arts. 46 and 51, LGEEPA arts. 34, 35 and 35 BIS; Reglamento arts. 46 and 51, 1996-12-13 official text · verified 2026-10-26
Cost to do it: Modification request fee MXN 12,952.55 (about USD 694); exemption request fee MXN 5,941.17 (about USD 318).
Example: Replacing a boiler with one of the same capacity in an authorized cement plant only needs prior notice; adding a new kiln line needs a new evaluation. / Buying a project with an MIA authorization requires notifying the change of holder (Reglamento art. 49).Reglamento LGEEPA en materia de evaluación del impacto ambiental, Arts. 6, 7, 28 and 49, 2000-05-30 official text · verified 2026-10-26
Cost to do it: From MXN 17,975.34 (USD 963) to MXN 189,771.14 (USD 10,168) per filing.
Example: A particular MIA for a chemical plant using highly risky substances, outside protected areas and with no forest land, scores 1+1+3 = 5, medium grade: fee MXN 96,680.23. / About USD 5,180.Ley Federal de Derechos, art. 194-H; Resolución Miscelánea Fiscal para 2026, Annex 4, DOF 28 December 2025, LFD art. 194-H, sections I, II, III, VI and VIII, 2025-12-28 official text · verified 2026-10-26
Cost to do it: Fine range: MXN 3,519.30 to MXN 5,865,500 (about USD 189 to USD 314,271), up to three times for repeat offences.
Example: Starting earthworks for a coastal development before the MIA is granted can lead to closure of the site and a fine of up to MXN 5,865,500, plus the duty to repair the damage. / Up to about USD 314,271, or about USD 942,814 for a repeat offence.LGEEPA art. 171 (reformed DOF 31 December 2001 and 1 June 2012); decree on deindexation of the minimum wage, DOF 27 January 2016, transitory Third, LGEEPA art. 171; deindexation decree transitory Third, 2012-06-01 official text · verified 2026-10-26
| Filing | Grade | MXN 2026 | About USD |
|---|---|---|---|
| Preventive report | MXN 17,975.34 | USD 963 | |
| Particular MIA | Minimum (score 3) | MXN 48,338.98 | USD 2,590 |
| Particular MIA | Medium (5 to 7) | MXN 96,680.23 | USD 5,180 |
| Particular MIA | High (9) | MXN 145,021.50 | USD 7,770 |
| Regional MIA | Minimum (score 3) | MXN 63,258.58 | USD 3,389 |
| Regional MIA | Medium (5 to 7) | MXN 126,514.87 | USD 6,779 |
| Regional MIA | High (9) | MXN 189,771.14 | USD 10,168 |
| Modification of an authorized project | MXN 12,952.55 | USD 694 | |
| Exemption request (Reglamento art. 6) | MXN 5,941.17 | USD 318 |
Environmental impact duties in 2026 (LFD art. 194-H; RMF 2026 Annex 4; USD at MXN 18.6638)
| Step | Term |
|---|---|
| File integration | 10 days |
| Preventive report decision | 20 days |
| MIA decision | 60 days from receipt |
| Suspension for clarifications | Up to 60 days |
| Extension in complex projects | Up to 60 days, once |
| Exemption or modification ruling | 10 days |
Review terms (LGEEPA arts. 31, 35 and 35 BIS; Reglamento arts. 6, 28 and 46)
Worked example
- A foreign investor plans a 150 MW wind farm on rangeland. It is an electricity industry project (LGEEPA art. 28, section II) and, if it removes forest vegetation, a land use change (section VII). Not in a protected area, with forest land use change and no highly risky substances, it scores 1+3+1 = 5 and pays the medium particular MIA duty of MXN 96,680.23, about USD 5,180 (LFD art. 194-H). SEMARNAT has 60 days to decide; a clarification request can suspend the term up to 60 days and a complex case can add 60 more, so the investor schedules site works at least six months after filing, and separately obtains state and municipal permits (art. 33).
Step by step
- 1. Screen the project against the thirteen categories of LGEEPA art. 28 and the detailed list in Reglamento art. 5, and check state rules for projects outside federal scope.
- 2. Decide whether a preventive report is enough (standards, evaluated plan or authorized industrial park) or an MIA is needed, and whether it is regional or particular.
- 3. Hire an environmental consultant; add a risk study for highly risky activities (LGEEPA art. 30).
- 4. Pay the LFD art. 194-H duty at the 2026 amount and file; publish the newspaper extract within 5 days if a consultation is requested.
- 5. Answer clarifications fast, since they suspend the term; negotiate conditions and guarantees.
- 6. After authorization, notify start and completion of works, comply with conditions and notify any change of holder.
Common traps
- Starting site clearing before authorization: closure, fines of up to 50,000 UMA and repair duties follow (LGEEPA art. 171; Federal Environmental Liability Law).
- Assuming a federal MIA covers everything: it does not bind state or municipal authorities (LGEEPA art. 33).
- Modifying an authorized project without telling SEMARNAT: changes must be submitted for a 10 day ruling (Reglamento art. 28).
- Underestimating consultation: any community member can trigger a public consultation, and comments are recorded in the resolution (LGEEPA art. 34).
- Letting the authorization lapse: it lasts only for the proposed execution time (Reglamento art. 49).
Sources
- Ley General del Equilibrio Ecológico y la Protección al Ambiente, Chamber of Deputies consolidated text (last reform DOF 19 January 2026)
- LGEEPA, copy of the Chamber of Deputies text consulted
- Reglamento de la LGEEPA en materia de evaluación del impacto ambiental, Chamber of Deputies text (last reform DOF 31 October 2014)
- Reglamento EIA, copy consulted
- Ley Federal de Derechos, Chamber of Deputies text
- Resolución Miscelánea Fiscal para 2026, Annex 4 (DOF 28 December 2025), SAT
- Constitution, deindexation decree DOF 27 January 2016 (transitory Third), Chamber of Deputies text
- IMSS Technical Council agreement citing the 2026 UMA of MXN 117.31 (INEGI, DOF 9 January 2026)
- US Federal Reserve H.10 via FRED, Mexican pesos per US dollar (DEXMXUS)
Related pages
- regulation/overview
- regulation/environmental-liability-and-contaminated-sites
- regulation/hazardous-waste-and-circular-economy
- regulation/climate-change-and-emissions-reporting
- sectors/electricity-generation-and-power-market
- sectors/mining-concessions
- real-estate/land-use-and-urban-planning
- /country/mexico/
- /calendar/
- Live dashboard
Related: Mexico country profile · live dashboard · central bank and release calendar · our posts on X