Countries › Uruguay › Guide › 13. Regulation › Environmental impact authorization in Uruguay
Environmental impact authorization in Uruguay
Last verified: 2026-10-27 · Status: Stable
Listed projects, from roads and ports to power plants above 10 MW, industrial plants over one hectare, urban developments over 10 hectares and works in the coastal strip, need a prior environmental authorization (AAP) from the Ministerio de Ambiente before any works start. The developer communicates the project, the Ministry classifies it as A, B or C within 10 business days (40 for sensitive sites), and categories B and C need an impact study, a 20 business day public review and, for C, a public hearing; the Ministry then has 120 days, and silence means denial. Many plants also need an operating authorization renewed every three years, and building without the AAP is a serious infraction with fines up to 50,000 UR (about US$2.4 million).
USD figures use UYU 40.210 per US dollar, the BCU quotation for DLS. USA BILLETE on 27 October 2026; amounts in Unidades Indexadas (UI) use UYU 6.6792 per UI, the BCU quotation for 27 October 2026, both retrieved from the BCU quotations service on 27 October 2026. Amounts in Unidades Reajustables (UR) use UYU 1,940.77 per UR, the value fixed by Decreto 229/026 (IMPO lists it as the latest UR, in force for September 2026). Conversions are rounded and for orientation only.
Key facts
| Deadline to classify a project (A, B or C) | 10 business daysDecreto 349/005 art. 6 (Decreto 416/013), as of 2026-10-27 · in force |
|---|---|
| Classification deadline for sensitive projects with site study | 40 business daysDecreto 349/005 art. 21, as of 2026-10-27 · in force |
| Public review of the summary environmental report | 20 business daysDecreto 349/005 art. 15, as of 2026-10-27 · in force |
| Deadline to decide the prior environmental authorization | 120 daysDecreto 349/005 art. 18, as of 2026-10-27 · in force |
| Effect of silence on the authorization request | Deemed denial Decreto 349/005 art. 18, as of 2026-10-27 · in force |
| Public hearing | Mandatory for category C Decreto 349/005 art. 16, as of 2026-10-27 · in force |
| Environmental operating authorization renewal | 3 yearsDecreto 349/005 art. 23, as of 2026-10-27 · in force |
| EIA required for industrial plants with industrial area above | 1 hectaresDecreto 349/005 art. 2 num. 19, as of 2026-10-27 · in force |
| EIA required for urban developments above | 10 hectaresDecreto 349/005 art. 2 num. 24, as of 2026-10-27 · in force |
| EIA required for transmission lines of | 150 kV or moreDecreto 349/005 art. 2 num. 18, as of 2026-10-27 · in force |
| Government fee for the prior environmental authorization | None set in Ley 16.466 or Decreto 349/005 Ley 16.466; Decreto 349/005, as of 2026-10-27 · in force |
The rule
Cost to do it: No authorization fee is set in Ley 16.466 or Decreto 349/005; cost is the study by qualified professionals and the publications.
Example: A 2 hectare food processing plant near Canelones exceeds the one hectare industrial threshold and needs an AAP before construction. / A US$60 million 40 MW solar park exceeds 10 MW and needs an AAP before groundbreaking.Ley Nº 16.466 (Environmental Impact Assessment), art. 6 and 7; Decreto Nº 349/005 (Regulation of Environmental Impact Assessment and Environmental Authorizations), art. 2 as amended, Ley 16.466 art. 6 and 7; Decreto 349/005 art. 2, 2005-09-21 official text · verified 2026-10-27
Cost to do it: No fee; professional time to prepare the communication and environmental sheet.
Example: A project communicated on 2 November 2026 must be classified by 16 November 2026, or the developer's own classification stands. / A foreign developer that proposes category A for a project the Ministry reclassifies as C faces a full study and a public hearing, adding months to the timetable.Decreto Nº 349/005, art. 3 to 8 (art. 6 inciso 1 as amended by Decreto Nº 416/013), Decreto 349/005 art. 3 to 8, 2013-12-19 official text · verified 2026-10-27
Cost to do it: Cost of the multidisciplinary study team and the signing professional; no official fee set.
Example: A Uruguayan quarry expansion classified B needs a sectoral study signed by a qualified geologist or engineer. / A foreign mining investor can keep its ore processing know how confidential by filing it in a separate document.Ley Nº 16.466 art. 12 and 15; Decreto Nº 349/005 art. 9 to 12 and 19, Decreto 349/005 art. 9 to 12 and 19, 2005-09-21 official text · verified 2026-10-27
Cost to do it: Publication costs of the notices (non official notices at least 7 cm by two columns) and hearing logistics; no official fee set.
Example: If the last newspaper notice appears on Friday 6 November 2026, the public review runs from 9 November to 4 December 2026 (20 business days), before the 120 day decision clock matters. / A US$200 million port terminal classified C should plan for a public hearing and up to 120 days for the decision after a complete file, with silence meaning denial, not approval.Ley Nº 16.466 art. 13, 14 and 16; Decreto Nº 349/005 art. 15 to 18, Decreto 349/005 art. 15 to 18, 2005-09-21 official text · verified 2026-10-27
Cost to do it: Cost of a site selection and alternatives study; no fee set.
Example: A planned industrial park in Paysandú must file its site study and wait up to 40 business days for a viability statement. / A foreign energy company comparing two sites for a 100 MW plant should present both; a non viable site is ruled out before the full study.Decreto Nº 349/005, art. 20 to 22 (art. 20 as amended by Decreto Nº 162/014), Decreto 349/005 art. 20 to 22, 2014-06-04 official text · verified 2026-10-27
Cost to do it: Cost of renewal studies and management plans every three years; no fee set in the decree.
Example: A Uruguayan cement plant authorized in 2023 must renew its AAO by 2026 and again in 2029. / A foreign owned free zone operator should calendar AAO renewals every three years in its compliance plan.Decreto Nº 349/005, art. 23 to 25 (art. 23 as amended by Decreto Nº 162/014, 271/018 and 368/018); Ley Nº 16.466 art. 17, Decreto 349/005 art. 23 to 25, 2018-11-05 official text · verified 2026-10-27
Cost to do it: Fines from 10 UR (about UYU 19,408, US$483) to 50,000 UR (about UYU 97,038,500, US$2.41 million).
Example: A developer who starts earthworks for a 15 hectare gated community before the AAP commits a serious infraction and the landowner is jointly liable. / For a foreign investor the maximum fine is about US$2.41 million, but suspension of works and joint liability of landowners are the larger risk.Decreto Nº 349/005 art. 29; Ley Nº 16.466 art. 8 and art. 11 as reworded by Ley Nº 19.924 art. 521; Ley Nº 16.112 art. 6 as reworded by Ley Nº 19.535 art. 168; Ley Nº 19.889 art. 291 and 293, Decreto 349/005 art. 29; Ley 16.466 art. 8 and 11; Ley 16.112 art. 6; Ley 19.889 art. 293, 2020-07-09 official text · verified 2026-10-27
| Step | Term | Source |
|---|---|---|
| Project communication and proposed category | Before any works | Decreto 349/005 art. 4 |
| Classification (A, B, C) | 10 business days; silence confirms the proposal | art. 6 |
| Classification for sensitive projects with site study | 40 business days | art. 21 |
| Impact study and AAP request (B and C) | Developer's timing | art. 9 to 12 |
| Public review | 20 business days after last notice | art. 15 |
| Public hearing | Mandatory for C | art. 16 |
| Decision | 120 days, suspended for information requests; silence is denial | art. 18 |
| Operating authorization | Before operation, renewed every 3 years | art. 23 and 24 |
Procedure and timeline
| Activity | Threshold |
|---|---|
| Power plants | More than 10 MW, any source |
| Transmission lines | 150 kV or more |
| Industrial plants | More than 1 hectare of industrial area, or foundries of 50 t/year or more, or hazardous chemicals |
| Urban developments | More than 10 hectares, or near existing towns |
| Solid waste plants and landfills | 10 t/day or more |
| Sewage plants | Serving more than 10,000 people |
| Pipelines | More than 10 km |
| Dams | More than 2 million m3 or 100 ha of water surface |
| New forest plantations | More than 100 ha in one holding |
Selected thresholds (Decreto 349/005 art. 2)
Worked example
- Wind farm timeline: a 50 MW wind project is communicated with a site study on 2 November 2026. Classification takes up to 40 business days, to early January 2027 (Decreto 349/005 art. 21). If classified B, the sectoral study is filed, say, in March 2027; after the 20 business day public review and up to 120 days of review, the AAP can be expected in the third quarter of 2027, and operation then needs an AAO renewed every three years.
- Fine exposure: starting construction without an AAP is a serious infraction (art. 29 a), with fines up to 50,000 UR, about UYU 97,038,500 or US$2.41 million (Ley 16.112 art. 6), plus suspension of works by the Executive (Ley 16.466 art. 8).
- Category A route: a small project that the Ministry confirms as category A within 10 business days receives the AAP without a study, possibly subject to mitigation conditions (Decreto 349/005 art. 6 and 8).
Step by step
- Check the activity and size against Decreto 349/005 art. 2 early in project design.
- For sensitive projects, prepare a site selection study with alternatives and file a copy with the departmental government.
- Communicate the project with a realistic proposed category, signed by a qualified professional.
- For categories B and C, commission the impact study covering construction, operation and abandonment, and separate any trade secrets.
- Publish the notices, manage the 20 business day public review and, for C, the public hearing.
- Do not start works before the AAP; build the 120 day decision term (with silence as denial) into financing and construction contracts.
- Before operating, obtain the AAO and calendar its renewal every three years.
Common traps
- Silence on the AAP request is a denial, not an approval; only the classification step has positive silence.
- Proposing too low a category can backfire if the Ministry reclassifies the project.
- Landowners and professionals in charge are jointly liable for unauthorized works, so lenders and landlords should check the AAP.
- The AAP sets its own validity period; delays in starting works can make it lapse.
- Many projects need a second authorization (AAO) to operate, renewed every three years.
- Departmental permits and land use rules apply in addition to the national environmental authorization.
Sources
- IMPO, Ley Nº 16.466 (consolidated)
- IMPO, Decreto Nº 349/005 regulation text (consolidated)
- IMPO, Ley Nº 16.112 art. 6 (environmental fines)
- IMPO, Ley Nº 19.889 art. 291 (Ministerio de Ambiente)
- IMPO, Ley Nº 19.889 art. 293
- IMPO, UR values table
Related pages
- regulation/regulatory-compliance-essentials
- regulation/environmental-liability-and-waste
- sectors/electricity-generation-and-wholesale-market
- sectors/large-scale-mining
- real-estate/coastal-defense-strip
- real-estate/zoning-subdivision-and-building-permits
- investing/industrial-and-technology-parks
- /country/uruguay/
- /calendar/
- Live dashboard
Related: Uruguay country profile · live dashboard · central bank and release calendar · our posts on X